Actual Dates in Production Resource Tool

Hi All,
In PS, we can plan PRT (Misc nature) for activities in Network Maintenance. On PRT screen, PRT takes scheduled dates from the activities.  There are fields for actual dates, but actual date never flows from actual date of activities.
How SAP derives the actual dates for PRT
Thanks in Advance
Regards
Prash

Mahesh,
Are u using one of the process
1. A hammer tool which can be used in process called flattening steel, and end of the process you will use the same tool for some other process-
For this maintian this in PRT in Routing.
You can maintain and service this tool say after specified period u will allocate some time for this.
2. Substance like catalyst that can be used for the process, and end of the process u can extract catalyst.
For this you can maintain as BOM. If say beginning of the process u add 10 ml of catalyst and end of the process u get exact same amount, without any change in costing terms you can say this as byproduct (default)
If say 10ml yields 10 +/- 5 ml then mainain as co-product by just turning check mark.
Hope this helps

Similar Messages

  • MATERIAL TYPE : Production resource/Tool...

    Hi...
    MATERIAL TYPE : PRODUCTION RESOURCE/TOOL.
    Friends..i want to know about the above material .and its uses..generally i heared that this type of materials mostly used in manufacturing industries...if i want to configure this in which way i can configure..and let me know brief about material (production resource/tool..)
    (or)
    plz share with me your experience about this type of material and its configurations..
    It will be verry helpfull to me..
    Regards,
    Sirish

    Hello,
    Please go through this documentation:
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/PSPRT/PSPRT.pdf
    Prase

  • PRT Production Resource Tools Counter

    Hi,
    I am trying to setup a production resource tool which is counted at time of production.
    I have setup the Material, Equipment, BOM, Counter, Routing.
    When executing a production order the Counter is not updated with the ammount produced.
    Does anyone have a manual on how to setup PRT Counters. I have looked on the SAP Library but this is not sufficient to solve the problem.
    Regards
    GIlbert

    Dear Gilbert
    You have to create the equipment as PRT Equipment category. In PRT data you have to assign the (counter) measuring point and maintain the usage formula. Assign the Equipment PRT in the production orders and Enter the usage value and UOM. Ensure the UOM of the usage value and the UOM of the characterestic value you have assigned in the measuring point are same.
    Now the confirmation will update the measuring point by creating a measuring document for the measuring poit to the count of the confirmation you are entering.
    Regards
    Soundararajan M.

  • Difference bet ween Fleet Object and Production Resource Tools

    Hi all,
    Please give me the difference between Fleet Object and Production Resource Tools in Plant Maintenance
    Thanks in Advance
    Thanks,
    shriraam

    Dear,
    Production Resources/Tools (PRT)
    Unlike machines and fixed assets, production resources and tools (PRTs) are movable (not stationary) operating resources that are required to perform an activity and can be used repeatedly. For example, PRTs include documents, engineering drawings, jigs and fixtures, and measurement instruments.
    Fleet Management
    Here can map the vehicles as equipment master records and enter vehicle-specific additional data, which is displayed in the system on two additional tab pages. This means that you can now specify important fleet data such as the license plate number, load volume, consumption data, fuel card number, engine data, or fuel type and so on directly in the equipment master record.
    You can also perform maintenance planning for a fleet object. You can make the date of the next scheduled service dependent on the distance
    Please refer this link,
    [Link|http://www.nd-solutions.com/pdfs/white_EAM/EAM_ConfiguringFleetMgt.pdf]
    Regards,
    R.Brahmankar

  • How to Set up PRT (Production Resource Tool)

    Hi ,
    Anyone knows How to Set up PRT (Production Resource Tool)  for equipment , is it all master data set up or there any configuration required to activate PRT .
    Thanks
    Pawan

    just in case have a quick look here:
    http://help.sap.com/saphelp_47x200/helpdata/en/89/a42719461e11d182b50000e829fbfe/frameset.htm
    Logistics - Production Process - Master Data - Production Resources/Tools - Production Resources/Tools - Equipment - Create.
    spro->production planning for process industries->master data->production resources/tools (PRT)
    you will see 5 transactions to configure your settings:
    -define PRT auth.grps
    -define PRT status
    -define Task List Usages
    -define PRT Group Keys
    -Define Overview Variant for Where-Used List/Mass Replacement

  • Material type FHMI(product resource/tools)

    hello gurus,
    can u tell me why materials under material group FHMI  production resource / tools are only managed on quantity basis

    Dear Raghu,
    Production Resources/Tools (FHMI) are unlike machines and fixed assets, production resources and tools (PRTs) are movable (not stationary) operating resources that are required to perform an activity and can be used repeatedly.
    For example, PRTs include documents, engineering drawings, jigs and fixtures, and
    measurement instruments.
    Please follow the link to know more :
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/psprt/psprt.pdf
    Regards,
    Syed Hussain.

