0ps_c04

I am using the business content for populating 0ps_c04 (Project system (controlling) cube) in BI7.  I have managed to install the cube, infosource, datasource etc, but cant seem to find any infopacakges and thus process chains.  Does anyone know wether they should be part of this or do I need to create them manually.  Is there a white papaer on how or what this cube does, as well as any other geric white papers on BI Finanace
Thanks
Edited by: Dominic Rowe on Jun 12, 2008 9:14 AM

Hi,
Infopackage and Process chain wont be a part of the Business content. You need to craete this manually.
Regarding this cube 0ps_c04 :
http://help.sap.com/saphelp_nw70/helpdata/EN/17/416d030524064cb2b8d58ffb306f3a/frameset.htm
Thanks...
Shambhu

Similar Messages

  • Error while activating the infoprovider 0PS_C04 from BI content

    Hi,
    We are trying to activate Infoprovider 0PS_C04 from BI content and getting following error. We have applied OSS Note 493422 and also tried several options by granting appropriate authorizations to the RFC user BID_CUA_200 being used for the extractors.  However, we are still getting following error message. Unfortunately we have been experiencing this problem for most of the Infoobjects
    Kindly throw some light on this please. I will certainly reward full points.
    Best Regards
    Venkat. P
    "Error when creating transfer structure /BIC/CCBA0CURTYPE_TEXT in source system ECDCLNT200
    Message no. R3104
    Diagnosis
    An error occurred when creating transfer structure /BIC/CCBA0CURTYPE_TEXT as an IDoc segment in source system ECDCLNT200 .
    System Response
    The action was terminated. No data was changed.
    Procedure
    Use the generation log in source system ECDCLNT200 to identify the error, and remove the cause.

    And also check whether there are any dumps in ST22.
    Khaja

  • Jumping from BW 0PS_C04 to SAP R/3 PS

    Hi Folks,
    We are seeking help to resolve a Report to Report Interface problem. Users are able to jump to R/3 CO/CCA, but not to R/3 PS. The following behaviour is observed when a query created against 0PS_C04 attempts a jump or Goto - CJ74. First warning message states that 0DOC_DATE cannot be uniquely assigned. Second warning message states that 0PSTNG_DATE cannot be uniquely assigned. The third and final message states that 'You cannot use the report-report interface to call up report RKPEP000.
    Please, advise of potential fix or resolution.
    Thanks and regards,
    Cassio Bastos

    Hi!
    Did you find solution? I have the same problemm just other report and fields
    4nx in advance

  • ANEP-ANBTR FIELD ADDITION IN 0PS_C04

    Hi All,
    I am working with 0PS_C04 cube and have developed a CAPEX report on top of it.
    Now further enhancement is required and i need to add a column based Asset Line Item ( ANEP table).
    I need to fetch values of field ANBTR from ANEP.
    Is there a standard datasource that i could use to fetch these values ???
    Thanks a lot.
    Regards,
    Rohit

    Datasource associated to table ANEP
    FI-AA: Transactions -  0FI_AA_11
    http://help.sap.com/saphelp_nw70/helpdata/en/a4/f4153c4eb5d82ce10000000a114084/frameset.htm
    The field ANBTR is present in the Above data source
    BW_ANSBW_T - Acquisition value for transactions - ANEP -- ANBTR
    There is no need to enhance the DS.
    For your info
    if you want to enhance the DS, check the below link
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/302d4b15-5847-2a10-93bb-9c45d9f06b16?quicklink=index&overridelayout=true
    Create a MP on the top of the 0PS_c04 and target on the above DS - create a report on the top of this MP.
    Edited by: prashanthk on Sep 17, 2010 11:26 AM
    Edited by: prashanthk on Sep 17, 2010 11:28 AM

  • Data Sources for "0PS_C04"

