Account assignment indicator cannot be removed (Error: CJ056)

Dear Experts,
I hope somebody can help me:
I want to assign a network activity to a wbs element - but I don't want that the wbs-element is an account assignment indicator.
I first thought that I could control that by the paramter "Control key" in the networt activity - but I still get message/error above (CJ056).
In this case I want to use the network acitivty only for Scheduling not for any "Cost-Activities".
I hope somebody can help me.
kind regards
nexus

I just created a new project to check if the status is the source of my problem.
But even with a new Project without any posted costs, it's not possible to remove the flag.
the error cj056 relats to the following check:
"The following assignments are checked:
network
network activity
Aufträge zum Projekt (Fertigungsauftrag, Innenauftrag, Instandhaltung)
Planauftrag"
Is it such a mandatory requirement that the flag is sent, when you assign a network acitivity to a wbs-element?
even when you use the network activity just for scheduling?
Edited by: nexus_123 on Aug 9, 2010 3:21 PM

Similar Messages

  • Account assignment category cannot be changed for limit items

    HI all,
    I am getting same error in RZ20
    Instance POXXXXX of object type PurchaseOrder cou ld not be changed
    Purchase order still contains faulty items
    Account assignment category cannot be changed for limit items
    PO is created with service item and it is in backend.
    When it is changed it is giving error. User is added contract no# on change version.
    Could you please share the solution...

    sometimes sap throws unwanted error messages. these are example notes
    415346  ME21n, ME456 when filling the account assignment type
    411883  ME21N, ME456 when filling the account assignment category
    403537  PO from PReq with different account assignment type: E456
    Using Transaction ME21N,you create a purchase order for external service and add a new item by copying a request for quotation. If the request for quotation does not have a plant, when you enter the assignment category, the system displays error message ME456 "Account assignment category cannot be changed for limit items". Also there is no account assignment change involved.
    Additional key words
    what exactly you are trying to change the carts?

  • "SD/PS Assignment" indicator cannot be set Message no. CJ119

    Dear Experts,
    We are trying  to create a  project from sales order ,we need to create One WBS per each Item. But when we set SD/PS assignment indicator in standard project definition,  system is throwing the following error.
    "SD/PS Assignment" indicator cannot be set Message no. CJ119
    My Standard Structure
    M2-000004
    M2-000004.01
      M2-000004.01.01
      M2-000004.01.02
      M2-000004.01.03
      M2-000004.01.04
      M2-000004.01.05
      M2-000004.01.06
      M2-000004.01.07
      M2-000004.01.08
    Please help me.
    thanks
    Shareeq

    This means that your basic settings for assembly processing are not correctly set up.
    Read SAP help or more and also check forum for more information.
    Basically you need to ensure -
    You have to set up std network and std WBS as templates
    material with sales view
    assignment between material and std network - txn CN08
    Configure requiremetns that allows assembly in sales order - ie to generate network
    Once these are done then you can use the SD/PS assignment indicator in the project definition
    For this the only other mandatory requirement is that in the project profile the only one root indicator should not be set.
    Any experienced PS consultant should be able to set this up for you.

  • Auxiliary account assignment to asset possible remove entry

    While selling f-92 asst sale iam gettign this error Auxiliary account assignment to asset possible,remove entry.
    Please guide me on this

    Hi,
    While doing F-92, you are not supposed to enter the asset no in Clearing Rev from Asset Sale GL line item. Instead you need to select check box Asset Retirement(just above text field) for the same line item and press enter, then system will prompts with another pop up window, where you need to enter the selling asset no and value date and Complete sale and ENTER.
    Cheers,
    Srinu

  • AA449 (Auxiliary account assignment to asset not possible) error

    Dear colleagues,
    While posting asset sale through FB01, it is giving the following error: Auxiliary account assignment to asset not possible, remove entry (message no. AA449)
    I have already checked the note 787350 and below thread that was previously discussed but we are on ECC 6.0, with support package SAPKH60405 note is not applicable.
    http://bit.ly/gTdFA6
    Regards
    Metin