  • From Which table Production resource/tool number can be retried

    Hi Friends,
    In SAP Query I am Using MAPL,PLAS, PLPO, PLKO, I want to retrieve Production resource/tool number PLFHD-FHMNR, can any one tell in which table it is storing the value.. & what link condition I need to use to retrieve thisfield.. Transaction CA03.
    Thanks,
    Ravi.

    FHMNR is stored in table ADFSH_PRTHEAD. You may need to pass ORGEH - Org. Unit to get the Production resource/tool number.
    This may help you.
    Regards
    Karthik D
    P.S. May i know why you have mentioned FHMNR in all your answered questions today?

  • IA07 : Key for Task List Group and Production resource tool number link

    HI abapers,
    In IA07 TCODE , i want to retrieve Key for Task List Group( PLNNR ) and Production resource tool  number ( FHMNR) .
    In technical settings for both the feilds, structure names are mentioned.
    Is there any function module or table link to retrieve both .
    thansk & regards
    Raghul

    Hi Raghul,
                    i am also facing the same issue. Kindly let me know if u get any solution for this.
    Thanks in advance.
    -AruN.

  • Status: Production resource/ tool

    Hi,
    I don't understand the function status for production resource/ tool.
    1. MM01. in the view Production resource/ tool and in the field Plant-Specific Material Status there are 2 choices. 01 blocked for procment/whse and 02 blocked for task list/ BOM.
    I would like to blocked the material for the routing. when I choice 02 It isn't been blocked for the routing. when I choice 01 It is blocked. I don't understand it because it is the opposite.
    2.The same in the PRT Master there are 3 status 01created on  02 release for PRT usage planning, 03 release for production. When I choice 02 I It is blocked for the Routing although 02 has to be release for the routing. with 03 function correctly
    Can you explain me how the status function in the 2 cases. Do I do it wrong?

    hi
    May be it has been customized in different way .kindly check in OMS4
    regards
    thyagarajan

  • Production resources/tools

    Dear gurus,
    Could you please help me with the following issue.
    There is a neccessity to use production resources/tools, because we have materials, that
    Firstly, are produced,
    Secondly, are used in production, but should not add value to it,
    Thirdly, have some durability, which is diminished during the usage of PRT,
    Forthly, are being repaired, and the durability is being restored.
    Plant maintenance is not implemented.
    I know from help, that it is possible to create PRT as a material, machine or a document and maintain in the rooting.
    Tell please, is it possible to create a material type FHMI (PRT) in order to:
    1. Produce it (not procure).
    2. Maintain "ST" a basic UoM for it, but also to maintain some durability for it somewhere.
    3. Maintain it in the rooting.
    4. During the production order confirmation, diminish the durability without diminishing the quantity.
    5. To issue this material to CO-order for repairs (without plant maintenance), when the durability reaches 0, and somehow to restore the durability for it.

    Hi Nikolaj,
    It's very common requirement in many implimentations. But unfortunatley SAP does't support that process in PP module. Only from PM module we can support that process.
    But there are many ways to map process by using small development.
    Eg.1 Delcared PRT as material master and assign it in BOM. And update a Z field in BOM depending on the number of production order qty. when it reaches zero we can trigger message!!.
    Any way you need CO order only for settlement. So you can always book cost for restoring the PRT to relevant cost object.
    Eg.2.
    Create other or doc PRT and assign it to a routing for a specific operation. And then trace that operation in the production order by a development and manage the life of PRT.
    Reg
    Samson

  • Datasource for capture of PRT (production resource tool) details in PM

    Hi,
       I searched for a datasource which gives the production resource tools (PRT's) assigned to an activity in a maintainance order (Plant maintainance). I was not able to find any!. Should we go for a generic extracor to have the PRT details in a maintainance order?
    If yes what are the tables that we can get this details.
    Thanks in advance.
    Rajeeve Patric

    Hi Gurus,
    still waiting for your update on this..

  • PM: Print / View Production Resource Tools - documents from Iw32

    Hi SAP Gurus,
    My requirement is to create a customized program to print the documets save in Production Resource Tools-IW32/IW33.
    Please suugest!
    Thanks and Regards,
    Pavan.

