Activating Process Chains in QA System

Hi All,
  i have transported objects from DEV to QA. all the objects in the QA are in active state but the process chains are not activated and they are in grey state. how to activate the process chains manually. are there any pre defined programs to activate the process chains.
Regards

Hi,
try to do the following..
Got to RSPC and there select ur chain by double clicking it, next go to the menu PROCESS and there u have option called check and activate . So this option will first try to check the consistency of ur chain and then if no problem exists it will activate it.. and in case if prob does exists it will highlight the process where it encountered teh errors..
Hope this helps..
Regards,
Pankaj

Similar Messages

  • Short dump while activating process chain

    Please let me know the cause of short dump while activating process chain.. when trying to activate local process chains in metachain it is causing dump

    Can you share more details about error.
    Have you done any changes to local chain? or is this is new chain?
    Try to remove meta chain from schedule, later activate your local chain and meta chain.
    schedule your meta chain.

  • Trigger Process Chain from Source System into Target System

    Hello...actually in source system BZD, we have a process chain, in the target system BWD, we have another process chain as well. We want to have a process of combining these two process chain together. When the process chain in source system is completed successfully, the system will sent out some sort of signal to start the process chain in BWD. I am not sure how this can be done, I try to use the function module "BP_EVENT_RAISE" in the BZD and when this module is called, it does not start the process chain in BWD after the process chain in BZD is completed. I just wondering am I using the correct method. If will be good if anyone here can help...thanks alot.

    >
    FluffyToffee wrote:
    > Hello...actually in source system BZD, we have a process chain, in the target system BWD, we have another process chain as well. We want to have a process of combining these two process chain together. When the process chain in source system is completed successfully, the system will sent out some sort of signal to start the process chain in BWD. I am not sure how this can be done, I try to use the function module "BP_EVENT_RAISE" in the BZD and when this module is called, it does not start the process chain in BWD after the process chain in BZD is completed. I just wondering am I using the correct method. If will be good if anyone here can help...thanks alot.
    Hi Fluffy,
    Check RFC connection between the two sysems.
    Try using remote process chain process type in the process chain. the fllowing link may help you.
    http://help.sap.com/saphelp_nw70/helpdata/EN/86/6ff03b166c8d66e10000000a11402f/frameset.htm
    Regards,
    sunmit.

  • Problem in activating Process chain in Quality after transport

    Hi All,
    We have moved a set of process chain to Quality system.
    When tried to activate the Process chain it is showing error in DTP.
    The DTP name is same as in the Dev system.
    So, we tried moving the DTP alone in another transport request.
    Still the error exists. We also tried moving the process chain again.
    We had tried importing only the structure and also the entire flow again.
    Nothing worked.
    Please suggest some solution.
    Thanks in Advance,
    Geetha

    Thanks for yor reply.
    Suman,
    I have checked the Object Changeablity now in Dev system, I found it like Not changable for DTPA.
    The DTP from DSO to Cube is fine, but we have problem with the DTP from DataSource to DSO.
    Also, in the dev system when i clicked on Object Changeablity I get a popup like "System can be changed; settings not necessary".
    Please suggest me like what must be done.
    Prashantk & Arvind,
    We imported the Process Chain along with the DTP first and we faced the problem.
    So we imported the DTP alone again, but still we had the problem.
    Again we imported the Process Chain after importing the DTPs.
    So what i feel is DTPs must be there in the Quality, but why we have the problem persisting.
    That too only for DTP from Data Source to DSO but not for the DTP from DSO to Cube.
    Regards,
    Geetha
    Edited by: Geetha Devi Ramalingam on Jul 12, 2011 9:43 AM

  • Errror when activating process chain

    Hi All,
    Geeting the error while activing process chains in Quality.
    Error is *'Node Characteristic 0classnum is not entered as hierarchy characteristic for 0material*
    can any one help on this.
    Thanks in Advance.
    Srinivas

    Hi
    This is not advisable to activate a process chain in quality directly. You should do it in development and then transport it across.
    This error is realated to hierarchy. Do you have a hierarchy load attached to this chain?
    Check the hierarcy first. Then activate the chain.
    Cheers
    Chanda

  • Activation Process Chain, Info Objects, Transformations

    Hi Experts;
    Is there any function or abap program, activates inactive Process Chains, Info Objects and Transformations.
    Please Advice
    Regards
    Bilal

