Gurus,
I am working on a scenario where we have 2 main cost centers  (A & B) from which services are used in different cost centers one of which is C. C is assigned to a work center. Now for the cost center C,two activity types are defined ATA and ATB which are actually the services from cost center A and B respectively.
   Now for standard cost estimate I can define planned rates for those two activities based on the cost center C. Now at the month end I want to draw the costs from A and B based on the % of the services drawn by C and then calculate the actual price for those activities, i.e. run revaluation cycle. My question is, when I would run the revaluation cycle, how am I going to differentiate the cost of each activity types based on the cost input from respective cost centers (A and B) ?
   I short, with more than one activity type and more than one input cost center, is it possible to valuate the activities on actual prices?
Thanks in advance!
Snigdho

Hi Snigdho
Yes, you can!!
If I have understood your question well - What you want is that the Cost allocated to From A to C should be divided by Act type ATA and cost allocated from B to C, should be divided by ATB, at the period end... Is that what you want?
You can achieve this in SAP... 
1. Create 2 separate secondary cost elements for each Act Type ATA and ATB
2. Create a Spliting structure in OKES... You would assign Secondary cost ele 1 to ATA and Sec Cost ele 2 to ATB
Assign cost center C to this splitting structure in OKEW
3. now, when you calculate Act price, you will get what you want
Regards
Ajay M

Similar Messages

  • Actual price calculation

    Hi Experts,
    We have this scenario:
    1. Activity prices are entered manually in KP26.(Activity type indicator=5)
    2. At the time of CO11N only POWER activity will confirm.
    3. Executing CPTA for overhead allocation.
    4. KSS2 for power activity
    5. No splitting for other cost elements
    6. KSII Actual price calculation
    7. MFN1 Revaluation of order
    After revaluatin of order when i am checking actul cost for activities only power cost is coming.
    Please find the enclosed print screens for same above process.
    Please guide me how to get the actual price calculation for other activities.
    KP26 :
    KSS2:
    KSII:
    CO03:
    Regards,
    Vivaan

    Hi Rajneesh,
    Yes Splitting rule is Activity only.
    Ex.
    1.Order Quantity = 1000
    2. I confirmed yeild 500 Qty & power activity 200 in CO11N.
    3. Now when i execute  CPTA for that order its calculating like below.
    4. KSS2:
    KSII:
    Now actual price is coming same for other activities except power.
    If i maintain no split structure that time in KSII only power actual price coming as print screens posted in original query posted.
    Please advise me on Actuall price calculation as per our business scenario.
    Regards,
    Vivaan
    Now my client is asking is as below
    Cost center report  xxxxxx
    Water GL cost = 60000
    Water Qautnity=1000(This is PO Total order quantity)
    Water actual price=60000/1000 =60
    Confirmed Quantity= 500
    Actual price  calculation for water = 500*60=30000
    same for other activities also.
    Please advise.
    Regards,
    Vivaan

  • Actual price calculation - acutal price indicator KSII

    Hi Friends
    I am trying to calculate actual price (KSII) and am getting the following message.
    All activity prices are manually entered
    Message no. KP211
    Diagnosis
    All activity prices in controlling area 1000, fiscal year 2009, and version 0 were determined and set as manually entered prices.
    In actual price calculation, all plan activity prices, meaning those calculated automatically (activity price indicator 1 and 2) and those set manually (activity price indicator 3), are treated as if they have been set manually.
    System Response
    The SAP System cannot calculate activity prices automatically.
    Processing is cancelled.
    Procedure
    Check your activity type planning. To calculate the activity price automatically, you must set the activity price indicator accordingly.
    Pl suggest what the actual price indicator should be in activity master data
    I am putting 5 there (after some actual data is posted) but it is not working. it is still giveing the above error and not calculating the actual price.
    Pl suggest the way out.
    Regards,

    Hi,
    In activity type creation check whether you maintained activity category as "1" and actual price indicator as"5"
    Regards,
    Sreekanth

  • Actual activity price calculation for production order

    Hi
    Can any one guide me in how many ways we can assign actual activity price calculation for production order?
    I knew only one way by assigning PPP2 costing variant?
    I have another doubt is: if we don't mention any material valuation indicator (moving average, standard) in valuation variant, how system will calculate material prices? is there any other way, to recognize the prices by system?
    regards,
    Ramesh B

