Activating capacity display in Planning table of MF50.

Hi Experts,
I intend to use the MF50 for Planning my FG. My scenario is a normal PP PI and not REM. I am using production version to distinguish the work centre (defined as production place). I want to display the Capacity of the Workcentre on the MF50 screen along with the Planning table. I am able to see the Prod Versions, planned ordes / requirements on the screen. My only concern is I want to display the capacity on the same screen, I found that the Activate graphic and set graphic settings in the Capacity reqt planning have got greyed out.
I request the experts to guide me in this case.
Regards,
A S K

Hi
Check the following settings :
1. In  production Version whether work center is maintained as production line or not ? .Also make sure that  same work center ins maintained in  Routing or not .
2. In MF50 Initial selection screen Scheduling TAB check whether  'capacity requirement ' along with detailed planning  is activated or not.It must be activated.
Regards,
Velmurugan S

Similar Messages

  • Use of Planning Table (MF50) in Capacity Levelling with Production Order

    Hello Experts
    I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
    Any clue or help pertaining to this will be highly appreciated.
    Thanks in advance
    Regards
    Jayanta

    Dear ,
    MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP ,  MRP system assume Infinite Capacity  and schedule the order as per your selection in MD02(2,1,3,3,2)  and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
    In stanadrd SAP  , it is not possible to use MF50 for discrete production order.
    In discrete order or process order ,  do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done  in following way :
    1.CM31-Production Order Wise -Tabular
    2.CM23-PO wise -Graphical
    3.MC88: Ruf Cut Planning
    Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
    Make sure the below set up before  you carry on the Capacity leveling :
    .Define time profile in OPD2.
    Define the strategy profile in OPDB
    Define the Overall profiles in OPD0.
    In OPJK  maintained check capacity with SAPSFCG013 profile for your production order type
    In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
    In OPJU , chekc the contol tab of the scheduleing as per OPU3
    In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013  with finte scheduling tick.
    Master Data :
    1.Materials Master define the Production scheduler and production scheduling profile
    2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    3.Routing - enter the values for the standard values. Use control key with scheduling.
    Hope this will help you .
    Regards
    JH

  • Clear the History Data Automatically in Production Planning Table MF50

    Dear Friends,
    I have the problem to set the Production Planning Table (Txn MF50) to
    clear the history data automatically. Currently, all the history data
    in the planning table has to be cleared manually.
    Appreciate your help.
    Rgds
    Zahari Yusof

    instead of just removing the whole history like private browsing do, i just want to remove browsing/download history and form&search. i didn't want to remove cookies and active logins, heheh. thank you

  • Reg: Functions of Planning Table MF50

    Hi Friend,
    i wish you all a happy Friendship day...
    I need to know the following Function in REM,
    1. Functions of Planning table.(MF50)
    2.When we carry out Backflush , Components , activities get Posted. where can i find the reports for activities and components posted.
    3. Preliminary Costing Values.
    Thanks in advance.

    Hi dayanan,
    1. Planning table MF50 is used to create a manual planned order respective date wise inspite of creating in MD11 one by one.
    2. When you assembly backflush in MFBF your component consumption and Activities will get posted automatically GI, GR & Activities will be posted. This component consumption you can see through movement type 261 in MB51. Cost of that consumption and activities you can monitor in Product cost collector. PPC. for that go to KKF6N-select version- Header---- costs.... There you can refer the updated cost of consumption and MHR.
    3. If you to consume additional component without GR that means only GI, goto MFBF and select component backflush and enter the component which you want to consume.
    Hope this will clear all your doubts.
    Regards,
    Santhosh.

  • REM Planning table - Capacity requirements and Levelling.