    Hi There,
    I am installing 0PS_C04, but unable to figure out which data sources to be used? I have the list of data sources below :-
    0CO_OM_OPA_1   Internal Orders Costs
    0CO_OM_OPA_3   Internal Orders Overall Annual Plan Values
    0CO_OM_OPA_6   Internal Orders Actual Costs Using Delta Extraction
    0CO_OM_NTW_1   Network Costs
    0CO_OM_NTW_2   Networks Actual Costs Using Delta Extraction
    0CO_OM_NWA_1   Network Activities Costs
    0CO_OM_NWA_2   Network Activities Actual Costs Using Delta Extraction
    0CO_OM_NAE_1   Network Activity Element Costs
    0CO_OM_NAE_2    Network Activity Elements Actual Costs Using Delta Extraction
    0CO_OM_WBS_5   WBS Elements Accrual Calculations
    0CO_OM_WBS_2   WBS Element Budget
    0CO_OM_WBS_1   WBS Elements Costs
    0CO_OM_WBS_4   WBS Elements Statistical  Key Figures
    0CO_OM_WBS_3   WBS Elements Overall Plan     
    0PS_CSH_NWA     Payments in Network Activities
    0PS_CSH_NTW     Network Payments
    0PS_CSH_WBS     Payments in WBS Elements
    0CO_OM_WBS_6   WBS Elements: Actual Costs Using Delta
    Few of these are the delta datasources but simultaneously few are full uploads. Please suggest me on the same.
    Thanks and Regards,
    Sangini Mathur

    Thanks Manjunath,
    That is fine, for example I have a datasource 0CO_OM_WBS1 to 0CO_OM_WBS6 which seems to be repetitive with delta funtionalities incorporated. I want to saagrigate these...
    I have master data source like "0WBS_INH_ATTR - Inheritance Data for WBS Elements" and "0WBS_ELEMT_ATTR - Work Breakdown Structure Element (WBS Element)" which one to use as I need to have those User defined fields also which is not there in wbs_attr data source but in inheritance data source, but few fields are there in wbs_attr data source but not in inheritance data source.
    Thanks for the reply,
    Sangini.

  • 0PS_C04 (CONTROLLING)  aggregate level

    Hi,
    I want to know if it's posible make to these extrators:
    0PS_CSH_NWA:     Payments in Network Activities
    0PS_CSH_NTW:     Network Payments
    0PS_CSH_WBS: Payments in WBS Elements
    More aggregate level, adding the doc_item field to them.
    That it's posible? Or we have to make another extractors?
    Thanks for your help.
    Victoria

    Check :
    0CCA_C11 Delta and Full upload datasources.
    0PS_C04 controlling - from which whcih data source should fill this cube
    /thread/664877 [original link is broken]

  • 0PS_C04 - What datasource to use for plan values entered via t-code CJR2

    We are using standard 0PS_C04 with all the recommended InfoSources.
    We use t-code CJR2 in ECC to enter plan for the WBS elements.  That said, I chacked to see whether 0CO_OM_WBS_2 or 0CO_OM_WBS_3 pulls these records, and it does not.  0CO_OM_WBS_3 is pulling from t-code CJ40.
    Hence, how could I bring the values from CJR2 or report S_ALR_87013542 into PS_C04 of BW 3.1?
    I also noticed that using 0CO_OM_WBS_6 only brings in actuals where valuetype=10.  We need to bring in value type=20 and version=0.
    Please help!!!

    Hi,
    you'll find Project cost plan  in tables RPSCO / COSP
    regards Andreas

  • R/3 data Not matching 0PS_C04 cube

    hello guys, we had an oracle upgarde last week and "apprently after the upgarde the data in this cube isn't matching the data in r/3". first i thought may be the data in the cube was inaccurate, so
    1) i cleaned the cube reloaded all the data accordingly, but it seems the error still existed.
    2) Cleared the cube again and reloaded all the data from masters tables, to make sure nothing was missed
    PROBLEM STILL persists,
    Any suggestions?

    Hi,
    U r talking of which Data inconsistency,, is it Project and WBS element Data. If So, There exist Conversion Exit of Project and WBS element Data.
    try these Following Conversion Exits in R/3 and then c how the Data gets changed
    CONVERSION_EXIT_ABPRJ_INPUT    Converts External Project Number to Internal Project Number (Definitio
    CONVERSION_EXIT_ABPRJ_OUTPUT   Converts Internal Project Number to External Project Number (Definitio
    CONVERSION_EXIT_ABPSN_INPUT    Format > Without Edition (Project Number / WBS Element Number)
    CONVERSION_EXIT_ABPSN_OUTPUT   Format > With Edition (Project Number / WBS Element Number)
    CONVERSION_EXIT_ABPSP_INPUT    Conversion External > Internal WBS Element Number
    CONVERSION_EXIT_ABPSP_OUTPUT   Conversion Internal > External WBS Element Number
    assign Points if helped
    Thanks

