Actual capacity after confirmation

Hi,
How can I get the actual capacity per day.
in CM01 I see the capacity requirement and the available capacity.
When you confirm all the orders in a day you have the actual capacity it can be different
with the capacity requirement.
I need the actual capacity after the confirmation.
Thanks
Dede

Dear Dede,
As i could'nt undrstand ur requirment, but per my understanding
1) The Moment We do final confirmation to Production order
2) then all the remaining Capacity requirments of that order will set to Zero
Regards
kumar

Similar Messages

  • Actual Activities not appearing after Confirmation

    Hi,
    I got a situation where in we are using CO11 for confirmation.
    We have 3 Activities in the Std Values viz, Machine, Labour and Actual Weight
    After entering the Yield Qty and pressing Actual Data, Machine and Labour are appearing, but Actual Weight is not Appearing.
    Necessary settings in OPK4 and OPK0 are already in place.
    Please guide.
    Thanks in advance,
    Harris

    Hi,
    Thanks for the prompt response.
    - System is calculating the Activities as required in the Production Order which i can see in the details information of the Operation.
    - They are using CO11 for the confirmation.
    - There is no Manual entry at the time of Confirmation.
    - In OPK0 Default Confirmation Profile SAP001 is being ticked marked.
    - Default Values , Qty and Service in OPK0
    Procedural Steps for CO11:
    - I run CO11
    - Enter Production Order No. and give enter
    - Here it shows the Yield Qty
    - Then i press ACTUAL DATA icon and i get only the Machine and Labour Activity, but not the ACTUAL WEIGHT.
    Procedural Steps for CO11N:
    - i also tried running it in CO11n
    - Here i enter the production order no. on the time ticket screen and give enter
    - Here too only Machine and Labour is seen, Actual Weight is still missing.
    - Then i once again hit ENTER and i am getting the Actual Weight Now.
    - But as soon as i press Actual Data button, the Actual Weight disappears and the field appears Blank.
    It is very strange, but this is the problem.
    Please guide
    Thanks and regards,
    Harris
    Edited by: Harris Panchal on Mar 12, 2010 3:19 PM

  • Actual Cost Machine hours is zero (After confirmation)

    Dear Guru,
    We are implementing PP module and product costing. We enter the budget with activity type in KP06 & KP26. After confirmation, the actual cost in machine hours is zero but not in electricity or steam. Why the actual cost is zero in activity type machine (we enter the actual qty machine hours) ...
    May you assist me to solve this issue
    Thanks
    Maju S

    Dear Umapathi G & Shaubhik
    Thanks for your replay.I have checked the Control key is marked for costing and the cost center is assigned correctly and we have executed the KPSI before and I found the fixed price for Machine hours in tcode KSBT and cost center is not locked for posting secondary CE
    For additional information, we have 3 activity type, Machine hour, Electricity and steam. The actual cost for electricity and steam are not problem, only for actual cost activity machine is zero. The issue only for activity type for machine.
    May you have me to give the other solution to be checked
    Thanks for your replay and I am really appreciate it
    Maju S

  • Capacity releasing after confirmation

    Hi,
    My requirement is as follows
    Having one service order with 2 operations (each with 8 hours work and 1 capacity).After creation and releasing of order,I can see the capacity loading in CM01 for daywise . Now If I confirm the operations well ahead of the planned time and my issue is it's not reflecting in CM01.Logically speaking,after confirmation of operations in orders there should not be any requiremets pending.Will this reflect anywhere.If so pl share with me.
    Regards
    A.Sureshbabu

    A.Sureshbabu,
    The main profile is linked to many other profiles... Its a bit of a nightmare to set up.
    Basically these profiles determine which data is selected, how it is displayed and what functions are available
    PeteA

  • Network Activities update issue after confirmation

    Dear,
    In our PS projects we are using one network header (with backwards scheduling) with both internal (PS01) en cost activities (PS03). The cost activities are linked to two internal activities to establish a cost spread.
    For example Cost activity 1 is linked to internal activity X and Y=
    Cost activity 1 has a SS relationship with internal activity X
    Cost activity 1 has a EE relationship with internal activity Y
    => as such the planned costs defined in the cost activity are spread over the planned period between internal activity X and Y
    Now when you do a confirmation of a internal activity, e.g. X, then the planned dates of the cost activity are not updated with this actual dates of the linked internal activity
    => a

    hi
    after confirmation have you run the schedule project/network.

