57F4 Challan in MIGO

Dear All,
When I refer the subcontracting challan in MIGO the system tends to accept all the challans which are not relavent to the purchase order.
Kindly help me if any setting is to be made to validate the P.O and the challan number.
Help in any form will be rewarded.
regards,
Arahanth

Dear All,
When I refer the subcontracting challan in MIGO the system tends to accept all the challans which are not relavent to the purchase order.
Kindly help me if any setting is to be made to validate the P.O and the challan number.
Help in any form will be rewarded.
regards,
Arahanth

Similar Messages

  • 57F4 challan while GR

    Hi friends,
    I have created the 57F4 challan wrt the 541 E doc...
    Then i have to do the MIGo for the good from Subcontractor.... my doubt is how the 57F4 challan related with this GR?
    regards,
    sathes

    Hi Vipin,
    I don't get you....
    first i wish tell what i did
    i have to issue my special stock to sub-contractor against the SB-PO which is created based on sales order....
    i did this through (MB1B; 541 E) transfer posting...  311 E is not for Sub contractor stock transfer posting, it is for location to location....
    now i have created 57F4 challan against the document 541 E....
    Then i have received the material from Sub contractor and need to do GR.  Here my question is how should i link this GR with 57F4 challan?
    regards,
    Sathes

  • 57F4 challan print - getting parent item no and po number for child item

    Hi ,
    In 57F4 challan, Subcontract components - i.e Child items are used for creating the challans.
    However while printing needs the parent item no with the purchase order number for that child item number.
    It is getting stored in RM07M structure.
    Any inputs / suggestions how to retrive parent item number and purchase order number for child item i.e for subcontract items?
    Thank you .
    Prasad.

    Thank you for the reply. I checked the table RSEG table for material document and PO details, however the RSEG gets populated when there is credit or debit entries.
    In this 57F4 challan there is no credit or debit enteries hence would not get in RSEG table.
    Appreciate your inputs for any other alternative.
    OR is there any table or Function Module to get the enteries of the struture of RM07M .

  • 57F4 Challan printing with Purchase order number and parent material

    Dear Team,
    As a SAP standard 57F4 subcontracting challan will have only legal entities,child materials, quantity, assable value etc.
    but as a client requirement we need to incorporate the PO number and line item in the 57F4 challan, additionally client requires the parent material also printed in 57F4 challan
    Anybody can help me how to get the PO number and parent material in 57F4 Printing, because i have already searched in MSEG table but for the material document number iam not able to find the PO number and line item.
    iam posing the GI with referenc to purchase order only. but even iam not getting the PO number with reference to the posted document number in the table.
    J Sridharan
    Satyam Computer Services Limited

    thanks for your reply hemalatha,
    i have tried with OMJ3 transaction, but it is purely a print parameter settings for J1IF form. please help me where i can maintain this settings to get the output in MSEG table.
    moreover iam creating all the subcontract material documents with ref to PO number only through MB1B transaction. please advise.
    Regards
    Sridharan

  • Customer 57f4 challan capture

    Hi all!
      We are doing a mere job wok. Customer is sending raw materials with delivery challan and 57f4 challan. We are processing the raw material and sending the finished material to the customer. I am receiving the raw material by 561 or also i can use 501 mvt type. I can enter the customer DC number in the TEXT field.
    But how to capture the 57f4 challan in SAP. Since we have to do ageing analysis to send it within 180 days.. How to do this?
    Thanks in advance,
    Raj.

    hi
    1. Define your customer materials (both component and finished product) as non valuated material, because these materials not effecting the our inventory.
    2. create Bom for finished product.
    3. Create sales order for service charges with reference to your customer PO.
    4. Receive the component from your customer through 501 E (with out po sales order specific).
    5. Create Production order with reference to sales order through MRP or manual.
    6. confirm the production order and receive the
    finished product.
    7. Delivery to customer as in normal sales process.
    8. Then create performa invoice or billing to your customer.
    Please maintain the customer excise challanas manually or you can develop z development for tracking purpose
    http://help.sap.com/bp_blv1600/V5600/BBLibrary/HTML/150_EN_IN.htm
    regards
    kunal
    award if helpful
    Edited by: kunal ingale on Sep 13, 2008 2:09 PM

  • 57F4 Challan no. re. to PO. No.