    Dear,
    Costing variant PPP2 is linked to some valuation variant inn OPL1
    System will check the valuation of material and activity according to this valuation variant
    For material valuation there are many stg acceding to which system will take the price the raw material,
    Valuation strategy for material component
    Strategy sequence that determines the valuation of the materials used in the cost estimate.
    Use
    The materials are valuated using the price in the material master record or the values calculated in a material cost estimate.
    Procedure
    You can enter a single strategy, or you can enter multiple strategies in the form of a strategy sequence. If you enter multiple strategies, the priority of the strategy determines what price or what values are selected.
    Examples
    Assume that the following strategy sequence is entered for material valuation:
    1. Planned price 1
    2. Standard price
    3. Moving average price
    If the system finds a value in the Planned price 1 field (costing view), this value is taken as the value for valuating the material.
    If the system does not find a value, the value in the Standard price field (accounting view) is used.
    If the material does not have a standard price, the system uses the value from the Moving average price field.
    if you have not mentioned, then system will give error that "valuation stg not found"
    Valuation strategy for internal activities and processes-
    Strategy sequence that determines how internal activities and processes are valuated in costing.
    Use
    The activities and business processes used are valuated with the prices from Cost Center Accounting or Activity-Based Costing to determine the production costs or process costs. The prices can either be calculated iteratively through price calculation, or entered manually by the user.
    Procedure
    You can enter either a single strategy or more than one strategy in the form of a strategy sequence. If you enter more than one strategy, the priority of the strategy determines which price is selected.
    Examples
    The following strategy sequence is entered:
    1. Actual price of the previous period
    2. Plan price of the previous period
    3. The most current plan price
    If the system finds a price for the activity type, this price is used for valuating the internal activities. If no price was calculated for the previous period, the plan price from the previous period is used to valuate the activity type.
    If the system cannot find a plan price for the previous period, it looks for a future plan price, using the next price in the posting period to valuate the internal activities. For example, if plan prices have been entered for periods 2 and 3, and a plan price is calculated in period 1 for period 4, the system uses the price from period 3 in accordance with the valuation strategy Most up-to-date plan price.
    Again if you have not mentioned, then system will give error that "valuation stg not found".
    You can use any costing variant for actual (PPP2)and planned(PPP1) according to your requirement.. check in OPL1

  • Authorization control for actual price calculation

    Dear all,
    I found that there is no authorization control for actual price calculation(KSII), this means user can calculate actual price for all cost centers, even this cost center belongs to other company. Is there a way to control this?
    Thanks,
    Ben

    Hi Ben,
    By SAP standard we do not have the control.  we also have the same situation.  We are venturing in to Realisation phase and we decided to have some kind of program (development) to control this.
    Please let me know if you find some better solution
    Best Regards
    Surya

  • Calculation formula userexit not working for multiple condition types

    Hi,
    we have a problem in the CRM ISA-B2B scenario where the custom user exit is only working for single condition type.
    but we need it for multiple condition types .
    the value of the subtotal is not being retrieved for multiple conditions. at a time only one condition value is being retrieved and shown in the webshop - shopping basket.
    for ex:
    we have scenario 1 where Y001 -Freight condition type is applicable for one customer.and Y002 is applicable for another customer.
    when we are trying to show the subtotal condition value in the webshop by using a single custom user exit in the pricing procedure it is only working for either of the above 2 customers depending on the VMC cache status.
    is there any problem if use the single user exit for both condition types?
    and if it needs to be differentiated how exactly we can do that with the same logic in the java class.
    Thanks in advance,
    PSR.

    Hi Arshi,
    below is the code:
    public class ZValFormula_ZZWI1 extends ValueFormulaAdapter {
         private static String zzwi = "ZZWI1";
         private static char  zzwiC = '@';
         private static UserexitLogger userexitlogger = new UserexitLogger(
         ZValFormula_ZZWI1.class);
         public BigDecimal overwriteConditionValue(IPricingItemUserExit item,
                   IPricingConditionUserExit condition) {
              ICurrencyValue val = condition.getConditionValue();
              userexitlogger.writeLogDebug( "value saved for " + zzwi + " (" + zzwiC + ") = "
                        + val.getValueAsString());
              item.setSubtotal( zzwiC, val.getValue());
              return val.getValue();
    hope this would give more idea to look at the problem.
    Thanks,
    PSR

  • Actual Price Calculation Issues

    Hi,
    I need explanation on how the system calculates actual prices in KSII.
    In my cases i maintained Rs 1.00  as variable price for my activity type and cost center combination in KP26. My planned activity is 1000 Mins and actual activity is 3600. in KSII system is showing 2129.64 as actual price calculation. how the system is calculation as 2129.64. If i see cost center report it is showing that over absorption as -2600.
    Please guide me on the actual price calculation.