  • Added new attribute to WBS

    Here is my current issue.
    I added a "deleted indicator" to the WBS_ELEMT_ATTR on r/3, then created a new infoobject in BW (did not flag it w/master data) and added this new infoobject as a navigational attribute to the WBS_ELEMT infoobject in BW.
    Went to the infosource for WBS_ELEMT and added it to the transfer structure and the comm. structure. Activated it. Then reloaded the master data for WBS from r/3. Went to "Maintain Master Data" for WBS_ELEMT and I can see the new field is populated correctly in the new field I added to WBS_ELEMT.
    Then I went to the cube 0PS_C04 and marked the new attribute I added to WBS_EMEMT as a navigation attribute and re-activated it and the update rules.
    The problem is in the query and when viewing data with list cube or cube contents the field is blank. But its not blank with maintain master data for WBS_ELEMT.
    Does anyone have any clues as to my mistake or what I need to do. I'm needing to restrict a query based on 0PS_C04 by this new attribute I added to WBS.
    Will reward points as always.
    Richard

    Hey Richard,
    WBS_ELEMT is a navigational attribute in 0PS_C04 and "deleted indicator" is a navigational attribute of WBS_ELEMT. So, "deleted indicator" is a second level navigation attribute for 0PS_C04. This will not show you any data in the query even if you can see the data for this field in WBS_ELEMENT. One more thing is that in the update rules for 0PS_C04, you have mapped only WBS_ELEMENT but not "deleted indicator". Hence, the data is not displayed in the report.
    You can handle this in 2 different ways.
    1. Add "deleted indicator" to the cube directly and map it all the way down to the data source.
    2. Add the "deleted indicator" to the cube and in the update rules, map it as an attribute of WBS_ELEMENT.
    Unless it is mapped to the cube from the comm structure in the update rules, you can not see the data in the report.  Try one of these and let us know if it works.
    Thanks and Regards
    Subray Hegde

  • Inventory Management and WBS?

    Hi there,
    We want to show an inventory management report which contains WBS Hierarchy. It shall look like the following style:
    Dimension     Fact Stock Value
    FKSTL
    ->PROJECT
     ->WBS
      ->MATNR    xxx,xxx,xxx
    I have activate two InfoCubes, 0IC_C03 and 0PS_C04. What can I do to show the report like that?
    Thanks in advance

    Hi
    Have you uploaded the hierarchy for FKTSL and include this infoobject in your cube......you can execute the report to drilldown based on the hierarchy
    Hope this helps
    Cheers
    N Ganesh

  • Mismatch in PS reports BW vs R3 Standard reports

    hello Gurus,
    I have loaded the 0PS_C04 (Controlling) for PS.
    The Budget data comapared to R3 figures are matching perfectly.
    Bu the Actual Cost show big difference. The R3 data using tcode:S_ALR_87013558 shows a very different Actual Cost.
    The report in BW is the standard report WBS Elements:0PS_C04_Q0004
    I tried filtering on Valuation View,Vtype,0metype etc....
    Is there any config setting in R3 for PS....
    This particular is coming in BW production data.
    In BW Dev the figures are right compared to R3 Quality server....
    thanks in advance.

    hi,
    I got similar problem in BW (Project systems) report on 0PS_C04.
    The Cost Plan and Revenue Plan data compared to R3 figures are matching perfectly. Bu the Actual Cost show big difference.  I am using sap delivered restricted key figures.
    Can any one please help me to match my Cost Actual and Revenue Actual with R/3 Data
    Thanks in Advance
    Rajesh

  • Plan Vs Actual report in PS

    Gurus,
    New in SAP PS module, appreciate your advice on the PS Plan Vs Actual cost reporting.
    What kind of standard extractor should we use in order to extract the Plan cost entered in PS?
    What kind of standard extractor shoud we use in order to extract the Plan cost enter?
    I would assum that we need to have to InfoCube where one will keep the actual and one will keep the plan cost?
    Then we build the multiprovider on top of this in order to report the Plan Vs Actual.
    Kindly advice, thanks!

