I am faced with a message 'Account XXXX needs assignment to a CO object'
hw do i go abt accomplishing this ?
reward pts for help
siddharth sridhar

Dear Sridhar,
This error has surfaced because somebody has created Primary Cost Element (KA01) for the G/L account , that is maintained in VKOA (Revenue account determination) or OBYC( Configure Automatic postings).
Now nothing can be done with that G/L account.
Take help of FI consultant and create new G/L account (FS01) ( or use existing unused G/L account that meets your requirement). Assign this G/L acct to the revenue account or invenotry account (as the case may be) in VKOA or OBYC.
Hope this solves your issue.

Similar Messages

  • Gl account require assignment to Co object

    Hi
    while  doing PGI .it is giving error of  "account require assignment to CO object"
    please clear where to assign Co object & how.
    do i need to assign the Gl in okb9 seeting

    hi,
    First identify GL account which you have assigned in OBYC . then go to FS00 and enter your account no. and press on Edit Cost Element in that there is 3rd tab page Default account assignment there give cost center and save it.
    Now try once again.
    thx.
    Ganu

  • Account 891000 needs assignment to CO Object

    While doing GR for subcontracting goods, I encountered an error saying Acc 891000 does not exist in CC 1000, when i created one using FS00, the error comes as ' it needs assignment to a CO object'.... Hw do i go with this....

    Hello
    Go to customizing task OKB9
    Copy an entry and use your 891000 account.
    Regards
    Kedar Kulkarni

  • GL account requires assignment to CO object

    Dear All,
    While preparing excise Invoice the accounting document is not getting released. On going to T-code VFX3 and tyring to releasing the document message comes as "Account 00000 requires assignment to CO object".
    Kindly guide on this issue .
    Thanks in advance.

    Hi
    I think it comes form the Account assignment tab in Item / header level of sales order where we mantain the Business Area.
    just check the settings (Path -
    ENTERPRISES STRUCTURE>ASSIGNMENT>SALES AND DISTRIBUTION>BUSINESS AREA ACCOUNT ASSIGNMENT

  • Account 233000 needs assignment to CO Object

    Hi
    Im trying to post differences in Physical Inventory and this error appears. What are the possible reasons and how do I fix.
    Vishnu

    Hi
    For G/L account 233000 you will have to maintain these details in FS00 in Edit cost element tab.
    Regards,
    Sourabh

  • Error in VF44 require assignment of CO object

    Hello SAP Gurus,
    We are executing VF44 for Sales order (sales order line has account assigment as WBS element) an error messsage - Ledger Account require assignment of CO object.
    What to do in this case to resolve this.
    Regards

    You use a income account and it is cost element also and you have to assign a co object but cost centers are statistical posting object for income cost elements so you have to use a PA object. If PA is not active do not create cost element for that income account. Delete cost elemenent. If you can not delete or if you want it to be a cost element then create a dummy internal order for revenue carrying account assignement object...

  • MR11 clearing - GL accounts requires an assignment to co object

    Hi Experts,
    While executing MR11 clearing, system is throwing error account xxxxxxxx requiring an assignment to CO object. We have done GR as well IR for which cost object is correctly picked as in purchase order. But while doing MR11 it is throwing error. What configuration needs to be checked to over come this error.
    Thanks in advance
    Narayanan

    Hi,
    Go to FS00 choose  your That g/l account click on change mode and click on Edit cost element (F8) and click on Default Acct Assgnmt Tab give me a cost center and save
    Thanks,
    Raviteja

  • Account Assignment to CO object

    Dear,
            While doing goods receipt  for Purchage oredr, it is showing error Account 800066 requires an assignment to CO object.
            Kindly help me out.
            I sincerely thanks in advance to responder.
    Regards
    AJIT K SINGH
    Edited by: AJIT K SINGH on Oct 30, 2009 9:37 AM

    Dear AJIT K SINGH,
    These are the following points could be the reasons for the Error;
    1. While cration of the Purchase Requisition u entered the Account Assignment Category, then only it will ask Cost Object while in GRN.
    2. In OKB9 my be automic assignment assiment must be there.
    In the previous mail as per as Mr. Prawan kumar, i hope in grn both accounts should be the Balance Sheet G/L account, then there is no chance, it would become as a Cost element.  Pawan kumar plese check once.
    Regards

  • Location and account assignment for technical objeCT

    WHAT IS Location and account assignment for technical objeCT , FOR functional location

    Hi
    check the one of the Views for the above data (notification no + fun Location)
    VIQMAML_IFLOS   
    VIQMELST_IFLOS  
    VIQMEL_IFLOS    
    VIQMFEL_IFLOS   
    VIQMSML_IFLOS   
    Regards
    Anji

  • MIGO Error - Account 6500029 requires assignment with CO object

    Hi Experts,
    I am facing problem with new material code opened recently.  Valuation class assigned is ZSTD. 
    At the time of GRN, It is  giving an error msg :
    Message no. KI235.  Account 6500029 requires assignment with CO object. 
    Kindly note I am not making an account assignment P.O.  It is a normal P.O.
    Previously also with same valuation class, we have received no. of materials with out any error.
    It should post the material to my inventory account 1220000 as it did with materials of the same valuation class earlier.  I don't know from where it is picking GL 6500029.
    Kindly help.
    Regards,
    Rajneesh Gulati

    Hi ,
    In OBYC kindly check the Key BSX for the GL account assingment to the valuation class .
    As inventory accounts are Balance sheet accounts and do no require an assingnment to a cost element .
    If your account is getting changed then check the same in OBYC - BRX .
    Regards ,
    Dewang T

