Actual cost of product in COPA

Dear all,
I am relatively new to COPA functionality.
The requirement is that actual cost of product should be reflected in COPA and not the planned.
Kindly give me the background also, as in the integration of COPC and COPA.
Thanks in advance

Hi,
Sudhakar is completely right in his comments. But, I would not just accept that actual costing is not active, so you have to find a solution without it. Your requirement is a good reason to activate actal costing, and calls for it.
The way SAP foresees to bring actual costs into CO-PA would be:
Activate material ledger / actual costing
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/a5/320e28d56c11d295c200a0c930328a/frameset.htm]
Calculate periodical actual prodcut costs at period end
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/ec/f835d7f08311d185810000e8a4bacc/frameset.htm]
Revalue CO-PA at actual costs with KE27
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/f5/0f0739edfcb03ae10000000a11402f/frameset.htm]
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/7a/4c39be4a0111d1894c0000e829fbbd/frameset.htm]
That brings you a completely integrated and accurate solution for actual product costs in CO-PA
best regards,
              Udo

Similar Messages

  • Actual cost of material in COPA

    Hi Team,
    We have implemented PP, CO & COPA  our client has the requirement to see the actual cost of material in COPA as per their requirement we designed the KE30 report as product wise profitability report in that report we used the record types B( direct postings from FI), C(Order settlement), D(over head cost) from the copa assessment cycle & F ( SD billing).
    1) Is it possible to see the actual cost of material( Including activity cost) in copa.
    2) If it is possible please advise.

    Hello
    It is not possible to get the actual cost of the material in COPA. Actual cost can only be derived if you implement material ledger.
    However in COPA we may come close to actual cost to some extent. The following configuration needs to be done:
    1. Run standard cost estimate every month so that the price reflects the most recent material prices.
    2. Define assessment cycles for auxiliary cost centers (whose cost should form part of inventory cost) to production cost centers.
    3. Configure for splitting and revaluation at actual price.
    4. Take the production variances to COPA.
    5. Create a report to show the standard cost and variances.
    One of the difference is that the total standard cost is for the quantities sold during the period however the variances will be for the quantities produced during the period.
    Another difference is that the unabsorbed overheads could not be allocated to individual materials.
    Hope this helps.
    Sangram

  • Function module for calculating planned and actual cost of production order

    Hi ,
    Do we have any standard function module for calculating planned and actual cost for production order?
    i need to implement this in a Z-report.
    Thanks
    Srini

    Hi,
    try below function module
    CRMCO_GET_PLAN_ACTUAL_COSTS
    CO_IH_GET_PLANNED_COSTS_TOTAL
    Regards,
    Sankaran

  • Actual cost of Production Order settled to Fixed Assets

    Dear all,
    My client is doing in-house production of moulds (internal order suggestion is not accepted by the client) for which
    they have the following
    1. BOM
    2. Machine hour
    3. labour
    4. overhead etc
    5.plan value
    6. actual value
    Can i settle the actual cost of production order to Fixed Asset ?
    If yes
    what are process kindly give me if any process other then the below
    1.production order created
    2. settlement profile - FA is settlement optional
    3. allocation structure
    4. Asset created
    5 define asset in settlement rule
    Kindly give me your valuable input
    regards
    elango

    Hi,
    Although i am not CO expert , please check with your FICO consultant who are expert before make the final call.
    During settlement to a G/L account or a fixed asset, the system ignores additional account assignments that were manually specified in the distribution rule.
    Based on what i know .
    you can stipulate that settlement may be made to cost centers and orders, but not to fixed assets.
    The Settlement profile is something that you need to create a settlement rule to settle the actual costs of a sender object.
    About the Settlement rule is something that  contains the distribution rules for the sender. It will define how the way to settle the cost.
    Allocation Structure
    In the settlement structure you combine the primary and secondary cost elements into groups, in which debits are then posted to the sender objects. For each group, you specify whether (for settlement to a given receiver type) settlement is performed
    by cost element or using a settlement cost element.
    For example, you might use settlement cost elements:
      To document the purpose of an order (such as, repairs or maintenance)
      To reduce data volumes (you can combine a number of debit cost elements
    under one settlement cost element).
    TQ

  • Table of Actual cost of production

    Hi Experts,
    I m developing one Z report for our client which shud contain Standard cost & Actual cost of production of the sold material for that particular month.
    I am following KKBC_PKO tcode for the same.
    Standard cost & Actual cost has a part of secondary cost element.
    Can I know which table will have Actual cost details to present in above mentioned report??
    Thanks in Advance.
    Madhu.