    HI,
    KSII - Actual Cost/Actual Qty.
    Please check what is your actual cost and Actual qty. in your cost center report and check. Planned qty. or Planned cost is not taken for consideration during KSII.
    Bye,
    Ramesh

  • KSII (Actual Price Calculation)

    Gurus
    When I execute the said KSII; result for activity prices is as follows:
    ACTIVITY TYPE 1 = ACTUAL COST/ACTUAL HRS = RESULT OK
    ACTIVITY TYPE 2 = ACTUAL COST/ACTUAL HRS = RESULT OK
    ACTIVITY TYPE 3 = RESULT WRONG
    ACTIVITY TYPE 4 = NO RESULT
    Same rule is assigned to all activity types in Cost Splitting Structure.
    Actual activity quantity is also posted for each activity, I am confused why not system's behaviour is same for all activity types price calculation.
    Thanks
    bukhari

    Hi,
    Just check if you have done the Cost Element planning for the correct Cost Element & Cost Centre combination as defined in the Splitting structure and further the Splitting rule is based on the Activity quantity.(KP26)
    Also ensure that you have planned for the Activity quantity for the same cost centres for which you have planned the costs. (KP06)
    Award points if useful.
    Regards,

  • Multiple Activity Types with one Production Cost Centers

    Dear Experts,
    I have One Cost Center 2 Activity typesu2026I can plan in kp06 in single shot thatu2026
    1Ctr-1ActvtyRs.100 and 1Ctr-2Actvty----Rs.200u2026.(Same Cost Elements)
    Here my confusion is while doing actual posting we can post cost element to Cost Center i.e.Rs.300 to 1Ctr.
    Here how I can map that 100 belongs to 1Activity and Rs.200 belongs to 2Activity because there is only cost center.
    I know that solution is simple we can maintain separate cost center for both activity types i.e 1 to 1 mapping of cost center to Activityu2026So Actual posting weu2019ll be fineu2026.
    Then what is use of Kp26 to maintain 1 cost center to multiple activity types?
    Kindlyu2026..Clear my problemu2026
    Regards,
    Balaji Bhonsle.

    Hi Balaji
    You have pointed out a valid concern.. There is a solution to it as well, however, very cumbersome and less practical
    In OKKP - You allow some control indicators i.e. CCA, IO, PCA, COPA, etc.. Here, you need to allow Activity Type as Addiitional Account Assignment Object.... (This is below Cost Center Accounting)
    While booking expenses from FI, you can specify the Act TYpe along with the cost center... Provided you have that much patience and it is identifiable....
    Also, you can assign act type in Asset MAster so that while posting depreciation in AFAB, the same gets assigned to Act Type
    Br, Ajay M

  • Actual Price Calculation (KSII)

    hi,
    I am not able to get the actual prices for my production order.
    I maintained certain settings for actual price calculation in OKEQ.
    Does it is mandatory to run the MFN1 (Revaluation of actual prices) before the KSII.
    Srinivas

    Hi Sateesh,
    Please find below the process for calculation of Actual Activity Prices:
    1. Define Splitting structure, rules (method). I am sure you would have done this
    2. Assign the splitting structure to Cost Centers. I hope you would be done this as well
    3. Actual values (Costs and quantitative details) will get collected to cost centers in the following way:
         - Quantities will get collected to Cost Centers once the confirmation of activities are done for the        production order.  Please make sure that "Record Quantity" check box is selected for the relevant secondary cost elements. 
         - Values will get collected from FI to the primary cost elements
    you may check whether the values have been properly collected to the cost center using the cost center reports
    4. Execute cost Split using - KSS2
    5. Then calculate Actual activity unit price - KSII
    6. Once the prices are successfully calculated, you can check the prices in KP26
    7. after this process is completed then you can revaluate you production orders using the actual activity prices
    I hope i made is clear.
    Let me know if you need further details in this regard
    Surya

  • Actual price calculation configuration

    Dear experts,
             What are the configuration settings required for actual price calculation in product costing?
    Regards
    Jay