  • CO12-Yield quantity shown is zero even after confirmation with correct qty.

    Hi Experts,
    While confirmation using CO12- collective confirmation, i get a message "Total confirmed quantity does not equal planned quantity"( ECC6.0 system). Moreover for  few plants, the yield is zeroed out, eventhough i enter the planned qty and after confirmation is executed, the yield shown is zero for those confirmed operations.
    1. Why does the message "Total confirmed quantity does not equal planned quantity" appear eventhough i enter the planned operation quantity for confirmation?
    2. Why does the yield quantity zeroed out for some plant? (maybe for some material)?
    Any pointers would be of great help.
    Thanks,
    SudhaharN

    Hi,
    Answers to your questions are,
    1. Why does the message "Total confirmed quantity does not equal planned quantity" appear eventhough i enter the planned operation quantity for confirmation?
    Total confirmation quantity for that particular operation is exceeding the actual Qty.
    You can check in CO14 how much it is already confirmed.
    2. Why does the yield quantity zeroed out for some plant? (maybe for some material)?
    Check setting in OPKI (for collective conf) wether you have selected the option Qtys immeed.
    This will propose you the remaining qty in CO12 you need not to enter.
    Give points if this is useful.
    Regards,
    Vinayak.

  • 85% current capacity after 4 cycles in Macbook Pro Retina.

    Is it normal that I have only 85% current capacity after just four cycles in Macbook Pro with Retina Screen? A little bit over 7140 mAh compared to 8460 mAH in design capacity?
    Should I call Apple Support?

    Hey Allan,
    Greetings!
    Yes you rightly pointed out the changed format
    And I have been around for a few years but mostly get active whenever I purchase a new Macbook. you know how the honeymoon period is
    Unfortunately I am experiencing two difficulties myself which I haven't been able to figure out.
    I have this late 2013 Macbook pro Retina, 13". Purchased it 20 days ago!
    Now the two problems are
    1. Safari sometimes doesn't load some pages and apple.com being one of them. Again as I read somewhere when opened on the Chrome and then back on safari almost at the same time, safari pulls it up.
    I dont prefer other browsers as my battery discharge becomes rather quick on chrome doing the same task.
    Do you hav any idea what might be wrong. I tried switching of all extensions and plug ins. Also did a few resets.
    Read somewhere that it has to do something with the DNS of the router but then why this erratic behaviour and not a consistent one.
    2. My battery is also showing erratic behaviours. The max health varies between 6350 to 6673 (Didn't see the later for last few days). Also the life the system predicts vastly varies doing the same tasks. Sometimes if I am reading a page online it would show 14 hours on 100% and sometimes just 7-8.
    The worst part is that the it just doesn't show it that way rather behaves the same way. That means that battery actually drains at the rate the sytme predicts.
    Also even in shut down (and not sleep), the system tends to use charge at a rate of 1% per 8 hours.
    All this mentioned in the paint 2 started happening when my machine got drained to 1% power remaining once and the other time was shut down as I was travelling and didn't have the charger. Is that to blame?
    Any input would be appreciated.

  • Iphone 5 16 gb actual capacity

    in a 16GB Iphone 5 how much actual capacity do i get, after os6 installed, basically how much free space do I get in a brand new iphone ???
    Reg
    Vikram.R

    and which one do you advise 16 GB or 32 GB, I can compromise on the audio and photo and also planning to use icloud is it a good idea to get 16 GB since the prices here in India are very expensive.

  • Open follow up transaction type screen automatically after confirm account

    Hi Gurus,
    I have a transaction type Z010 for interaction record that is copied from standart 0010 transaction type.
    I define dependent transaction type SRVO that is service order as a follow up of Z010
    My requirement is to open automatically open service order screen after confirming account
    As agents must do everything vey quickly while they are on phone, it is needed urgently.
    Now they have to open Z010 interction record screen, have to press follow up button, click to clipboard and then can open the scrren of service order.
    How can we automatically open service order screen after confirming account??
    I will be very pleased if you will help...
    Thanks.