    Dear Madhu,
    Table COEP will help you to check the actual cost.
    Check and revert back.
    Regards
    Mangalraj.S

  • Actual Cost of Product with Price control "S"

    Dear Gurus,
    Is there any report available where we can know the Actual Costs of Materials with Price Control "S".
    In the material master field the actual cost in the "Moving Price Tab" of the material with Price Control "S" is available, but is there any report available for plant level?
    Thanks & Regards,
    Amit Dhanurdhari.

    Hi Amit,
    -- Under Standard Costing, you value your inventory at Standard Costs and any variances in Production Process will be settled to Price Difference Account. You will not be able to find out actual cost per unit. In Multi-level BOM scenario under Standard Costing (CO-PC), variances don't get rolled-up to the next level, only costs get rolled-up.
    -- Under Actual Costing - Material Ledger, You will be able to find out the Actual Cost per Unit. Variances get rolled-up to the next level.
    To explain difference between Standard Costing in CO-PC and Material Ledger briefly....
    You have given Price Indicator as "S" in the material master of "X" material (semi finisher or finished) and you are doing Standard Cost Estimate for arriving at Standard Cost per tonne. Let's say, the Standard Cost per tonne is Rs.1000/-
    Now, when you created production order for 10 tonnes and received output of 10 tonnes (GR). But the total cost incurred on that production order is Rs.1100/-. In this situation, actual cost per tonne is Rs.110.
    But, because you are following Standard Costing, When you post GR against this Production Order, inventory will be posted at Standard cost only, i.e., Rs.1000/-. and the balance of Rs.100 will be posted to Price Difference Account. (and parallally the variance of Rs.100/-) will flow to COPA.
    So, it is clear that, though, at Production Order level you can see the actual cost, at "material" level, you will not be able to see the actual cost per tonne.(as long as you are using only Product Costing and Standard Costing)
    Alternatively, if you maintain Price Indicator as "V", you will able to get the Actual Cost per tonne at material level, but there will be no scope for establishing standard cost and comparison with actual thereof.
    But, the same is possible if you are using Material Ledger (CO-ML). If Material Ledger is active, you will be maintaining "S" in the material master, still, the variances will be settled inventory and you will be able to get the actual cost per tonne. (bothe Standard cost estimate, actual cost per tonne will be possible).
    Pls revert back for further explanation
    Srikanth Munnaluri

  • Price differenc value in Actual cost of Production

    Hi,
    We are creating a production order for Billets that is our Semifinished goods. The material master is maintained at Std price.
    Lets say that Std prce of the Billet is 100.
    Lets say that after the production order is completed , the actual cost of Billet is comes out to be 125.
    Now this billet is used for the production of the finished goods Wires. For the production order of wires, the price of the billet is taken as 100. 
    In this way the actual cost of the Wire will not come.
    May be this is the standrad process. Let me know in any way can we use price difference of 125-100= 25 in the production cost of wires so that I can get the actual cost of the wire.
    We are not using Material Ledger.
    Any suggestion
    regards

    Thanks Ajay,
    Even using ML we cannot get the actual price before the end of the period. And at the month end only we can valuate the inventory withe actual cost. I hope I am right till now.
    Pl correct if I am wrong.
    But in this case some wires rods are already out from the inventory for the sale that was valuated with the Std Price of the Billet.
    Hence these invenories will  not be available at the month end for the revaluation.
    Pl. correct If my thought is OK.
    ML can only be used where ther is lots of Raw Matl price variation..Hence I think I should go with the std price valuation itself.
    regards
    Kamlesh

  • Actual cost of production order in inventory valuation

    Hi,
    Kindly tell me in our client requirement to "capture actual cost of drum manufactured. This cost will go to finished mixer. So actual goods receipt of drum should be with actual production order cost . Also actual mixer cost should be taken from actual production order cost. How to map this s cenarionin in SAP" ?
    Best Regards,
    Anindita

    Hi Shyam,
    In SAP product costing we use generally standard cost estimation. Raw material ara taken as moving averagae price as v and finished products are taken as standard price i.e, S. Before cost estimation we update plan price in material master costing view 2 for accurate cost estimation. In case of standard cost estimation price variance is occured which is post to separate gl account. Our client wants actual cost rather than standard cost. Without implementing material ledger is it possible to do actual costing in SAP. Please let me know the process of actual costing...
    Regards,
    Anindita