    Hi,
    please find below the list of activities that need to be done to calculate the actual price calculation:
    Config requirements:
    1. You have defined the splitting structures
    2. You have assigned Splitting structure to Cost Centers
    End user side:
    1. KSS2 - Execute Actual cost splitting
    2. KSII - Calculate Actual activity price
    Please let me know if you need futher details in this regard
    Surya

  • Cost splitting and Actual price calculation

    Dear all,
    What is the difference between cost splitting and actual price calculation?
    Thanks & Regards,
    Ar

    Hi,
    KSS2 (splitting) is fixed cost splitting based on defined splitting rules. Fix cost splitting means, although the cost are activity unindependent (=FIX) they are splitted to each actual activity unit,... (based on the splitting rule you use)
    This is/can be a prerequisite for calculating actual activity rates, which is done by KSII (actual price calculation).
    best regards, Christian

  • CALCULATION OF ACTUAL PRICE CALCULATION  - KSII

    Dear Friends,
    We are using Make to Order scenario and NOT USING Sales order based costing, I would like to calculate Automatic activity price calculation and revaluate my production order with actual prices (MFN1), for this I need to create & assign splitting rules to cost centers & follow the t.codes KSS2, KSII, KBK7 (DISPLAY) and finally MFN1.
    For Calculation of KSS2, how Plan Quantity has to be decided, this because for calculating Operating rate system take the formula as below, whether the below formula is correct?
    Actual quantity/ Planned quantity * variable price
    If for a cost center, postings are happened in FI for 10000/- then how system calculate & segregate this?
    if possible with an small example, when checked in KSS2 it shows the amount of postings from FI with cost elements.
    But when we checked t.code KSII it was showing the some different Actual Activity and variable price. How system takes the Actual activity and Variable Price and is there any report to check this?
    please guide me
    Regards,
    Sandeep
    Edited by: sandeep jain jain on Nov 2, 2009 4:15 PM

    Hi Paolo,
    You were exactly right that it was rounding off.
    But still am not able to get the calculation working for me.
    In Cost Center Report Actual/ Plan it shows
    Debit Assessment Cost Element 10000
    Credit Machine Hour 458.16-
    Credit labour Hour 124.96-
    over/under Absorption 9,416.88
    This are all actual cost.
    When i run KSII the result is as below
    Oty  Object                        Name                    AUn              Activity Qty Total Price     Price(Fixed) PUnit
    ATY MBX273/L1                Testing CCTR         H                 1.666         3,001.20         3,001.20      1
    ATY MBX273/M1                Testing CCTR         H                 1.666         3,001.20         3,001.20      1
    I am not getting how this value  3,001.20  is calculating.
    Kindly help me to under stand this
    Edited by: lolu jo on Oct 28, 2011 3:57 PM

  • I want to order multiple copies of an iPhoto book I have already purchased once. Is there a price break for multiple copies? Also, can I send to multiple addresses?

    I want to order multiple copies of an iBook I have already purchased. I have two questions:
    1) Can I send them to multiple addresses?
    2) Is there a price break for multiple copies?

    1) No.
    2) No.

  • Custom HoverPanel for Multiple File Types Preview

    Hi Everyone,
    We Have a requirement to customize SP2013 Search Results webPart to List down multiple file types (Word, Excel, PowerPoint, PDF, Images, etc). we created our own Design Template for Search Results Item to show managed Properties we require. and we need to
    create a Hover Panel to show the preview of those files. we tried to achieve this, but failed. can anyone please provide us a Solution for this ?
    Thank you!

    Hi  Mohamed,
    According to your description, my understanding is that you want to customize Hover Panel for multiple file type.
    For achieving your demand, you can refer to these blogs:
    http://sharepointfieldnotes.blogspot.com/2012/11/customizing-sharepoint-2013-search.html
    http://yeshagrawal.blogspot.com/2013/06/sharepoint-2013-search-adding-hover.html
    http://blogs.technet.com/b/tothesharepoint/archive/2013/09/17/how-to-display-values-from-custom-managed-properties-in-the-hover-panel-in-sharepoint-server-2013.aspx
    http://www.sharepointnutsandbolts.com/2014/01/extending-SP2013-Office-365-search-hover-panel.html
    Best Regards,
    Eric
    Eric Tao
    TechNet Community Support
    Thank you So much Eric,
    The First Link "http://sharepointfieldnotes.blogspot.com/2012/11/customizing-sharepoint-2013-search.html"
    Serves my purpose 100%, but seems like it has 3rd party Product Involved. can i achieve the same Results without using any 3rd Party Tools ?

Maybe you are looking for