    Hi Denis, thanks for reply.
    I read it and see that interaction record is automatically created. How can it be made, is it a standard customizing?? Our interaction record is created automatically when follow up process-it is service order here- is created. First we confirm customer, then press to Interaction Record at the left hanside, then in this screen we press follow-up button, then click on Activity Clipboard, then service order screen is opened. I want to pass two steps, pressing Interaction Record and pressing follow up record, how can I do this??
    Exactly I have to define process type Business Activity for interaction record, I can't give Service Order process type directly to interaction record. Service Order type must be dependent to business activity, is it true?? If there is a way to directly giving service order type as an interaction record type, and making interaction record creation automatically after confirming, my problem is solved as very well.

  • Deletion of Delivery after confirm of Pick and WM TO, should not be allowe

    The system will allow a delivery to be deleted after confirmation of Picking and WM TO. This creates all kinds of issues in WM for tracebility. Is there any way to prevent this from happening through config in WM or SD?
    Edited by: Daryl Dellinger on Jan 30, 2008 3:51 PM

    Try OSS notes 567666 - stock inconsistencies after deletion of delivery items
    Regards
    Edited by: Shiva Ram on Jan 30, 2008 8:32 PM

  • Vendor marked as purchasing Block after confirmation of Vendor through FK08

    Hi ,
    We  are having SRM 5.0 Add On System. While Creation of Vendor In ECC system it goes for Confirmation First.
    So in SRM Vendor Remains as Blocked for Purchasing in Table BBPM_BUT_FRG0061 as Vendor in ECC system also remains as blocked for Purchasing.
    Confirmation FK08 is done by different user. After Confirmation in ECC system vendor get unblocked for Purchasing but in SRM it remains as blocked for purchasing.
    So Purchasimg Blocked is not removed in SRM.
    If we are removing the block tick by Changing the Vendor(XK02)  then in SRM Vendor get unblocked automatically.
    Expecting reply at the earliest.
    Thanks & Best Regards,
    GK

    Hello GK,
    Behavior you describe is the standard one.
    FK08 is to confirm vendor modification regarding accounting data, that is at company level.
    So, purchasing organization data being not concidered, vendor is unblocked for posting (all companies or selected company) but not for purchasing.
    Regards.
    Laurent.

  • Qm order after confirmation of activity

    Hi, Please advise what are all the steps required after confirmation of qm order at the time of results recording. like do we need to deactivate the asignment of qm order, settle it, close them etc. please advise the steps involved.

    Dear Raju
    You need not do so
    The QM orders are like internal order which is settled using K088 or using CO88. You may check the CO guy regarding the settlement rule and activity costs
    Regards
    Gajesh

  • Standard available capacity Vs actual capacity used in W/C

    Hi Gurus
    Can some tell me the tcode for a report which will give me the "Standard available capacity Vs Actual capacity used" for a Work Center?
    regards
    HR

    HR,
    It is unclear to me how this report falls short of your requirements.
    CM01 displays  Capacity requirements (load), Capacity available, and percentage of requirements vs available.
    http://help.sap.com/erp2005_ehp_06/helpdata/EN/89/a41dd8461e11d182b50000e829fbfe/frameset.htm
    Other ways of evaluating the same data:  CM02, CM03, CM04, CM05, CM07, CM50.
    I suggest you work with the standard reports for a while before you consider changing them.  However, you can alter the standard cap evaluations in many ways.  Review
    http://help.sap.com/erp2005_ehp_06/helpdata/EN/91/dcac7377be11d183b30000e83235ee/frameset.htm
    Config starts at IMG > Production > CRP > Evaluation.  Work downward from there.
    Best Regards,
    DB49

  • Not directed to Interaction Record automatically after confirmation of BP

    Hello Experts,
    i'm currently working on a requirement to direct a user to the Interaction record creation view automatically after confirmation of an account and installed base. Consequently i have maintained  following customizing setting within our account identification profile:
    Account Navigation:
    Object type = BT126_INR, UI Action = D
    I have tested the following scenario's:
    1. In case when i confirm an account AND installed then automatically the Interaction Record create view is being displayed --> OK.
    2. In case when i confirm an account which is not linked to an Installedbase then nothing happens. --> NOT OK
    3. In case when i confirm an installed base and the related account afterwards then nothing happens --> NOT OK
    Can you explain why in situation 2 & 3 i'm not directed to the Interaction Record create view?
    Regards, Sander