    Hi,
    I know this post is old, but to answer the question:
    Yes, you can link, using Object Linking functionality in DMS, to a PRT.
    The object is a bit obscure in the object list, but, when selecting a object in the DMS Config>Define Document Type>Define Object Link, look for the object called CRVS_B.
    This is the PRT Object Link's definition, which will then allow Object Linking functionality as required.
    The other way, as mentioned earlier, is to simply use the PRT functionality from your transaction, i.e. IA06 to link to a DIR. This has the downside though that the bi-directional navigation from DMS<>PM for example will not exist.
    Regards,
    Freddie.

  • Documents to be linked from DMS to Production Resource Tools

    hi, All
    I want to Link some documents to PRT through DMS.
    From DMS i choosed object link Production resourec/tools.
    I searhed PR/T no result found.
    So Now i want to Know that How i could Creat PRT and Link some document to PRT.
    Any one help me
    Rgds,
    Ben

    Hi,
    I know this post is old, but to answer the question:
    Yes, you can link, using Object Linking functionality in DMS, to a PRT.
    The object is a bit obscure in the object list, but, when selecting a object in the DMS Config>Define Document Type>Define Object Link, look for the object called CRVS_B.
    This is the PRT Object Link's definition, which will then allow Object Linking functionality as required.
    The other way, as mentioned earlier, is to simply use the PRT functionality from your transaction, i.e. IA06 to link to a DIR. This has the downside though that the bi-directional navigation from DMS<>PM for example will not exist.
    Regards,
    Freddie.

  • Production resources/tools (PRT)

    hi,
    my client is doing gear mfg.they want to maintain machine tool (PRT) in sap. there want map prt for every operation.
    no plant maintenance module.
    and they want to maintain PRT in inventory
    we can create prt in material master and assign PRT in routings.
    How can issue prt for production order (but not a consumable item) and how can i trace it
    if tool(Equipment) gets repaired. we have to procure new tool .
    tool is transferable from plant to plant
    how can i map this???
    thx in advance

    Hi Brahmaji,
    Thanks for your response.
    1. I had set the PRT availability as you suggest.
    The thing is, PRT availability check still say that the PRT is available - while the stock of this PRT is 0
    2. CF11 only show the production order no & the order quantity that use this PRT.
    It didn't show the required quantity of the PRT (let say, if 1 pc of FG need 2 pcs of this particular PRT, it will only show 1 pc in this report)
    3. If it is not possible, then could you please advice, how the system could inform us when and how much to buy the PRT to ensure that the PRT quantity will not be in shortage?
    If the material PRT can't fulfill the requirement, then which PRT type would be the best sollution?
    Thank you.

  • CHECKING AVAILABILITY OF PRODUCTION RESOURCES TOOLS IN TWO PRODUCTION ORDER

    HI
    I hav two production order 1)having  start date:22.12.2006 & finish date 24.12.06 and second is 2) start date 25.12.06 finish date 27.12.06
    this production order for same material, now i have to check PRT for 1st order during order creation system response that all PRT are available but while checking  PRT for 2nd P.O system should say that PRT in engaged in first order but system showing that all PRT are available.
    so how to check it .Is there any customization needed (Scenarion Is MTO production)
    please kindly help me
    regards
    Dev

    Hi Dev
    Please check the configuration in SPRO for availability check in production order
    i.e Define checking control
    select the required checking rule and other parameters as reuired
    Hope this may solve
    Regards
    Vijay

Maybe you are looking for

  • Which is best way toalign divs at bottom?

    I am hopefully getting near to completing my layout for webste and I am trying to build it as follows:- First I created a wrapper div to contain everything. Next I created a header div in which I will put my logo image jpeg as a background. Then I cr

  • Add soap header in SALT

    Hi everyone! I want to send a soap header(an UUID) using SALT, and honestly, I didn't found a detailed explanation or an example on how to do that. The only thing I know so far is: - Add in the ".wsdf" file: <Property name="mapsoapheader" value="true

  • Type httpsURLConnection is not defined

    I'm relatively new to using the JSSE (read: several hours into tinkering with it) and I'm completely at wits end trying to figure out WHY I can't locate the httpsURLConnection class. I have fully updated my Java to include JSE 6 Update 2... however I

  • Chkdsk Scandisk mess in XP

    After deleting a large number of files on my 100Gb X61 with XP Pro, I though a defrag might be in order. However Diskeeper Lite reported that "CHKDSK is schedules to run on preload (C". Rebooting the machine to run CHKDSK gave the error that C: could

  • HT1491 iTunes Store issues

    I bought a season pass for a tv show and have had no problems until yesterday when I tried to watch an episode it gives me an error that I don't have authority to access?  Any ideas pn what might be wrong?