9 Day fortnight shift sequence

Hi PP'ers
Our company is changing our working pattern to a 9 day fortnight, here we work 1 week with 5 days and one week with 4 days and repeat.. i.e. we have every second friday as a holiday.
What is the best way to reflect this in SAP such that we cannot plan production on every second friday?
A shift sequence... I can't seem to find a way to make a sequence longer than 7 days
A change to the factory calendar?
any tips appreciated.
thanks

dear friend,
you can create a new holiday calendar and set it in your current factory calendar fixing workdays as well.
use SCAL
if you need, you can create a Special rules...
regards,

Similar Messages

  • Shift sequence query in PP work center

    Dear All,
    I am having one problem while maintaining shift sequence in work center. I have maintain all config settings in OP4A shift 1 shift 2 shift 3 but when I create work center and select shift sequence, it is only taking shift 1 and not all 3 shift for all 7 days.
    Can anyone tell me the solution?
    Thanks in advance.
    Regards,
    Max

    Dear Santosh,
    Thanks for the valuable inputs.
    I have created following sequence in OP4A.
    1, Create a Group eg. CB
    2.Create a shift definitions like SHIFT1,SHIFT2,SHIFT2, START/END DATE, START/FINISH TIME OF SHIFTS, NO BREAKS ARE THERE and assign it to group.
    3. Define individual shifts SEQUENCE DAYWISE wrt to groupo.
    4..Assign grouping in capacity header of work center.
    5.Now go to add interval option and create a new version of capcity which contains desired shift sequence from the shift group assigned.
    7. assign proper valid froma and valid to dates.
    8. In capacity header screena ssign the newly created capcity vesrion as active vesrion.
    BUT STILL i WILL ABLE TO MAINTAIN ONLY FIRST SHIFT SEQUENCE FOR ALL 7 DAYS.
    SYSTEM IS NOT SHOWING 2ND AND 3RD SHIFT.
    PLEASE HELP ME OUT.
    THANKS
    MAX

  • Shift sequence

    Hi all ,
    What is the use of shift sequence ?
    I have defined Shift sequence , assigned to work center Etc .
    But  whr does the same will appear or what is the use of the same .
    (HR module is not implemented here )
    Regards

    Hi venky
    Normally the available capacity of that particular work center is calculated from the data we are giving in the capacity header/Available Hrs from - To and the break time, the number of work center and efficiency
    If we give shift definition and shift sequence. We have to assign that in shift group in the capacity tab.
    The available capacity will be calculated from your shift definition and brake time which is given in your shift group.
    if your shift start time is 06.00 end time 14.00 break time is .5 hrs. Then Available capacity per day is 7.5 Hrs.
    If your are giving shift sequence also 14.00 to 22.00 - 22.00- 06.00. Then the available capacity 7.5 X 3 = 22.5 Hrs per day.
    Regards
    J. Saravan

  • Shift sequence in available capacity

    hi, all SAP experts,
      my question is as follows
    I created grouping in which shift sequences are defined and i assign this group to work center in capacity header. So work center should have to select shift sequence in capacity tab but i enter manually start time and finish time in capacity header.So why systm can't show interval of available capacity daywise automatically through grouping or is there any setting for this?
        thanks in advance
    i will look for points also
    regards
    Nitin Nerkar

    Dear,
    In work center change transaction capacity view
    assign this grouping no XX.
    Enter active version = 1
    Then Click on interval and shift push button (left top)
    follow the menu path Edit>insert>insert interval
    enter
    valid from and valid from field
    enter shift sequence and remove the data if there in any other filed and click on ENTER. all the days in week are defaulted with the shift seq you defined.
    It will work for you.
    Regards,
    R.Brahmankar

  • All Day Events shift order randomly when printing!

    When trying to print in month view, my all day events shift order within their day in a seemingly random way. This is a problem because I want certain all day events to line up next to each other day after day in a specific color coded way. This has been impossible for me to accomplish because for some reason what the month view looks like is never what the preview or printing looks like. Is it possible to lock the position of all day events so they print as they appear in month view?

    I'm having the same problem only not just when printing. My All-Day events (which I use more as notes than actual events) switch places all the time and I can't make any sense out of it. I thought it had to do with alphabetical order, but that's not it, then I thought it had to do with the order I typed them, but that's not it either. It's particularly annoying when I have two days with multiple identical events and yet they don't have the same order. There's got to be a way to order them manually, but if there isn't, Apple should add it quickly.

  • Assignment of shift sequence in work centre

    I have already created the grouping key & shift sequences in OP4A. There are 7 groupings when I see in OP4A. But when I try to assign them in CR02 capacity header screen , I see only 3 grouping keys. I dont see the one I have created too. What could be the reason?

    Please check you have any letters in grouping code?
    use only nunmbers - it will appears
    instead of AA, AB, AC create with 11,12,13
    Please close the thread if answer is okay, otherwise revert back

  • Shift sequence in CO11N ?

    Dear guru ,
    in the confirmation of the operation of a production order (CO11N) i want to enter the shift sequence
    for the work centre capacity involved.
    Itu2019s this field available in this transaction ?
    Thanks a lot.

    Dear,
    Shiftwise confirmation is now part of SAP standard! The new functionality is now part of ECC6.00 Enhancement Package 3, see help.sap.com for further information and assistence,
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/46/f2a5ce3cd767f9e10000000a1553f7/frameset.htm
    Use Release Ecc6.00 with enhancement 3
    Otherwise you need to go for Z development.
    Regards,
    R.Brahmankar

  • What will happen if a maitain both standard available capacity and grouping key ( shift definition and shift sequence) in the capacity header of a work center?