    Hi Metin
    1. Use Tr F-92
    2. Specify  Customer No in 1st screen  & "Asset Sale Clearing Account" against Posting Key 50
    This GL account should have Field Status Group G029 in Fs00
    3. Tick the "Asset Retirement" check box in the above Gl acount and press entre
    4. Enter the Asset No, Amount and other details in the next pop up screen
    Br, Ajay M

  • Deletion Indicator cannot be unset" error message in PO

    Hi Experts!
    I have a PO in which I deleted a line item, which has been invoice verified, delivered, etc.  Now when I choose to unblock/undelete the line item, it give me error message:  "Deletion Indicator cannot be unset".  Is this a major problem or can it be fixed.  Any information would be greatly appreciated.  Urgent!  Thank you for your time!
    Best Regards,
    WC

    Hi,
    I would say that system should prevent you to delete a line item po with a GR and or invoice entered. For me it should be a bug.
    Now you have done the line item deletion, inconsistency may occur...
    Did you try first to uncheck the final invoice indicator in the PO ?
    Did you check OSS note 1023130 ?
    Kind regards,
    Yann

  • Account assignement category for purchase requisition - error message

    Hi All!
    I created a new Item category in service order (IW31) "O" with the account assignment category "O". If I don't set the Consumption posting indicator to V for this category, when I set the account assignment category "O" to the purchase requisition in <i>Plant Maintenance and Customer Service-Maintenance and Service Processing-Maintenance and Service Orders-General Data-Define Account Assignment Category/Document Type for Purchase Requisitions</i>, I receive the message:
    <b>"Acct. assign. cat. "O" for purchase req. does not exist.
    Message no. CS 075"</b>
    The client request is not to charge immediately for the goods receipt with the relevant costs the service order. The client wants to create the goods receipt in a storage location for the plant and then confirm the components and charge the costs after the component confirmation (movement type 261) - similar to stock material.
    Any idea about what should I do?
    Thank you.

    Hi Everyone,
    The problem is solved now. The cause was that the test requisition that I was making was satisfying more than one rules and hence I end dated the remaining rules which solved the problem.
    Thanks!

  • Multiple Account assignment with cost distribution value error

    Hello Experts,
    We are facing the below issue,
    We are trying to create Limit SC with MAA cost center with cost distribution "By Value". we distribute the total value to 5 cost centers. when we try to order the SC, system is not allowing us to order, we got the error message "Multiple account assignment only with percentage less than 100%".
    Please advise how to resolve this issue.
    Regards,
    Santhosh Kumar.G

    Hi
    Check this OSS notes : 1644804
    Regards
    G.Ganesh Kumar

  • About account  assignment  error

    when i am   Releasing Credit Memo to Billing
    i am getting this type of error
    Account assignment analysis cannot be carried out for billing type G2
    regards
    raj K

    Dear Friend,
    The account analysis is only possible if you have assigned a G/L accounts for your transactions of Billing type G2.
    Ckeck VK0A.
    here you check your pricing condition types account keys and G/l Assignments.
    after doing so check your billing documents of G2 type you will be able to do account analysis.
    regards,
    Amlan Sarkar

  • PM Error Message " FM Account assignment is incomplete (Funds center) messa

    Dear PM Experts.
    We use PM module for both Preventive maintenance and Breakdown maintenace.
    While creating an breakdown maintenance order, the system gives me an error message: " FM Account assignment is incomplete (Funds center), error  message number FI135";
    As a result i cant release the order for further processing.
    Kindly help me to resolve this.
    Thanks in advance.
    Richard.

    Hi
    Try below it may solve your problem .
    1. Go To Change Order  (IW32)
    2. form the Menu Path --- GOTO -- Assignments -- Fund Management
    3. Either your Fund center field will be blank there or the Fund Center available there is no more Valid now .
    4. Get the correct Fund Center from commercial & Enter there --- Save the Order & Release it .
    Regards
    Sameer

  • True Account Assignment-  Posting Error

    Hi
    Can anyone help me out from the below error.
    Enter a true account assignment object with revenues
    This error message comes when i try to post an entry in F-22. I couldnt under the sys Diagnosis
    message.. can anyone explain me in simple term with example.  please
    Thnx

    It is looking for real cost object. you need to enter profit segment with manual derivation. In the line item go profit segment field and derive the by entering relevant fields such as business area, sales organization.etc.