    Hi i have few queries in REM planning table.
    In REM planning table MF50 my selection is based on entire plant. Here in total capacity data tab for any particular plant it will show the list of work centers which are maintained in particular plant to know the capacity details as per our requirement.
    1.When i select any WC line and click on change capacity display from CRP it is giving break up with required and available capacity hours for any particular WC available time is assume 22.5 hrs per day which is given in operating time in capacity header in WC but in MF50 it is showing 23hrs.I have defined shift sequence in OP4A and assigned in capacity header grouping which have 3 shift with 30 mins break in each shift which results in 22.5 hrs working for a day so in shift sequence and operating time it is mentioned as 22.5 hrs is the time available for day but in MF50 it is showing 23 hrs available for day?
    2.What is due% in MF50 total capacity data for any work center and how required time would be calculated?
    Appreciate if any one has any example.
    Cheers
    KK

    Hi bump for any suggestions?
    i have noticed one thing the time available is a round up value actual time available as per capacity header is 22.5 but in MF50 it is showing as 23..if i change to 21.5 then it is showing 22hrs available per day is this the standard behaviour?
    can anyone tell me how the required time is calculated?
    Cheers
    KK

  • Planning Table MF50

    Hello experts,
    Can some one please explain the purpose of the planning table MF50 and how to use it for capacity levelling. I am in a REM environmnt.
    Thanks
    Raman

    HI
    1)In Repetitive Manufacturing, the master plan is represented by the planning table. The planning table is a tool for operative planning and is used to plan the production quantities:
    2) In a repetitive manufacturing environment, planning and control is usually carried out in a period and quantity basis. The layout of the planning table has been designed to support this requirement and is also based on periods to provide a very clear, easy-to-interpret overview of materials and production lines.
    3)The planning table is the planneru2019s/MRP controlleru2019s most important tool for planning the production quantities. At a glance the planner can check production quantities, monitor the available capacity of the production lines and check up on the availability situation of the products produced on each line.
    4)You can directly enter and change production quantities in the planning table. You can assign u2018non-assignedu2019 production quantities to the production lines or you can reassign production quantities to alternative production lines.
    5) You create the production quantities or assign them to the production line in the planning table.
    6 )You can also use the planning table with capacity planning. Here, planning is based on lead time scheduling. The basis for lead time scheduling is the routing. You can access the capacity planning table directly from the REM planning table.
    Regards
    Anupam Sharma

  • Operations are not getting despatched in capacity planning table

    Hi Experts,
    I am using capacity planning table (Graphical) to level the capacities and sequence the process orders. The start date of my orders are very well in future and sufficient capacities also is available in resources. But when I go to CM25 and select one order and click on despatch, system is not despatching it. This is the case for almost all the overall profiles.
    The surprising factor is, this function was working fine earlier without any issues. I havent done any changes in configs which will affect capacity planning.
    What can be the reason for this? Any thoughts please?.
    One more thing. Is there any option to avoid the capacity planning step if Iam using R/3 and manage it by some other way?
    Appreciate your earlier reply
    Thanks & Regards
    Prathib

    Most likely you didnt define the rowsource key properly. Please look under <install>/errors folder for any file there.
    Also, please read the documentation. There is information there about how to troubleshoot a loading problem. Please always read the documentation and we would appreciate feedback on the documentation.
    http://download.oracle.com/docs/cd/E17236_01/epm.1112/iop_user_guide/frameset.htm?launch.html

  • Error message in capacity planning table

    Hi,
    I am  using REM planning table.I enter the planning table by giving the selection criteria of Plant and production line.
    System is giving following error message,
    the error message and dignosis of the error message is given here.
    'No prod. dates for material MTI_FERT011, version 0001, production line 2279'
    Message no. REMPT315
    Diagnosis
    The planned order has no production dates for the combination of material, production version and production line you specified.
    This may be as a result of the following, for example:
    The planned order was scheduled but not using the production line you selected. (The production line is determined by the production version you entered in a planned order.)
    Procedure
    One possibility of finding out what is causing the problem is:
    To access the planned order from the detailed dialog box in the table via "Change" and reschedule the planned order. Check the scheduling log by choosing "Goto --> Scheduling log". More information is displayed in the log's warning or error messages.
    But which master data to be corrected is not known.
    Experts please guide me.
    Regards,
    Ravindra