    Hi,
           Is there any std. report with which we can find the subcontract challan number and goodws transfer number ref. to the Subcontracting PO number.
            Also in which table we can get the information easily  as if we select the Table MSEG  to get the material transfer doucment with movement type 541 , syetms it taking lot of time then after that i have to seelct the challan number from another table .
        regards,
          zafar

    Hi,
               Thanks for your reply, it is very usefull,  one more think i want to know  is there any report  in the same way but it should also give the PO numbers for which still there is No GI  and 57f4 challan made  as in JI17,  it is displaying the Po for whcih challan is made.
        regards,
         zafar

  • Subcontract process (57F4 challan)

    Dear SAP Guru,
    I implement a scenerio of subcontracting. A new requiremnt is come under subcontracting. i.e A plant send a Material X to subcontractor through 57F4 Challan. And soncontracotr process that material and add some material with X (i.e. Excisable Material which is add to X) and generate FG Y. when we receive the material then subcontractor want to converison charge with ED of adding material. How do we process this scenerio and how we to capture ED with material and how to  pay the excise duty to vendor.
    thanx

    Hi,
    U can Map as -
    solution1)
    If material code u want for added material then -
    Create PO with 2 line item against the vendor.one is procurement item i.e added material and second is s/c item i.e. Y.
    Solution2)
    If u dont want material code then-
    Create PO with 2 line item one is service item which is nothing but the added material cost and second is S/c item i.e Y
    regards,
    sujit

  • 57F4 challan reconcilation

    Hello Friends,
    i am facing the below error while do the reconcilation for the 57F4 challan.
    "Challan not valid, material doc., is valid for another scenario"
    Kindly share your ideas to fix the same.
    regards,
    sathes

    Hi Dear,
    In IMG u have left the Setting.
    Logistic General-->Tax on Goods Mvt->Business Transaction-->
    Subcontracting--->Maintain Mvt Type groups---->
    0001 541
    0002 101
    0002 542
    0002 543 O
    0002 545
    Please don't enter Subcontracting challan manually...select subcontracting challan number by pressing of F4 and Select it and ente rthe  year.....

  • Closing of 57F4 Challan or Making GR after 180 Days

    Hi,
       I want to know  if we have made a 57F4 Challan   and partial material we have received from the vendor  and remaining material we have not recd  till the specified period of 180 days  then how to make the GR after 180 Days  or how to close the challan
    second scenarion  if we have send material to vendor with 57F4 channlan  and we have not receievd  material  with in 180 Dya  then  how to close the challan.
    regards,
      zafar

    Hi niti,
        Thanks for reply,  i want to know  even  if after 180 days we have not receieved the material  and if we want to cancel  all the document how is the sequemce and process for it  as we have created PO  ,  MB1B,  and J1IF01 challan  then  how to cancel all the documents
    and as u have steps for making GR after 180 Days  with J1IF  this is std. procedure avalibale for this   is there any effect of this on other FI entry etc.
      regards,
        zafar

  • SubContracting Challan (57F4 Challan)

    Dear Experts
    I want to print the 57F4 challan through system.
    I have done all neccessary configuration & able to print the challan. Output type used in this case is J1IF.
    Now I have created one output type YJ1F by copying the above output type. Also I have copy the sap script of 57F4 challan & made the neccessary changes & assign to new output type.
    Also I have assigned new output type in sub-contracting attributes.
    still I am not able get print from the system with required changes. Also system is not giving any message.
    So please let me know if I missed out any configuration. or any constraints in regards CIN.
    Kuldeep

    Hello Kuldeep,
    I have completed this requirement for our client and here is the "how to do" SAP wiki page.
    <[http://wiki.sdn.sap.com/wiki/display/ERPLO/SubcontractingChallan57F4_J1IF01_J1IF11|http://wiki.sdn.sap.com/wiki/display/ERPLO/SubcontractingChallan57F4_J1IF01_J1IF11]>
    Let me know if needed further information.
    Regards,
    Arif Mansuri

  • 57F4 Challans. CIN version

    Hi Gururs,
    We are using CIN version 4.0A. Here is one major problem we are facing.
    Just after SAP implementation in 2003, materials were sent to subcontractor along with 57F4 challans. When the goods came back, due to lack of awareness, user created new subcontract orders, raised new 57F4 challans and received the goods against them. So original challans are still open. How to close these challans.
    What will be the accounting entries ?