  • CProject Phase - Account assignment element

    Hi All,
              I am able to assign account assignment element for CProject phase manually.
    I want to do it through program,
    Could you please provide me the BAPI/FM to assign an account assignment element for each phase in XRPM .
    I am assigning WBS as account assignment element.
    Thanks and Regards,
    Ashok Kumar
    Moderator message: please (re)search yourself before asking, show what you have done yourself so far if posting again.
    Edited by: Thomas Zloch on Jul 15, 2010 12:49 PM

    If cost has been posted onto the subject WBS then the account assignment element cannot be unchecked i.e. it remains greyed out. You wont be able to change it even via CNMASS. The only option left could be to cancel the transactions that led to the cost assignment (please note a reversal means another transaction that only reverses the effect but does not remove the line items altogether, therefore a reversal does not remove the AA indicator).
    Also note that the cost can be both actual or statistical in nature. Even settlement from lower level WBS to higher level WBS leads to greying of the indicator.
    Regards,
    Ammar

  • Group chart of account assign consolidation report

    Hi All,
    Group chart of account assign consolidation report is throwing error in SAP. Kindly please let me know the process.
         Thanks...
    Saravana
    Edited by: saravana j on Jan 6, 2010 8:00 AM
    Edited by: saravana j on Jan 6, 2010 9:03 AM

    Hi,
    1. chart of accounts--> common set of accounts.
    2. Group of acts--> group chart of acts.
    Generally we use common set of acts.
    For common set of A/c-->OB13.
    For A/C groups>OBD4>new entries> give your chart of A/C, A/C group, name, from A/C and to A/c> SAVE.
    Assigning company code to chart of accounts-->OB62.
    Thanks.
    If this helps you please reward with points.

  • SRM PO error-Account assignment cannot be changed after goods/invoice receipt

    Hi,
    The SRM PO throws account assignment error in system (SRM7.2).
    Scenario: Shopping cart is created and SRM PO is sent to backend system and GR is also posted.The purchaser is now trying to change any data like,value,currency etc and the system throws account assignment error.
    The issue is system throws account assignment error for any change in other parameters but actually nothing is changed in account assignement part.This error is the backend error but not sure what can be done to stop this error.
    Need guidance from experts whomever came across this type of issue.
    Thank you
    swathi

    Hi,
    We started experiencing the ME 458 error last year when SAP introduced some new edits in BAPI_PO_CHANGE.
    It's triggered when the SRM account assignment (CO and FM) fields do not match the ERP PO account fields.
    SRM function B470_ACCSERV_CHECKACCASSIGNMT calls ERP function BBP4X_CODINGBLOCK_CHECK_47A. 
    In our case this only happened for material POs, services do not have this problem.
    There are numerous OSS notes out there for this problem, some are for MM and others for SRM.
    Hope this helps.
    Jerry

  • Set deletion indicator in purchase requisition account assignment

    Hi Guys,
    Can you please help we with the solution to set deletion indicator in purchase requisition account assignment or close purchase requisition. A purchase requisition of $3.600.000,00 was created through Project system Network-External Processing and it has 2 duplicate network activities and $2.246.577,20 was converted to purchase order then $1,353,423 became the network remaining order plan. A purchase order service entry sheet was accepted and the invoice was created. Now Iu2019m experiencing problem when Iu2019m trying to change WBS element and Network system status to TECO in order to remove the remaining order plan of $1,353,423. Iu2019m getting error message number:06411 the procedure I have follow to correct the error is to reduce quantities in the account assignment item and delete superfluous account assignment by setting deletion in each case but I cannot do that because the fields are grey
    Regards
    Sandile

    Hi,
    please check first if the report ZMO_CORRECT_EBKN  from note 739004  can correct the problem.
    I would like to recommend you to check also the note 796973 whether the correction is avalilable in your coding, it should solve the issue.
    In case the problem still persists, please open a ticket to get help from the primary support in area MM-SRV.
    Regards,