About the variance of production order difference.

hi all
now i am practicing producting. i have closed the production order by technocially completed.and the variance  (difference between standard cost and actual cost) will be settled to production order difference account through our customization.
when we are doing the delivery and billing, it is taking the standard price. but that variance is cost of this Finished product,but it is not including when we are doing delivery and billing. the variance is shows in P&L debit as a expenses.
When the SD people defien the sales price in "PR00", do they consider this variance also?
please let me know about this. can u give me the complete details.

Hi
I suspect based on the price control 'S' maintained for FG, the billing would happen at this standard price. Any variance in production would be settled to a separate variance account and would be available for analysis, based on which you could alter the standard price for the following period
Thank You,

Similar Messages

  • How to compare the variances of production order type and get report

    Hello All,
    I want to compare the variances of production order type wise.
    for ex. i want variances of order type PP 01 and PP 02 in a single report.

    Hi Sachin,
    You have to maintain summarization hierarchies to achieve this.
    1. Maintain summarization hierachies with hierarchy level - order type in the t.code.KKR0    
    2. Generate the hierarchy in KKRC
    3. Run the report KKBC_HOE
    Regards,
    Mukthar  

  • Expected yield variance in  production order creation

    Dear sir
    pl tellme ,where i have to capture the expected yeld variance.
    for thisbelow given reasion i have to capture the expected yeld variance
    Total confirmation quantity not equal to planned confirmatio.
    The confirmed quantity for this operation is not equal to the planned quantity to be confirmed
    The quantity confirmed until now for this operation is greater that the planned quantity to be confirmed.
    pl tell me
    thanks and regrds
    Baswaraj

    Hi raj,
    At the time of order creation system shows Delivery tolerance in goods receipt tab since you maintained at Material Master level But Expected yield variance will be Zero (System doesn't know how much you are going to confirm).
    After Doing Final confirmation with clear reservations indicator and goods movements, System calculates the difference between actual order quantity and confirmed quantity at operation level in percentage. System updates the same in Production order. In your first order you got 0.2-.   That means based upon operation yield confirmation, your expected yield i.e. GR quantity is 0.2% less than the order quantity. At the time of GR, system proposes the quantity you confirmed at operation level, but not the order quantity.
    Where as coming to second order your conformed quantity is same as your order quantity. Hence system is not showing any expected yield variance in production order.
    Check it with different order quantities.
    Regards,
    Venkat.V
    Note: At the time of operation final confirmation in CO11n, if you select Confirmation Type Final confirmation and the Indicator Clear Open reservations, Irrespective of operation quantity UOM system proposes Expected yield variance in CO02 after conformation.
    Edited by: Venkat V on Nov 13, 2008 10:48 AM

  • Wrong GL at the time of Production order

    Hello
    At the time of Production order settlement....its showing error that this GL is not possible to post automatically............there wrong GL(recon ac) have been assigned....where can i check this assignment in the system.................I have already checked it in OBYC.......but there i hv not found anything.......
    regards

    Hi Pari
    Check the following accounts for the relevant Val Class
    PRD-PRF (Variance acct) / GBB-AUA or AUF (COGM) /
    Also check WIP Account as well as Change in WIP assigned in IMG
    br, Ajay M

  • Selection Of BOM & Routing at the time of production order creation

    Hi guys,
    Please clarify how i can go about for the following mentioned scenario
    I have one Master BOM(Finished Product Level) & alternative BOMs for that,similarly i have one Master Routing & alternate routings for the same finished product
    At the time of production order creation is it possible for me to choose one of the BOMs & One of the routings of that particular finished product without creating a production version?
    Awaiting for a quick response
    Vijai

    Hi vijai prasad shanmugam ,
                                              In the material master MRP-4 view under the BOM selection you can maintain on what fatcors you want the BOM to be selected  Viz. Selection by order quant.,Selection by explosion date.Selection by production version etc.
    As far as the master recipe is concerned ........ I guess that if there are more than one valid master recipe maintained then SAP will prompt to select the one manually.........
    But it the standard practice to maintain the production version ....... for the similar situation to the one that you have mentioned.
    Please Let me know if I can help you in any way regarding this........
    Please reward the points......... in you find the ans helpful.....
    Thanks
    Kaushik