    Hello,
    Find below some activation programs used in BI.
    RSDG_CUBE_ACTIVATE      Activation of InfoCubes
    RSDG_DODS_REPAIR      Activation of all ODS Objects with Navigation Attributes
    RSDG_ODSO_ACTIVATE      Activation of all ODS Objects
    RSDG_IOBJ_ACTIVATE      Activation of all InfoObjects
    RSDG_IOBJ_REORG      Repair InfoObjects
    RSDG_MPRO_ACTIVATE      Activating Multiproviders
    RS_COMSTRU_ACTIVATE_ALL      Activate all inactive Communication Structures
    RS_TRANSTRU_ACTIVATE_ALL      Activate Transfer Structure
    RSAU_UPDR_REACTIVATE_ALL      Activate Update Rules
    RRHI_HIERARCHY_ACTIVATE      Activate Hierarchies
    SAP_AGGREGATES_ACTIVATE_FILL      Activating and Filling the Aggregates of an InfoCube
    RS_PERS_ACTIVATE      Activating Personalization in Bex(Inactive are highlighted)
    Programs for activating process chains and Transformations have not been delivered by SAP.
    Regards,
    Pratap Sone
    Edited by: Pratap Sone on Jul 19, 2010 8:39 AM

  • Error while activating Process Chains

    Hi all,
    while activating the Process Chains, i am getting the following error "Job BI_PROCESS_PSAPROCESS could not be scheduled. Termination with returncode 8"
    when i double click on the error msg, i got the following help msg: "
    <i>Message no. RSPC065
    Diagnosis
    Program RSPROCESS is to be scheduled as job BI_PROCESS_PSAPROCESS under user ALEREMOTE.</i>
    Can any one please show some way to solve this problem? please do this favor, i have been suffering with error for a long time.
    Points will be given
    Thanks
    Ganesh

    Hi,
    Just analyze the error message that you get while activating the PC, don't give any server name.If you are trying to run process chain using Flat file, it won't work,
    and you should have source system R/3 or you have own datasources in BW system itself at that toime you can use PC to extract data. If your source system is Flat ile, it won't work. other wise you should place your flat file in application server, using AL11 tcode.
    <b>OSS : 511475</b>
    <b>Symptom</b>
    You cannot schedule or perform any batch jobs with the BW or source system background user.
    The error RSPC 065 occurs in the process chains:"Job could not be scheduled, termination with return code 8"
    <b>Other terms</b>
    RSPC065
    <b>Reason and Prerequisites</b>
    The user type is
    "CPIC" up to 4.6B
    "Communication" as of 4.6C
    This user type may not execute or start any batch jobs, irrespective of the user authorizations.
    <b>Solution</b>
    Set the type of background user to
    "Background" up to 4.6B
    "System" as of 4.6C
    This user type corresponds to the "Communication" type and may also perform background functions.
    Through the Customizing, the BW user is automatically created by mistake as a communication user.Depending on your BW system release, you can solve this problem as follows:
    BW 2.0B
               Import Support Package 24 for 2.0B (BW2.0B patch24 or SAPKW20B24) into your BW system. The Support Package is available once note 456551 with the short text "SAPBWNews BW 2.0B Support Package 24", which describes this Support Package in more detail, has been released for customers.
    BW 2.1C
               Import Support Package 16 for 2.1C (BW2.1C patch16 or SAPKW21C16) into your BW system. The Support Package is available once note 456566 with the short text "SAPBWNews BW 2.1C Support Package 16" has been released for customers.
    BW 3.0A
               Import Support Package 8 for 3.0A (BW3.0A patch08 or SAPKW30A08) into your BW system. The Support Package is available once note 452632 with the short text "SAPBWNews BW 3.0A Support Package 08" has been released for customers.
    <b></b>

  • BI Content 7.57 SP4 Activating Process Chain

    Hi,
    I am trying to activate a process chain from BI content . My source system is ERP 6.0. While collecting objects for activating this Process Chain BW gives an errors. It says some of DTP and Transformations are missing. I have put two of the errors are at below.
    When i search these missing objects on the BI content these objects are not exist. Also on the BW system they are not exist. I could not find any solution for this problem.
    Can you please show me a way for solving this. I am stuck on this.
    I am trying to activate following Process Chain.
    Technical Name: 0HCM_FULL_P0EMPLOYEE
    Name : Load Data for InfoObject 0EMPLOYEE
    Error 1:
    Shadow object DTP_DYF4USYQ4EYMWILRMUGLXW2KG cannot be expanded; chain is inconsistent
    Message No. RSPC142
    Diagnosis
    You want to determine the objects that are source system-dependent for shadow object DTP_DYF4USYQ4EYMWILRMUGLXW2KG so that they can be inserted in the modified version of the process chain or of a referencing process. This was not possible.
    Error 2:
    Object DTP_ETKRN0DQM7QVOBZSVBC9J61HB (Data Transfer Process,DTPA) could not be collected for object 0HCM_FULL_P0EMPLOYEE (Process Chain,RSPC)
    Message No. RSO296
    Diagnosis
    You have collected objects in the BW Metadata Repository. Associated objects for the object 0HCM_FULL_P0EMPLOYEE of type Process Chain,RSPC have also been collected. Object DTP_ETKRN0DQM7QVOBZSVBC9J61HB of type Data Transfer Process,DTPA was among these objects. This object
    DTP_ETKRN0DQM7QVOBZSVBC9J61HB of type Data Transfer Process,DTPA, is not, however, available in the Metadata Repository.
    System Response
    Object DTP_ETKRN0DQM7QVOBZSVBC9J61HB of type Data Transfer Process,DTPA is ignored in further collections. The links for object 0HCM_FULL_P0EMPLOYEE of type Process Chain,RSPC are incomplete. This may result in not being able to activate this object.