    Hi all,
    Im little confused with the capacity header in work center. In the capacity header there is one place to give start time, end time, length of break and number of individual capacity. And in grouping key i can define the shift and shift sequence. So if im maintaining both of these ( standard avilable capacity and grouping key), which will be considered to calaculate avilable capacity?

    Hi
    If you are running three shifts ,please maintain the data as given belwo
    start :00:00:00
    End:23:59:59
    Break :03:00:00 ( 1 Hour per shift so 3 hrs for 3 shifts)
    No.of individual capacity :1
    System will understand that it is round the clock operation with total three hour brak and you will get 21 hour per capacity
    Hope this helps
    regards
    Prakash

  • About the shift sequence setup in capacity categary

    Hi
    Harish here
    Can any body give me the technicality behind the planning, how shift sequence will consider.
    For ex: i have created the wc and for that i have created the capacity as machine. in the capacity header i have entered the factory calendar and start time as 9.00 am and end time 5.30 pm and break as 1h. also i have created the group of shift sequence in that i have taken as general shift. that is only one sequence ( 9AM-5.30PM no break consider) that has been assigned to above category
    How the system is selecting the sequence for the group (enter in capacity catagory) as well as calendar and arrives the dates of schedule.

    ...

  • Shift sequences

    Hi team,
    plz can anyone tel me how to define the shift sequence in detail,i have been through this path but the sequence key its not taking ,on what basis it should be given
    SAP Reference IMG u2013  Production Planning for Process Industries u2013 Master Data u2013 Resource u2013 Capacity Requirement Planning u2013 Available Capacity u2013 Define Shift Sequence

    Dear Pravin,
    Step wise try to do like this newly,(T.code = OP4A)
    1) Groping:- Define new group say -95 ok with name TEST.
    2)Then Click on Work break schedules:- New entry-
    0001 0  BK1 12:00:00 12:30:00        0,50
    0002 0  BK2 18:00:00 18:30:00        0,50
    0003 0  BK3 03:00:00 03:15:00        0,25
    3)Define Shift definitions like as,
    A First Shift 01.01.0001 31.12.9999 07:00:00 15:00:00 7,50  0001
    B 2nd Shift 01.01.0001 31.12.9999 15:00:00 23:00:00 7,50  0002
    C 3rd Shift 01.01.0001 31.12.9999 23:00:00 07:00:00 7,75  0003.
    4) Define Shift sequences
    SH1  1   Frist Shift       A A A A A A A
    SH2  2   Second shift   B B B B B B B
    SH3  3   Third Shift       C C C C C C C
    Then Assign it to your work center.
    Regards
    R.Brahmankar

  • Shift sequence of a workcenter changed AFRU not updated

    hi all,
    i have an issue with the change in work center's capacity.
    by changing the shift sequence of a work center and then booking the hours against it, i can not get any update in AFRU in neither of its field ISM01, ISM02 ISM03....
    what could be the reason? or  am i missing anything?  do i need to do anything more after changing the capacity related parameters?????
    waiting for your master comments, valuable inputs?
    best regards,
    Maulin

    hello Thaila,
    first of all thanks for yout reply,
    in fact we have a schenario where we book the hours with event type B10 and B40. without any yeild confirmation.
    and we consider the duration between the  B10 and B40 as activity duration (in terms of hours).
    so when i change the shift timings in the work center and post the hours in B10 and B40, there is a miss match. e.g. B10 i posted at 17.06.2009 10:30:00 and
                             B40 i posted at 17.06.2009  16:30:00 so in ISM01 or in ISM02 (based on activity and std values maintained) it should updated as 6 hours....
    so it may possible that after changing the shift i am missing some other procedure.....
    i hope this would have clear the question you had...
    best regards,
    Maulin

  • Assignment of shift sequence to work centre

    I have created a new shift sequence. where can I assign it in the work centre?

    Hi,
    you need to define the grouping key /shift definition /shift sequence in SPRO.
    Assign the grouping key work center capacity tab pageunder capacity header.
    Regards,
    nandha

  • All Day Events Shifts Regular time events to the Right.  Unable to view meetings in portrait mode

    Is there a way to view the calendar with the All Day Events and regular meetings within a portrait view. 
    Thanks,
    BKLYN215

    Same problem here; if I EVER find out the solution I will post it here.

  • Sequence Issue, where did my work go. Spent all day and closed sequence now it's gone.

    I'm new at this version of premier. I did all my edits saved the file and then closed the sequence how do I get it back?
    Help@!

    Because you say you're new - have you looked in the Project window where all your media is? There should be a file there with a different icon that is your sequence. Double click that to open it again.

  • Current day "shift starts from previous day" night 23:00 hours

    Hi Experts,
    I have a challenging scenario in Positive Time Management which is current day 1st shift time starts from previous day 23:00 hours (eg: previous day 23:00 to 07:00 current day).
    As per my knowledge in SAP Time Management, Shift start time is considered as current day, but for my scenario Shift End time has to consider as a current day.
    I couldnu2019t brought this shift forward to as 3rd shift because Production Incentives amounts and public holidays are computing based on previous day 23:00 hours.
    Points will be awarded for helpful solution.
    Regards
    Raju

    While you create a recod in the IT 2011 as you give
    next field you wil be having a field for previous day option if you choose that
    p20 for out time
    ex: 7:00 am i.e next day but still it will count for the current day
    Best Regards