  • Input Quantity Variance and Input Price Variance for Production Order

    Dear All
    I am running variance program KKS2 for calculating variance of production order. for Activity variances are coming under input price variance and input quantity varinace but for material the variances is now shown separately for quantity and price rather it is shown as variances total amount. Can someone help me in know why material quanitty variance and price variance not shown separately
    Regards

    How does input variance and output varia.nce will be calculated on the settlement of production order after TECO.
    VARIANCE CALCULATION DEPENDS ON CONFIGURATION IN THE FOLLOWING AREAS,
    1) VARIANCE VARIANT -  DETERMINES WHAT VAREIANCE CATEGORIES ARE CALCULATED, E.G MATERIAL PRICE , USAGE, LABOUR RATE , USAGE VARIANCE ETC..
    2) TARGET COST VERSIONS
    3) VALUATION VARIANT FOR WIP  AND SCRAP
    Can we check in KOB3 or COOIS.
    KOB3 -  YES
    COOIS -  CHECK IN COST REPORT

  • Error while calculating variances for production order

    Hi Gurus,
    while calculating variances for production order i am getting the following error
    "Cannot calculate scrap variances" ( Error message)
    " no standard value estimate for material" (Warning message"
    A standard cost estimate exists for the material at the date mentioned in the error in released status.
    Please give solution for the error.
    Thanks in advance n Regards
    Arul.

    Is there an <b>itemization</b>, generated for the cost estimate used to calculate the target costs?
    Does the material components listed in the BOM of the cost estimate used to calculate the target costs, <b>assigned to the operations</b> in which they are used. Otherwise it is not possible to correctly report the variances and scrap when operations are confirmed.
    Does the order for which the variances are calculated have a valid <b>variance key.</b> ?
    Does the order have the status DLV (delivered) or TECO (technically completed). If the status was withdrawn, any variances and <b>scrap variances are canceled</b>.

  • A question about report completion in production order

    Hi,
    Rightnow, i am trying to develop some application about production order and play with the production order in SAP. I found a issue which I don't understand. Let's say I have a production order with some components issued for the BOM and these components are managered by serial number. Natually, when I issue components into this production order SAP asks me to select serial number. But when I report completion for some products, SAP doesn't ask me to select component's serial number. Also when I try to return left components from production order to warehouse, SAP ask me to select the component's serial but the serial # list is the complete list which doesn't make sense. Because I have already report some products completed, how comes it ask me to select serial # from all of them? So seems that SAP doesn't manager the serial number properly in production oder, something wrong either I miss some steps in SAP or SAP missing something to manager the serial # for production order.
    Any idea?
    Thanks,
    Lan
    Edited by: ZHANGLAN on Jan 13, 2012 8:56 PM

    Hi Gordon,
    Thanks for your reply. If so, I think we have to use add-on with UDF or UDO to find a solution.
    BTW, I will ask another question in a new thread.
    Thanks,
    Lan

  • How to find out the list of Production orders created for sales orders

    Dear All,
    Our company wants to generate a report for a List of Materials sold out in a particular Product Hierarchy. Along with that we want to know the list of Production orders created for the sales orders.
    How to identify the production orders which are created based on Sales orders.
    Kindly suggest.
    Regards,
    Mullairaja

    Check these threads
    [Sale Order & Production Order|Sale Order & Production Order;
    [Re: Linking Production Order against a Sale Order MRP run|Linking Production Order against a Sale Order MRP run;
    thanks
    G. Lakshmipathi

  • Changing the Assignment of production order in sales order in MTO scenario.

    Hello all!
    I have following problem:
    After the MRP a production order was created for a sales order. Because of the production in another plant
    the production order which was created automatically had to be technically completed and a new one
    created.
    If you want to check now the availability, the sales order finds nothing, because it's linked to the one,
    which was technically completed. Now is the question how can I change the production order for this
    sales order. (In the production order the correct sales order is connected!)
    As I found out it's connected to the field AUFNR in the table VBEP. But how can I change this
    field within a transaction and not in the database?!?