    Hello experts
    I am not able to find support package name.
    When i click on package level button from SAPM tcode
    BI_CONT     703     0000     -     Business Intelligence Content.
    Is my BI_CONT add-on installed successfully?
    And also i am not able to see BI_CONT in imported packages list.

  • Error "Object 'DM' (APCO) of type 'Application' is not available in version 'A'" while transporting process chain to production system.

    Hi Gurus,
    Whenever I try to transport a process chain ZFI_0FIGL_C10 from dev. to qua. & prod. the error “Object 'DM' (APCO) of type 'Application' is not available in version 'A'” is displayed in the end of creating transport package.
    The process chain was created to load data to 0figl_c10 and it works all right on all systems (dev. qua. prod.).
    The process chain contains processes for:
    - starting the process chain
    - executing infopackage (for loading data to 0figl_o10),
    - ACR (activate data in 0figl_o10)
    - delete index 0figl_c10
    - DTP loading data from 0figl_o14 to 0figl_c10    
    - executing infopackage 80FIGL_O10
    - creating index in 0figl_c10
    - building DB statistics
    - rolling up aggregates in 0figl_c10
    - deleting of requests from the changelog 0figl_o10
    - deleting of requests from PSA (0fi_gl_10)
    How to find what cause that error.
    Regards,
    Leszek

    Hi,
    A SAP consultant told me to ignore that error. 
    Indeed, after creating transport with some new process chains (again I was informed about that error "APCO ...") and transporting it to production everything works all right.
    The problem is described in sap note: 883745.
    Regards, Leszek  

  • Process chain - Two source system issue

    Hi Experts,
    I face problem when i transport a process chain from BW DEV to Quality.
    I have two source systems in Quality ECI and EXS.EXS is a sandbox server(Source system) which we no longer use.
    When i transport the process chain from DEV to QA, i get two DTP's automatically added to Process chain in quality for two source systems ECI and EXS whereas i do not want the data to be loaded from EXS client.
    I checked the BW dev system, it has only one DTP in the process chain.
    Now I want to elminate the other DTP in the process chain in quality.
    Please suggest.
    Regards,
    Srini

    I Dont think so a DTP for EXS system has got created automatically when you transport the PC to QA (which actually doesn't exist in DEV).
    Please check you DEV system once again, there might a DTP from EXS system also.. other wise go the Release TR and then check the contents-->iif you find two DTP's there then it is there in the dev system..
    Any ways if you want to delete the other DTP from the PC in QA.. you can Delete it directly from the PC itself.. Goto change mode of the PC and then select the DTP which you want to delete-->then right click and hten Click on Remove Process -->then activate the PC..
    Note: You might have authorization to edit the PC in QA then only you will be able to do the changes..

  • How to activate Process Chain in Production System?

    Dear all,
    We transported the process chain from QA to Production. But in Production they are in hidden mode. Means If i select the process chain, it does not showing any thing. How to I can schedule,  activate and how i can see it in change or display mode in production.
    Please provide helpful solution ...
    Thanks in advance

    Hi Shashi,
    This should not be a basis issue .
    Any how you have to take care of prerequisites like    If you use load distribution for your system environment, the server group (logon group) is reduced to one server before debugging commences or if any auth  issue.
    [Here is all about external debugging |http://help.sap.com/saphelp_erp60_sp/helpdata/en/af/0cb5403fd63426e10000000a1550b0/content.htm]
    Regards,
    Gagan Deep Kaushal

  • BI Admin Cockpit - Problem in activating Process Chains

    Hello,
    We're trying to activate the content for BI Admin Cockpit.
    While activating the process chains, we get a "red" message as
    mentioned below.
    "Object '0PAK_5JTN7F5HTP45CGZ04PQTMCNTI' (ISIP) of type 'InfoPackage'
    is not available in version 'D'
    Message no. RSO252"
    OSS message 966131 suggests that "The InfoPackages mentioned are shadow
    InfoPackages and the message is unnecessary because there should not
    have been a search for the package at all." and we should apply the
    correction (as part of SPS10) for this purpose.
    We are currently on SP11 but still having the same issue and hence not
    able to activate the process chains for BI Admin Cockpit.
    Thanks for your help with this.
    Ashish