    Hello,
    I had the same error while working with the REM planning table, despite the consistency of the data.
    Another cause that can lead to the error message REMPT315 is that in the production version detailed screen, "Planning data" table you have entered the routing next to rate-based planning. You must enter the routing (number of the group and the group counter) on the line detailed planning.
    After that, choose check again and try to introduce new quantities in the planning table. It worked for me!
    Irina

  • MF50 : Planning table and planning time fence

    HI,
    I use the transaction MF50 as planning table ( in order to do my MPS planning), I use "set firming date" to fix a firming date.
    Now, I want o know if it should possible to reveal a message when we create a planned order within the firming date??
    Thanks for your answer.

    Hi,
    For clarity , I am describing  below the functionlity of Set Firming date is explained as below:
    By setting Manual Firming date , we extend the planning time fence.
    If a planning time fence has been created for a material then the following applies:
    If the manual firming date lies before the end of the planning time fence, the planning time fence is still valid.
    If the manual firming date lies after the end of the planning time fence, the planning time fence is extended until this date.
    All order proposals with availability dates that lie before the end of the planning time fence of the manually extended planning fence are firmed for the planning run, if the materials have an MRP type which contains firming type or firming type 1 or 2
    The system does not automatically firm order proposals for materials that have an MRP type with firming type 3 or 4, even if their availability dates lie before the end of the planning time fence or manually extended planning time fence.
    Please check if this helps you.
    Regards
    Datta

  • MF50 Planning table

    Hi Gurus,
    I am working on planning table - MF50.
    I want to understand "Relevance of Refresh RS from - Actual Demand & Smoothed Demand".
    What to make a scenario for this for demo purpose showing the clear difference between the Actual and Smoothed Demand?
    Any guidance?
    Thanks in advance,
    Srini

    Create few planned orders and customer requirements with different dates.
    Actual demand - Takes the current stock of requirements
    Smoothed demand - computes the average requirements in the planning buckets and eliminates any sudden surge in demands for example - surge in product demand due to local or regional requirements
    Thanks,
    Srinivas Karri

  • Planning table ( REM)

    Hi Experts,
                 When we opening planning table (mf50) with material selection ,then complete capacity data  section is not appearing& in header view of capacity requirement planning (change capacity display isin grey color).
    we have already set the parameter related to REM senario (e.g,rem profile,prod.schdl.profile,scheduling parameters (PE),w.c capacity data etc).
    where i had mistake ,plz let me know....

    >
    panney wrote:
    > Thanks for reply... I am sending 2 images, please refer the images.The problem is complete capacity data tab is not displaying,so,plz let me know were i have gone wrong.
    Images path:
    http://picasaweb.google.com/112717423459525953218/PlanningTable#
    http://picasaweb.google.com/112717423459525953218/PlanningTable#
    Panney,
    Its a simple problem, you need to assign your resource to the production line field of the production version( use transaction C223 or MM02 in MRP4 view to make this correction). Once the production version has the Production line assigned you should be getting the Capacity data in MF50.
    Regards,
    Prasobh

  • Importance of Planning Table

    hi! Gurus,
    can you please expalin me the importance of Planning Table (MF50).
    i can see the capacity data & material data, with a barchart (Capacity Planning Table). but, wht information i can get from that? how it is useful for planning? because, i felt MD04 can give better information than a planning table.
    and moreover i am unable to interpret the barchart.....it is displaying all production orders in tat week or month. but, whats the use (who needs tat information & for what)?
    i think i clearly explaind my agony....please help me
    with regards,
    SAP Friend

    In MF50,
    You will get many options,
    Mainly you will get the requirement and after running MRP, you will get receipt element(planned orders), This planned orders can be scheduled alone the axis by distibuting the order qty considering the capcity so that you can see that wc is over loadded.
    From here you can create production order or planned order directly.
    See the link below
    http://help.sap.com/saphelp_47x200/helpdata/en/5f/1faba54aee11d189740000e8322d00/frameset.htm

  • Problem in REM Planning table.