    No replies

  • Report for comparing Variances of production order types

    Hi All,
    I want a report in which i can see variances of production order type wise and can compare that with other types also.
    means my input should be as follows
                1) Company Code/controlling area
                2) Plant
                3) Order type 1
                4) Order type 2 and so on.......
    like wise I want to develop a report.
    I have created summerization hierarchy  but it show order type wise data.
    i want data from multiple order type in a single report.

    Hi Sachin,
    I have attached screenshot for your reference. Please find it.

  • How to restrict the GR for Production Order when Goods Issue is not done

    Hi Gurus
    How to restrict the GR for Production Order when all the required components for production order are not issued with all required quantity. Even for partial issue system should not allow GR with 101. The user status with RMWA, RMWF & CGFB is not working.
    Pls suggest best solution.
    Abhijit.

    Hi,
    You can club together the GI nad GR at the time of confirmation..
    I.e Backflush for the components and auto GR for the Product.
    So that you can stream line the Process.
    The best Option would be to use the User Exit:
    Enhancement - MBCF0002
    Functional Module - EXIT_SAPMM07M_001
    Include - ZXMBCU02
    Refer below link for further details..
    How to stop the goods receipt before issueing the goods for production orde
    Regards,
    Siva

  • Function or  tables to know the positions of production order

    Hi Gurus,
    Someone knows a function, bapi or what are the tables in order to know what are the components of
    production order, in the transaction CO02, i can see the components of a production order but i need
    to replicate this for a z report.
       Any suggestions ??
      Kind Regards
         Noemí

    Hi,
    Check this link...
    Re: Find the table relations of production order and sales order
    Regards
    Debarshi

  • Exit/Badi in the transaction of production order create or change (CO02)

    hi all,
    I need an exit/Badi in the transaction of production order create or change (preferably during SAVE).
    I want to change structure AFVGD-usr02,AFVGD-usr03 .
    <b>PPCO0007 Exit when saving production order</b>
    the exit is not applicable EXIT_SAPLCOZV_001 .

    Hi
    we around 200 exit for this tcode i found only three badi for this tcode.
    AFABD_CHANGE          Change Relationship
    CAUFVD_CHANGE        BAdI: Overall Network Scheduling with Selection Option
    SIDAT_UPDATE            Change date of price simulation.
    check with this goto se18 and F4 thn give the Package as CO.enter u get this three.
    reward pointd if use full

  • What is the use of production order without material?

    Hi gurus,
    can anyone plz tell what is the use of production order without material?
    n steps involve to perform this task?

    Dear amnpp,
    It's widely used for capturing the rework activities(components and activity cost),both for final rework and inprocess rework
    activities.
    Check these links,
    Rework order manually (not Trigger)
    rework order
    Rework Order Steps
    Re: Coustomization order type for Rework
    Regards
    Mangalraj.S

Maybe you are looking for

  • How can I open the editing screen?

    I downloaded the PR app, I can look at the tutorial and upload files.  But I cannot get the editing screen.  Any help is welcome.

  • WebSite replication to other machines SharePoint 2013 Farm

    Hi all, I have done a basic install and configure a SharePoint 2013 with two front end (FE), three application servers (app1, app2, app3) and one SQL 2012 cluster. When I tried to import a SP 2010 site from app1 and test on this server it works. late

  • Strange effects in using f:convertNumber and h:inputText

    Hi everybody, I'm having really strange results with the following <h:inputText> and <f:convertNumber> tags in one JSF page: <h:inputText id="total" value="#{myBean.total}" required="true" size="10" ><f:convertNumber minFractionDigits="2" maxFraction

  • Gallery modifications (hints wanted)

    Hi, I'm a newcomer in the area of web development but I've spent a few years in VB development so I thought I'd give the Gallery a try. I've setup up my own gallery based on the demo example and it works just fine. The web is not public yet, but it l

  • ORA-01591: lock held by in-doubt distributed transaction string  error

    Hi Gurus, I am getting the error ORA-01591: lock held by in-doubt distributed transaction string error while running once procedure. Procedure basically inserts 2 tables and update 1 table. The order of execution is given below. However I get the err