    If I recall correctly, you can use 0PS_C04.
    This cube contains actuals, plan, commitments...
    Take a look at the business content for  this.

  • Trying to look Contents for a new custom InfoCube and giving ERRORS ?????

    Hi all,
        I have created a custom InfoCube (ZTEST_PS) in similar to 0PS_C04. When I try to look the Contents of this InfoCube through Manage --> Contents or Listcube Tcode option, it is giving the following warnings/errors for every attempt:
    1. Your user master record is not sufficiently maintained for object Company Code Hierarchy
    Diagnosis
    When checking your authorizations for object 'Company Code Hierarchy' (technical name: ZCOMPHIER) it was established that you do not have authorization in your user master record for this object (return code 12).
    Procedure
    How you continue depends on the return code. See the online documentation for ABAP language element "AUTHORITY-CHECK". Please note:
    With a return code of 12, the object 'Company Code Hierarchy' has not been maintained in the user master, meaning there is no profile in the user master record in which this authorization object has been entered. This is, however, absolutely necessary, as all of the authorization objects created in the development class RSR are validated in the 'and' link. If the authorization is missing for only one object, the request is rejected as unauthorized.
    Get the person responsible for your authorization to create you a profile containing authorization for object Company Code Hierarchy.
    2. System error: RSDRC / FORM AUTHORITY_CHECK USER NOT AUTHORIZED ZTEST_PS ZTEST_PS
    3. System error: RSDRC / FUNC RSDRC_BASIC_CUBE_DATA_GET ERROR IN RSDRC_BASIC_QUERY_DATA_GET ZTEST_PS 64
    Message no. DBMAN100
    4. System error: RSDRC / FORM DATA_GET ERROR IN RSDRC_BASIC_CUBE_DATA_GET ZTEST_PS 64
    When I try to run a query against this custom InfoCube, I am getting the same First Warning.
    How can I fix theses warnings/errors, PLEASE ?
    Thanks.

    Venkat,
    You dont have authorizations for the 'Company Code Hierarchy'ZCOMPHIER , you dont have authorizations.
    What you will have to do is ask the basis person to give you authorization for the Hierarchy , Or if you can ..switcg off authorization checks for the Cube in T-Code RSSM.
    Regards,

  • WBS Updates in R/3 not Key in BW

    In R3, POSID can be changed without impact to the WBS in R3, but with great impact to the WBS in BW, which understands the new POSID as a new WBS element. Only a full delete/load of both the WBS Master Data and Transaction Data into BW will keep the BW and R3 WBS records in full sync. This is not practical in the BW Production environment. Also, it would not be known when a user changes the POSID in R3, so full loads would need to be done daily to insure that all changes are captured. Again, not practical in Production.
    Although costs are often posted to Networks rather than to WBS elements, especially upper level WBS elements, “roll-up” of costs under a WBS is often a very common form of reporting in BW, especially for Project Managers. These WBS "roll-up" reports in BW would report costs on the previous POSID unless full replace of WBS Master and Transaction records were done between BW Report run times.
    Has anyone else run into this problem? One recommendation would be to change the current process with custom development. The "lowest impact" options in my opinion would be:
    Block the ability of the users to change the WBS POSID on the R3 side.
    Change the BW WBS Primary key from POSID to a concatenation of POSID/PSPNR, and create a Rule during BW WBS Extraction to check if the POSID for an existing PSPNR has changed – if yes, replace the POSID for the existing PSPNR with the new POSID name.
    Any thoughts?