    Hi PP Gurus,
    We created one material with REM profile 0004 with MRP1, 2, 3, 4, BD1, 2, Accounting 1, 2, Costing 1, 2 and Work scheduling views. In Work scheduling view weu2019ve not maintained any Production Scheduler and Production Scheduling Profile except Production storage location. Whenever weu2019re accessing Planning table (MF50) getting the errors
    1.     Date adjust. level incorrect: Plant 1001 /ord.type PE / prod.sched. *
    2.     No lead time scheduling: Plant 1001 / order type PE / prod.sched. *
    3.     No capa. data determined: Plant 1001 / Ord. type PE / Prod. sched. *
    One more thing. If we donu2019t put any sales order OR PIR using MD61 Planning table is not showing any details in Material Data rows of Planning Table. And system is not allowing to create any Planned Order manually. What might be the problem?
    If we put any Sales order or PIR using MD61 though the Rows in Material Data get visible but system is not showing any calculation changes in u2018Complete capacity datau2019 rows. We mean to say system is showing Available capacity but not showing any Required Capacity at Production line.
    Thanks & Regards,
    Abu Arbab

    Hi,
    In OPU5 Rate base scheduling active tick mark for scheduling and generate capacity with selection ID 02.
    Scheduling level -rate-based scheduling
    Scheduling type- Backward.
    Then check the planning table section parameter
    SPROProductionRepetitive ManufacturingPlanningPlanning Table--Maintain Entry Parameters.
    Please check scheduling level and other parameters?
    I hope u have not maintained any prod scheduler at work scheduling view.
    Please change this and try again run MRP with planning mode -3 deleted and recreated with lead time scheduling and check the result
    The production line what u have selected at planning table should be same with, production line define at "production version"
    Regards,
    R.Brahmankar

  • Product Group capacity can not be seen in MF50 output

    Dear All,
    I can not see the product group in 'total capacity' subscreen in output of planning table MF50.
    In MF50 the input parameter i am entering is product group and plant.
    In the scheduling tab of input parameters detailed scheduling and capacity planning is tick.
    For some product groups i can see in output as "Product Groups / Total Capacity" and also in the rows below it shows "Prod.Grp XYZ" then requirement and available quantity rows. After which the production line rows follows.
    For some product groups when enter in initial selection screen of MF50 with same input parameters in output i do not see Product group but i can see "Total Capacity Data" and then the rows starts with production lines. But no information on capacity of product group.
    The setup of all product group is same and are created with MM01.
    Regards,
    Vero.

    Hi Rupesh,
    Thanks for reply.
    In 'Control Tab' i am not selecting any parameter. So in output i can see all materials  in 'Material Data' section which are included in product group  irrespective of requirements.
    I have issue in upper half section of 'Total Capacity Data'. I can see the different production line rows with Requirement / Available rows with capacity values in each period. Unit is %.
    But i do not see 1st row for Product group row with 2 subsequent rows (requirement / available) with unit KG.
    I can see these rows only for some product groups but not for all.
    For the product groups for which i do not see these rows have capacity requirement in selected periods which can be seen in same output in production lines rows. (where selection in input screen is product group and plant)
    Regards,
    Vero

  • Planning table

    Hello,
    In planning table MF50 , the row 'not yet assigned ' is displayed from where we can assign plnd orders to any Packign line.
    But when i assign the qty from this row to any other packing line the qty from 'not yet assigned ' is not getting deducted . What settings i need to do ?
    Also can i assign by default some planned orders to any packing line.
    Regards
    ShankarR

    Dear,
    In MF50 select the row of 'not yet assigned and press Shift + F1 period you want then assign the quantity then use copy function and check. Tere you will get Truck symbol click on it you will get assign quantity.
    When you try to assign 50% or less of the quantity to any version, system is taking the correct values in assigned and not yet assigned rows. But when you try to assign more than 50% to any version, system is taking only the assigned quantity as assigned and remaining quantity which is not yet assigned, is not displayed. For that use the OSS note 1104677
    Hope it will help you.
    Regards,
    R.Brahmankar