  • Revenue account assignment for co object

    Dear All,
    Hi, I am posting customer invoice(FB70). At the time of posting i am getting the below error:
    Account assignment for co object.
    I already assigned the profit center in okb9. cost center is not assigned in okb9. because there is no direct co assignment for revenue cost element. is it right? if any wrong please correct me.
    Where i can assign the profitability segment in revenue gl account.please tel me assignment steps and t.code of that assignment.
    Thanks & Regards,
    Reddy

    where we can update the profitabilitry segment, any t.code is there.i tried to posting i am getting the error:
    Account 31111100 requires an assignment to a CO object
    Message no. KI235
    Diagnosis
    You have not defined a CO account assignment for an account that is relevant to cost accounting.
    System Response
    Account 31111100 is defined as a cost element.
    This means that you must always specify a CO account assignment.
    Procedure
    Enter one of the following CO account assignments
    Order
    Cost center / cost center/ activity type
    Sales order item (for a project or cost relevant)
    Project / WBS element
    Cost object (Process manufacturing)
    Network/ Network activities
    Business process
    Profitability segment
    Real estate object
    The posting row affected is 001, account 31111100.
    How to avoid the error message,how to assign the real controlling object to revenue account .please tel me process steps.
    Thanks & Regards, Reddy

  • Account 76701000 requires an assignment of CO object-Reversal of Invoice

    Statndard PO has been created by business . They did the IR without GR as they usually does. Now business is not going to procure material from the vendor they are not going to receive the material, But IR has been done, Now they want to reverse the IR document. But while reversing the IR document they are getting error- Account 76701000 requires an assignment of CO object.
    I have option to enter the cost center or order in the master data level. But is there any possibility to do the changes at PO level.
    But its surprise when we post the IR , no posting done in cost accounting , But while reversing why its asking for cost element, When i did the analysis Reversal is hitting PRD account key.
    I can do enter the cost center in the CO object and reverse the IR, But when i check in the FI costing document its showing zero values.I did it quality server, But Business is denied this solution and wants to do changes at PO level.
    Let me is there anyway to change the PO.
    Please help me to resolve this ASAP. IR has to be reverse for this PO.
    Edited by: varikais on Sep 8, 2011 6:53 AM

    hi
    In PRODUCTION server , there is no account in EIN/EKG In OBYC.
    also there no account maintenance for 602010 as a cost element in OKB9. But Error for CO object (while procurement of raw material) is not coming. WHY THIS?
    And CO object error comes only in DEV server.while procurement of raw material.Though we use MTO in DEV.
    I get confuse pl explain.(URGENTLY)
    Edited by: harshad deshmukh on Jun 18, 2008 12:32 PM

  • Assignment of Cost object

    Hi Gurus,
    I am using one controlling area for 4 for a group of companies with 4 company codes. When i am assigning some co object to a particular GL account that is creating the problem for other company codes. For Example:
    Controlling Area 1234.
    Gl account : 9000 4444( expenses) for 4 company codes "same"
    Already created 4 cost centres for each company code with the same number, only initial has changed. Like for company 1 it is 1000 1234, for 2nd company 2000  1234  so on.
    Now when they are processing they are facing problem for a different company code.
    Pls provide me the solution.
    Satya.

    Hi Satya
    In the cost element master, you can specify only one cost center as both company codes are assigned to same controlling area.
    In this case you need to specify default cost center using t code OKB9, wherein you will be able to specify default cost center per company code.
    Award points, if useful.
    Regards
    Rakesh Pawaskar

  • Cost assignment-Multiple cost objects being selected by default from the EP

    Hi,
    I have created an expense report from the Portal and entered the cost object - a WBS element and saved the report. Now, when I check in table: PTRV_SCOS, it shows me the cost object assigned are - both - the WBS Element as well as the Cost center. This is incorrect as there should be only one cost object - either the cost center or the WBS element. However, when I book the expenses from the backend, it works fine. Only the WBS or cost center is displayed in the table mentioned above. Anyone has any idea as to why this is happening?
    Many thanks in advance for your efforts.
    Cheers guys.
    Hope to hear from you soon
    Best regards,
    Tanmay Dhingra
    Edited by: Tanmay Dhingra on May 17, 2011 10:05 AM

    Hi All,
    First of all, thanks for your responses..
    Right, about the issue, what I explained here was that I am indeed assigning only one cost object: the WBS element. The issue was that even though I am assigning only the WBS element, it was also assigning the cost to the cost center by default. I did some R&D and found the solution to the issue (I was also asked to look for OSS notes but was not satisfied that this issue needs an OSS note to be applied so tried my solution). The issue was in table: T788M (allocate costs to variable account assignment). Here, I created an entry and called it USERGROUP_2 (just a random name) and assigned the variable cost objects (only the WBS and the Cost center) to be displayed. In the next step, I assigned this usergroup to the country in quesion feature (TRVCO). By doing this, I tell the system that only these cost objects are to be considered when an employee wants to assign the cost object. If the system sees that there is no value from the drop down to choose from, it picks up the default cost object (cost center). This was a simple issue that I had to rattle my brains on... but the solution I mention above worked like a hot knife going through butter...
    If you guys face this issue, please try this else feel free to get in touch with me on my number below.
    Once again, thanks for your responses.
    Best regards,
    Tanmay Dhingra
    +91 880 6666 606

  • Revenue GL assignment with CO objects

    Sir,
        Can anyone tell me where Revenue GL (3*) where we need to assign with CO object other than OKB9.
    As in my system no revenue GL are assigned in OKB9, I just wanted to know are there any other way of assignment. Just for my knowledge.
    Abhisek

    Hi,
    There are two ways of assigning viz. OKB9 or cost element master data itself.
    1. Go to FS00
    2. Enter the GL Code.
    3. Now click on Edit Cost Element button.
    4. Go to Default Account Assignment tab.
    5. You may define the CO object here i.e Cost center or order