    Here is a note from SAP on the WBS issue. According to Colm O'shea (SAP support) they are going to try and put a fix in the next plug-in upgrade. 
    New and extended interfaces for integrating SAP R/3, SAP R/3 Enterprise, and SAP ERP Central Component (SAP ECC) will no longer be delivered with their own add-on (SAP R/3 Plug-In).  As of SAP ECC 6.0, they will be contained directly in SAP ECC.
    PI 2004.1 is therefore the final separate delivered SAP R/3 Plug-In release.
    This means that:
    SAP ECC 6.0 and subsequent releases will automatically contain all integration interfaces that so far have been contained in the SAP R/3 Plug-In and that ensured the technical integration with other SAP Components.
    Customers who run SAP R/3 4.6C, SAP R/3 Enterprise 47x100 and 47x200, and SAP ECC 5.0 will receive additional integration interfaces in a Support Package for PI 2004.1 once a year. The delivery of this Support Package will be synchronized with that of mySAP Business Suite. The 2005 delivery is in November as part of Support Package 10. Information about the delievery from 2006 onwards are take place here
    This rule applies only for customers with a SAP R/3 Plug-In release PI 2004.1. Customers with PI 2003.1 or older must first upgrade to PI 2004.1 or SAP ECC 6.0.
    No new interfaces will be provided for integration between new SAP component releases and SAP R/3 3.1I to 4.6B.
    Number              739182
    Version             2 vom 25.05.2004
    Status              Released for Customer
    Set on             ,25.05.2004
    Language            EN
    Mastersprache       DE
    Short text          PSBW: Renaming PS objects
    Responsible         SAP AG
    Component           BW-BCT-PS
                        Project System
    Long text
    Symptom
    In the project system, you can rename the following objects: project
    definition, WBS element, network and network activity. In this case,
    only the external identifier of the objects is changed. The internal
    identifier (object number and Guid) is retained.
    In the BW content of the PS, the external identifier of the objects is
    stored in the cubes.
    If the objects in the source system are now renamed, the reference of
    the transaction data already loaded for this object disappears in BW,
    since this refers to the old external identifier.
    Other terms
    PSBW, 0PS_C01, 0PS_C02, 0PS_C03, 0PS_C04
    Reason and Prerequisites
    This is due to a design problem.
    Solution
    Currently the only solution is to load master data and transaction data
    again into BW.
    You can use the following authorizations to prevent renaming of the
    external identifier in the source system (in this case, activity '45' is
    responsible for renaming the external identifier):
        o  Project definition: C_PROJ_... authorization object
        o  WBS element: C_PRPS_... authorization object

  • Report-Report Interface from BW to Project Systems

    I'd like to jump from BW reports based on 0PS_C04 into the corresponding R/3 line items. If I specify CJ74 as the transaction target then run the BW report and choose the corresponding option from the 'GoTo' menu the following message is displayed. I find this very confusing -- it seems to be saying that the report behind the transaction cannot be used in the report-report interface, but in the procedure says always use the program in the report-report interface.
    Can anybody understand what the message is telling us? Can anyone tell me how to jump to an R/3 line item report from BW Project System cube?
    Thanks
    Robert Williams
      You cannot use the report-report interface to call up report RKPEP000                                                                               
    Message no. HF 800                                                                               
    Diagnosis                                                                               
    Line item report RKPEP000 is not suitable for the report/report        
          interface.                                                                               
    Procedure                                                                               
    Always enter RKPEP000 as the receiver report for project line items in 
          the report/report interface. This program uses the transfer parameters 
          to determine which line item reports can be accessed.

    Hi
    I dont know whether you have solved the problem or not yet
    But i came up with the same issue....
    Use interface program RKPBW000 instead of RKPEP000 in the RRI settings.
    OSS Note : 356166
    Thanks

Maybe you are looking for

  • Popups on firefox not being blocked

    Last week I had a problem accessing my earthlink webmail with random popups on my vista desktop. Did a system restore and then accessed the same webmail from my xp laptop without problem. System restore fixed the desktop problem until this morning. N

  • MS Active Directory (LDAP) and SAP Integration

    Hi all! don't know if I'm right here in this forum, but: I'm using MS Windows Server 2003 and installed Active Directory as LDAP-System on the one hand side, on the other I'm using a 6.20 ABAP Web AS. I'd like to synchronize the User Storage on these

  • Code to sort un-common elements in arrays

    the code which i made so far class ArraySetExample      public static void main (String [] args)           String rainbow [] = {"red","orange","yellow","green","blue","indigo","violet"};           String flag [] = {"red","white","blue"};           //

  • Upgrade SQL From the SQL Server 2000 to SQL Server 2008

    hello: I am running the following query. This query is based on SQL server 2008. POIShare is a view which is created by the table. "select PoiShare.AddressCode,REPLACE(PoiShare.NameSpell,' ','') as NameSpell,PoiShareOffset.Offset from PoiShare, PoiSh

  • Moving purchased movies out of ITunes.  Can I get them back again?