    Hi,
    after a lot of analysis, I found the problem is actually like this:
    Initially some subcontractor challans and subcontractor stock was uploaded in the system in 2003 just after implementation.
    When the goods came back, for whatsoever reason, user created new subcontracting PO, new subcontracting challan and received the goods against the new challan. The original challan is lying with status "Posted" in the system till date.
    (It is also noticed  that while creating the challan the system does not create any accounting document. Neither it does any if the goods come back within 180 days.accounting entries to CENVAT account is only made when the goods have not returned fully and somebody tries to complete the challan. At that time system debits the CENVAT account with the amount equal to the excise credit of the unreturned goods)
    Now, user wants to close the challans somehow.
    My question is, how to close these challans ? If I try to reverse the challan, system tells me to reconcile first. If I try to reconcile, it tells me to reverse first. How to go about it?
    Can we just change the status of the challan using ABAP at the tables ? Or is there any better way to do it ?

  • 57f4 challan

    hiii...
    here we using sap yearfrom  2006 .when i m using j1ifr for display the subcontarcting challan ...then system showing 2006 pending qty...how we clear 57f4 challan?
    Thanks
    Rekha Shrama

    Hello,
    I also facing same problem with 57 F4 challan,
    But before reconciling it we need to reverse the open qty towards the vendor then reconcile and then close.
    but again the period goes beyond the specified days specified in attributes (180)
    Also period not open for last year.. what to do as rekha also facing same problem..
    So correct me is that i am correct or wrong
    Abhinay Waikar.

  • 57F4 Challan Issue

    Hi everyone,
    Suppose i am transferring material from my plant to Subcontractor place through 57F4 Challan. I have to get back the material within 180 days. If not i have to pay excise from the day one. Is there any transaction so that i can monitor the material lying in the subcontractor place by Day wise???????
    Regards
    kamal

    hi
    If you want to monitor the Challans use report J1IFR - Challan Listing , & select the options reversal due . this will list you the challans
    If you want to monitor within 180 days period.... select the returns dtae from & to Option....

  • 57f4 challans  Annexure IV

    Hi experts,
    I have a problem with the report for 57f4 challans-J1IFR. In this report it shows "Quantity pending" even when I have reconciled & completed a particular challan. What does this mean?. I have seen the standard Annexure IV, but nowhere this kind of a remark appears. Is there anything else to be done to remove this message?
    Regard
    nabil

    Hi Expert
    I did all the step properly..................GR qty against excise qty. and material document is also correct.......can someone send the step from Subcontracting Po to Subcontracting  Challan complete.
    regard
    nabil

  • 57f4 Challan reconsilation

    Dear All ,
    If i do not reconsile the 57f4 challan in MM module what impact it will have in account side ? where ? How to see the same ?
    Regards

    There will be no impact in accounting. Only thing that the challan will remain open.
    The annexure IV register has to be filled acc.
    If partial Qty is received then u can keep on reconciling the challan for annexure -4 acc and then close the challan where in the sytem will issue a mesage that no further reconciliation is possible.
    you can see the reconciliation status in Tcode - J1IFR

Maybe you are looking for

  • IMAP Mail and syncing with Server

    So I would like to convert from POP mail to IMAP. I have created a new account in Mail and so far I have been able to receive emails no problem. The issue is that sent emails are not being saved and I cannot save drafts. I can send emails fine but I

  • Iconia tab 8 A1-840 won't connect to Wi-Fi

    Just opened a refurb Iconia Tab 8 A1-840.Wi-Fi is on.  I select my home Wi-Fi network.  Signal strength - excellent.  Security - WPA2 PSK.I enter my password...  Saved, secured with WPA2.I select my network again and hit connect.  Authenticating...  

  • Apple TV3 dropping connection from iTunes...

    Hi there, I've read a lot of issues on the same thing but I wonder if anyone is having the same issue as me. Thinking it was a hardware problem I secured a replacement from the store but I'm having the same issue. I have a PC, Windows 8 BT Infinity (

  • Russion text in a PDF doc displays ?????

    I have a PDF document that contains Russian text but the russian text characters display as question marks ????? I have attached the document, and also 2 jpg files. The first screen print is looking at the document in another PDF reader (Foxit reader

  • I am unable to upload any photos to photo sharing sites?

    For the last two days I have been unable to upload any photos regardless of size to a professional photo sharing website. I have tried everything possible such as disabling my Norton services, emptying the DNS cache, clearing all browers histories an