  • No actual cost in production order

    Hello,
    We just create a new plant in our SAP system, and create a new production in this plant, but there are no actual cost occured after confirmation although there are plan cost in cost analysi, I check the following areas:
    1, cost center, we maintained the price for activity types in KP26
    2, costing variant and valuation variant
    3, confirmation, there are posted quantity of activity types
    4, routing in the production order
    But I can't find the reason.
    When I use COFC, found the error that said no actitivy type price maintained, but we don't use this activity type for this production order's work center(cost tab).
    When I go to cost - itemization, the activity types are what we don't maintained in workcenter(cost tab)
    Any body can help me?
    Thanks,
    Richard

    Hi richard,
    Pls check that in kp26 transaction, which version do you select in the entry screen. Also the period for which the prices are maintained.
    Moreover, if your work centers use that activity type, only then it will show up in your cost itemization.
    Pls confirm the above and revert back.
    Awaiting for your confirmation,
    Regards,
    Ankita

  • Actual Costs for Production Order

    Hi All
      I have a scenerio where they dont want any product costing methods say WIP,Variance calculation & Settlement.
      When the Goods receipt is done for production order the actual costs and the Activity costs to be valuated.
    Regards
    Jayshankar.A

    Hi,
    In our case the Standard price is updated in the material master. For this, you need to create a costing estimate using T-Code CK11N and update & release in CK24.
    When CK11N is executed the standard price is calculated for the material by taking Moving Avg Price of RM (Price indicator V) and the activity costs are calculated as per data given in KP26. These cost components are added and a final cost estimate is prepared, which is updated using T Code CK24.
    the pre-requisites are:
    1. BOM should be maintained.
    2. Routing should be made.
    For executing the same procedure for all the materials, you can use T Code CK40N.
    Hope this is what you were looking for.
    Revert for further details.
    Regards,
    Rohit.

  • Actual Costing in Production Order

    Dear All,
    We are in Production Client.I have created cost estimate and moved to material master.
    PP has created a production Order and confirmed the activities.
    When I view the costs from CO03,i can see the target costs perfectly,but actual costs are not apprearing in the order.
    We have 6 activity types and out of 6 ,we have costs for 5 activities and for the remaining 1 activity ,plan qty is maintained ,but there is no plan cost.Is because of this ,actaul costs are not coming in to order? Or any thing is missed out ?  
    Please share any idea on this issue as we are in production.
    Regards
    Su

    Dear Mr Ajay,
    Sorry for the information given in the previous one as I have given wrong Order No.while checking.
    I have checked once again with the correct order.When I checked COFC ,System has given the error messages for the Setup activity type for which price is not available in the system as no costs are planned for the activity type as we don't  have setup hours for this month,but qty is planned and PP has confirmed the set up qty.
    Is because of this issue ,actual costs did not appear in the order?
    To my knowledge ,as I said we have 6 activity types,out of which there is no cost for setup,hence system is throwing a error for no price for that activity.
    But the system can capture the actaul costs for the remaing 5 activities for which prices are available.
    Regards
    Su

  • Actual cost in production order

    Dear Guru's,
    Please note the following scenario: For a production order of 100 pcs if I wastes/scraps 15 pcs in opeartion then how to capture only the cost of 85 pcs in production order? Please suggest the settings.
    Regards,
    SAP CONS

    Y U want cost for Only 85. It should be for 100
    For Ex
    f0r opern 10 
    Lets take Cost incurred for operation 10 for 100 qtys is 1000 rs
    In Operation 20
    If the cost incurred for 100 is 500, Consider 15 qty as waste
    In operation 30 cost incurred for 30 for qty 85 is 400
    Then the  actual cost incurred for the prdn  is operation 10 + Operation 20 + operation 30
    It should not be for qty 85.
    Edited by: Sundaresan . E. V on Jun 17, 2010 5:57 PM

  • COPA how to analyse sales by actual cost (MTS) ?

    Hi All,
    We use Make-To-Stock production type.
    I want to make a drilldown report for sales analysis use actual cost (COGS + production variance), how to link production variance to sales data.
    Any suggestion will be appreciated.
    Thanks & Regards
    Sam

    Hi Sam
    As I said, you can tag variance of FG upto some extent to the COGS of FG...
    Also note that, w/o ML, variance is disposed off in the month of mfg, where as COGS comes in the month of sale... For eg: You mfr 100 Kgs @ Actual cost of 120, where as your std cost is 100... You sell 50 kgs in Month 1 and 50 kg in month 2
    In Month 1
    COGS = 50 (@ std cost)
    Variance = 20
    In Month 2
    COGS = 50
    Variance = 0
    Variance analysis w/o ML is always limited.. At best what you can do is draw your COPA reports on YTD (Year To Date) basis... Assuming that your closing and opening stock is more or less the same, your variance related to FG can now be analysed with COGS and revenues....
    Also, if your prod order for FG is tagged to sale order on account of MTO scenario, your COPA doc for variance will have customer info as well
    With ML in place
    Variance of SFG can be rolled upto FG... i.e. Say, variance in SFG is 20 USD... Std cost of FG is 125 USD... When you roll up the variance to FG, your FG valuation will become 145 USD....
    Also, if part of the FG is sold off, then prorata variance will go to Inventory and the rest can be taken to COGS.. i.e. not only FG, you can also revaluate your COGS with ML...
    Regards
    Ajay M