    Hello, Sander.
    First of all identify which view and component you use while confirming partner (e.g. which view/component Confirm button belongs to).
    In general it should be ICCMP_BP_DETAIL component and one of its views: BuPaDetail, BuPaDetailB2B or BuPaMixDetailB2B.
    For instance, let's take a look into BuPaDetail (for other views procceed in the same way).
    In its event handler EH_ONCONFIRM there is such code at the very end:
    * process further steps
    CALL METHOD me->process_after_confirm
       EXPORTING
         ir_bupa_controller = lr_cucobupa.
    ENDMETHOD.
    Let's go futher and step into this method process_after_confirm. Here the check is started.
    * navigate only if ibase has been confirmed or if ibase is not selected in customizing
    lr_objcomp_cust = ir_bupa_controller->get_objcomp_cust_instance( ).
    CHECK lr_objcomp_cust IS BOUND.
    lt_bpcodeta = lr_objcomp_cust->get_bpcodeta( ).
    IF lr_objcomp_cust->objcomp_defined( ) EQ abap_false.
       lv_navigate = abap_true.
    ELSEIF  ir_bupa_controller->is_product_confirmed( ) EQ abap_true.
       lv_navigate = abap_true.
    ELSE.
       READ TABLE lt_bpcodeta WITH KEY auto_search = abap_true ASSIGNING <fs_bpcodeta>.
       IF sy-subrc <> 0.
    *      auto search is not set for any component
         lv_navigate = abap_true.
       ELSE.
         IF <fs_bpcodeta>-search_approach IS INITIAL.
           lv_navigate = abap_true.
         ENDIF.
       ENDIF.
    ENDIF.
    And after that the system creates objects for navigation. In the above code they check settings made in SPRO -> CRM -> Interaction Center WebClient -> Master Data -> Define Account Identification Profile.
    Hope this will help you.

  • 24 fps in Pal - after confirming attribute changes gives me a scare

    Dear Friends, I am currently editing 35mm Film on fcp, I would like to mention my workflow so that if there is something missing, someone can point it out (Please) Telecine 25 fps - Imported the atn files in to cinema tools and exported batchlist to fcp, imported batch at 24 list in fcp Pal DV 25 proj, loaded the material and confirmed it to 24fps through cinema tools, relinked it in fcp (now here is what i am scared about, when i relink it says some attributes have changed, is this normal, is it suppose to give me this message) after relinking i put the shots on 24 fps seq for 24fps edit.
    I had few problematic telecines and keylogs, so i decided to change the database and relink the shots manually, While connecting few clips to database, cinema tools messaged, it has trimmed the shots so that it can generate correct cutlist, now is this normal, or am i doing something wrong. my cutlist generated are perfect anyway.
    1. changed attributes after confirm.
    2. trimmed shots by cinema tool for correct cutlist.
    Thanks
    Macbook pro   Mac OS X (10.4.7)   2 GHz

    It did the same for me on a feature I have now finished. Neg cut, conform and DI all perfect. It is a worrying warning, but you get use to it.
    Search the forum for pal 24 at 25. A few posts on a number of issues which make PAL24 a bit tricky.
    Good luck
    John

Maybe you are looking for

  • Hey Apple when are you going to fix the problems with IOS 8.3??

    Hey Apple when are you going to fix the problems with IOS 8.3?? Message is working weird. I don't have internet service when I'm away from my WiFi, because my phone won't use LTE now. Should I wait for a IOS 8.3.1 update or reset my phone to factory

  • [SOLVED] make fails but makepkg works fine (when building zathura git)

    Hello, when I build the "zathura-girara-git" AUR package with makepkg everything works fine, but if I try to build zathura after cloning the git repo make fails with some errors. make output from makepkg: zathura build options: CFLAGS = -march=native

  • ITunes and Windows Server 2008 (32-bit Enterprise)?

    I tried installing iTunes 7.2 and 7.6.1 on my 32-bit Windows Server 2008 testing machine. It seems that 7.2 (with the standalone Quicktime 7.1.6 installed first) installed without any problem, but 7.6.1 seems that it cannot install some components (s

  • Created email account does not appear in list

    Having problems setting up emails in z10, go through advanced setup. Some accounts keep greeting error message, others just disappear and are not listed

  • Patch Info needed

    I am on 11.2.0.1 on RHEL Linux 5.6 and on Standalone single instance Grid Infrastructure , lets say i want to apply a patch, assuming this patch needs a shutdown of all components, So apart of Database instance and Listener running from grid home, wh