    Hi Ashish,
                   We had the same issue. You must have one of following:-
    BI_CONT 702, Support pack 7
    or
    BI_CONT 703, Support Pack 4
    Once you get either of above, you will not have that problem. But you might have some problem in process chains because of roll up of aggregate in delta PC. Just ignore that and you will be OK...( This problem is because there is no agg. defined and PC is trying to do roll up..which make no sense and hence there is error)
    Also refer to OSS note 965386
    This is my first answer to SDN...so assign my first points..:)
    Thanks,
    Anil

  • Do we need to create process chain explicitly nor system generates process

    Hi all,
    Do we need to create process chain explicity in bpc netweaver nor the system generates it internally when we run data managment packages
    thanks
    Pooja

    When you install BPC, there is a set of delivered process chains which are installed as well.  You create the data manager packages from the BPC Excel clicent based on these process chains.  You can of create custom BPC process chains in NetWeaver and create packages from those as well(for example via a How-To guide).   So to answer your question, no, you do not have to create the "standard" process chains, and they are not generated by the system either, they are delivered as part of the BPC installation.
    Regards,
    Rich Heilman

  • Creating the New Process Chains in BW System

    Hi SDN,
    What is the best practice of creating the New Process Chain?
    1. Whether to create the Process Chain in BW Development first and trasferring it through transfer request
    OR
    2. Create directly the Process Chain in the BW Production and schedule it
    Please provide the views.........
    Kind regards,
    Rajesh Giribuwa

    hI rAJESH,
    Ya,we must create any development in development system and then subsequesntly to test and then production system.
    but my exp was differnt in one of my project .
    i have developed the pc in dev first and then trasported to test and then prod,
    it worked fine in dev and test but in prod it was not running ,due to some system resources.
    so i did the change direclty in prod and then it worked .
    but it was risk .
    hope this is helpful
    Jimmy
    dont hesitate to move u r cursor towards the max point

  • Error while activating process chains from Business Content

    Hi All,
    I am trying to activate the SAP Business Content Process Chains, which load data to 0PM_DSO2 in Plant Maintenance Area -
    1.Delta Upload : MTTR / MTBR   (0PM_DELTA_P02)
    2.Initialisation  :   MTTR / MTBR  (0PM_INIT_P01 )
    And they are failing with the error
    "Object  0PAK_BZJNGI4SYTTJM5DXY8IPMHB0C could not be found in version
    Message no. RS_EXCEPTION280"
    "Message Text
    Object  0PAK_EYQGZ09K9SFFUMOFRQ0730LJ0 could not be found in version
    Technical Data
    Message type__________ E (Error)
    Message class_________ RS_EXCEPTION (Exception Messages)
    Message number________ 280
    Message variable 1____ 
    Message variable 2____ 0PAK_EYQGZ09K9SFFUMOFRQ0730LJ0
    Message variable 3____ 
    Message variable 4____  "
    In the collected objects, these two infopacks are not present also.
    Can you please let me know how to proceed?
    Many Thanks in Advance,
    Vineeth

    Hi
    Make sure these 2LIS_17_I0NOTIF and 2LIS_18_I0NOTIF datasources are being installed.
    Check these links.
    http://help.sap.com/saphelp_nw70/helpdata/EN/e7/082888ca2f994794986448568aec2d/frameset.htm
    http://help.sap.com/saphelp_nw70/helpdata/EN/e7/082888ca2f994794986448568aec2d/frameset.htm
    Chandu.
    Edited by: Chandu on Jan 22, 2009 2:24 PM

Maybe you are looking for

  • Attachments in a news scenario

    I create a standard News scenario. I want to insert an attachments field in the Edit form and i want to display the link in a Show form. How i can do? Thanks, Michela I use EP 6.0

  • ABAP Debugger: assign user to external breakpoint

    Hi, when I assign different users to an external breakpoint the program still stops when it is executed with the "original" user which is not assigned to the BP anymore. Has anybody any solution for this behavior? The procedure I use is the following

  • Local file in background mode

    Hi experts, Is it possible to upload data from local drive(presentation server) to sap in background mode. As I know ,in the background mode we can upload files from application server only. but here my functional consultant saying they did  upload d

  • I hate iPhoto '11 for emailing pictures

    Is there any way I can disable the email portion of iPhoto '11? Since I come from a blended family, I often send multiple sets of the same family pictures out using Mac mail. In the "old days" (before iPhoto '11) I could send a batch of pictures, fin

  • Query doesnot show data

    Hi experts we have one data validation query where I am trying to see data according to Request numbers...For every year we have two requests...one Base data request and other Restated data request... Like that for 2009..its showing data for Base dat