  • Material Ledger : Actual Cost settlement to Consumption Accounts

    Dear CO Experts,
    We are aware that when we run CKMLCP, all variances (in the Price Diff GL Account) due to Material Prices flutuation, diff in Standard & Actual Cost of Production, etc. would finally get settled to Consumption or Stock Account in its appropriate ratios.
    Consumption Acount GL is a Cost Element with Cost Category as 1.
    There can be cases, when there are diferences in Production Order, due to fluctuations in Prices or Actual consumption is more than standard consumption.
    When a Production Order is settled the difference is posted to Price Diff Account.
    When a Material Ledger (Actual Costing) is executed, Price Diff Account is targetted to be Zero. The Price Diff is then splitted in Stock & Consumtion Account in its appropriate ratios.
    Main Question :
    Since, Consumption Acount GL is a Cost Element with Cost Category as 1, what shall be the CO Account Assignment Object, when the ML value is settled to Consumption Accounts.

    hi merchant..
       1. Price diff between stnd and act is initially goes to PRD a/c through OBYC setting at the time of GR/Invoiceing/Issue if mat is set as S&3.
       2. In case of mat set as V&2 idially there should not be any diff but may arise some small amount due to "no or less stock qty" at the time of invoicing.
      3. When CKMLCP is run these price diff & order settlement diff splitted to cons and stock as you mentioned.
    Now your question :
      " Since, Consumption Acount GL is a Cost Element with Cost Category as 1, what shall be the CO Account Assignment Object, when the ML value is settled to Consumption Accounts"
        Cons GL is cost element cat 1 for capturing mat mov for Issues to orders/cost centres,oth co obj for primary posting at stnd price.
        Now at the time of CKMLCP run you revaluate the materials and price diff are splitted to cons & stock and goes to mat to calculate act cost (stnd +/- prd).
    I think this will give you some light on your issue.
      kkumar

  • (project system) do book confirmation amount as a actual cost

    HI all
    it is possible in project system when i confirm my activity then it does not book actual cost to my network activity.
    because i need to show this confirm amount as  only for information purpose....my clint requirement.
    thanks

    with the material ledger, actual costs are not only used to value the stock at the period end. You also have the possibility to revalue the cost of goods sold with the actual costs of production for the period.
    The system takes initial stock, initial value, production of the period, actual costs of production of the period to calculate "cumulative stock of the period" and "cumulative value". The cumulative value per unit is then applied to all consumption of the period (goods sold) and the final stock.
    Your only alternative to the material ledger would be to value yout finished goods at V-price, not S-price. The problem with this is that you don't necessarily have all the information about actual costs at the moment your finished product enters stock. For example actual activity prices can only be reasonably calculated per period.
    Whether V-price is an option depends on the details of your scenario.
    To me material ledger is the right way to value stocks and COGS at actual cost.

Maybe you are looking for

  • My ipod wont let me restore or update

    I have gone to the website and got all the latest downloads but it still hasnt been able to restore. A message pops up saying "ipod updater 2004-04-28 can't install firmware on connected ipod's hardwater and the Updater firmware are not compatible" P

  • Return link from Answers report

    Hello, I have created a report which uses GO URL to pass dimensions as parameters to second report. When user lands on the second report, how can I create a "Return" link to go back to original report? Thanks, Vivek.

  • Printing issue in ECC6.0

    Hi experts, We are facing problem in production server. When users are giving print it is under waiting status. So we have checked the spool request, it is 19500 (50%). But users are facing the problems since yesterday. Now we have removed spool of l

  • I downloaded Mountain Lion on my Mac Book Pro but when I go to install it, it says "OS X cannot be installed on Lion."   Any advice?

    I downloaded Mountain Lion on my Mac Book Pro but when I go to install it, it says "OS X cannot be installed on Lion."   Any advice?

  • User license reallocation

    Hello All:     Just a general question, a client of mine is setting up another instance somewhere else and want to reallocate part of their current license to that location. They currently have 100+ license in this one location and want to get 10 out