ADM delivery times from Apple.. 2-3 months!!
Hi,
We have a 3.5 TB RAID built with 250GB disks. One disk just died and the RAID is still running but no safety anymore..
It seems Apple is having a hard time delivering 250GB ADM modules (2-3 months)
Is it possible to use a larger sized disk? (750Gb is available 24hr) I realize we lose most of the disk but better than losing the RAID
cheers
Kaspar
Yikes! That's a long delivery time. I order our 250GB replacement drives from Mac Mall (www.macmall.com). They are pretty quick. We have had them sent next day air on several occasions, but standard delivery is usually 2 to 4 days.
-Phoenix
Similar Messages
-
Planned Delivery Time from Material Master instead of PIRs
Hi SAP Gurus,
Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5). So when MRP runs it will read 5 instead of 1.
Any additional information is appreciated.
Thank you
-nicHi Nicholas,
In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
Regards,
R.Brahmankar -
Copying delivery time from 1st (unconfirmed) schedule line to confirmed SL
Hi Friends
Long time since I visited our forum.
During order creation or change, by selecting all items and using 'Edit- fast change of- Delivery date' menu option one can set a delivery date and time for all the items. This info moves to schedule line 1 (for the requested delivery date) Shipping tab to Arrival time field. However if an item (s) is not confirmed for the requested date, then a second schedule line is created for the confirmed date based on user's choice in the ATP dialog window. Now the issue is that delivery time is not copied to the new SLs. And it will be cumbersome to enter it by going into the SL-Sales tab for multiple items via their confirmed SLs. Is there a config way ( I doubt it) to get the delivery time (only time) copied to the confirmed SLs from the first SL. Or user exit is the only route? if so is it FORM USEREXIT_MOVE_FIELD_TO_VBEP in MV45AFZZ? Does this info stay once it comes via this user exit or do we need to do anything extra during Sales document save or prepare? Oh, by the way, we are set up for complete delivery and fixed date/qty checked.
Let me know ASAP. Thanks.Hi
If I understand you, the problem is that EZEIT is initial, ie; VBEP-EZEIT = 0 (ie: it has the value on dynpro'00:00:00' depending of the format of your country). The problem for this userexit is that it's called in the end of subroutine VBEP_FUELLEN in the include FV45EFEP_VBEP_FUELLEN. If you read the ABAP coding you have the call to a subroutine before:
* Anlieferzeit ermitteln
perform vbep-ezeit_ermitteln.
If you read it in include FV45EF0V_VBEP-EZEIT_ERMITTELN, you can read this coding:
if vbep-ezeit = 0.
if vbep-edatu ne *vbep-edatu or vbep-prgrs ne *vbep-prgrs or
( svbep-tabix = 0 and ( vbep-wmeng ne 0 or vbep-bmeng ne 0 ) ).
perform anliefertermin_pruefen using vbep-prgrs
vbep-edatu
vbep-ezeit
vbep-cmeng
vbep-bmeng
da_dialog
da_edatu
da_ezeit
sy-subrc.
if sy-subrc = 2.
vbep-ezeit = da_ezeit.
endif.
endif.
endif.
* Sekunden sind bei Lieferplänen für Zulieferer nicht relevant
check not vbak-abdis is initial and
not vbep-ezeit+4(2) is initial.
clear vbep-ezeit+4(2).
I think that you are looking for this, am I right? Surely, you knew it before to post this subject.
Alghough the purpose of userexit is populate fields from an append (fields ZZ) but it's possible to change others. I suggest to think about this, because I think that it's the same and you can know the checks to avoid inconsistencies. If you need something else, please let us know.
This is only a suggestion. I hope this helps you
Regards
Eduardo
Edited by: E_Hinojosa on Apr 1, 2011 10:38 AM
Edited by: E_Hinojosa on Apr 1, 2011 10:38 AM -
Apple Store - Delivery times?? _ frustrating!!
I placed an order through the Apple Store on the 8th Aug at 6:53am GMT (17" MBP, Office and a 4gb Black Nano), the website informed me that the manufacturing time would be 24 hours and dispatch would be on the 9th with arrival on or before the 11th (which is great as I needed the laptop for this weekend).
I got an email this morning at 2:34am GMT informing me that my order has been despatched on the 10th and will arrive on the 14th. Why the sudden increase in delivery times? The website clearly stated all items were available within 24 hours meaning it should have been ready to despatch on the 9th to arrive with me on the 11th. Really disappointed I use to work in sales myself and if we gave a delivery date that was the date regardless, even if it meant having to have staff work overtime to complete an order and have it ready to leave on time.
So what’s the chances of my order arriving with me on the Friday? As their will be no one available to collect delivery as of the Sunday for 8-12 weeks as I have to go work abroad.
//On a side note why am I being shipping the US version of MS Office?
MBPDelivery to Europe *****. I've ordered several times from the Apple online store. The manufacturing dates Apple told me were always correct. But then, after handover to Kuehne & Nagel in Shanghai, everything comes to a grinding halt. My first MBP got stuck in Shanghai for 5 days. And it took another 5 for it to reach my door-step. The replacement MBP got delivered from Shanghai directly by TNT. I thought that would speed up the process - but I was wrong. Again, the thing got stuck somewhere in China. Once the stuff is in Europe, though, the packages almost always arrive within 24 hours. From what I've read, delivery to the UK sometimes takes 2 days from the Netherlands, though.
I just wished Apple would try to reduce the delivery times from Shanghai to Europe somehow. -
Delivery time calculation from purchase info records in MRP
Hi experts.
I am using MRP -manual reorder point planning . I have maintain the delivery lead time as 10 days . This material has a info-record for a vendor and a contract also. we maintain the delivery time for the supplier is 20 days in the info records. And a source list is also maintain for this material with reference to the contract and assigned as MRP relevant.
We run MRP of this material and create the PR directly.
we run ME59N for automatic creation of PO also.
what I see is the delivery time defined in the PR is consider as 10 days from the material master MRP view. But when we convert the PR to PO the delivery time is updated from the inforecord. but the delivery date in the PO line item is not update. It is showing the same delivery date as PR.
Is it possible to update the delivery date bas eon the info record when we convert from PR to PO automatically?
regards
DPI don't know the answer to your question, but can point you in another direction; you can set the system up in such a way that already MRP (as per the way you have described that you work) will take into consideration the planned delivery from the Info record/Contract:
In transaction OPPQ check the "Scheduling: Info Rec/Agreement" box!
This will make MRP take the planned delivery time from the IR or Agreement, whenever the source (vendor) is identified during the MRP run.
Regards,
Mario -
Planned delivery time in Scheduling agreement and MRP
Hello,
Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
Regards, jaanaThis can be customized in
SAP Customizing Implementation Guide
-> Production
--> Material Requirements Planning
---> Planning
> Procurement Proposals
> Define External Procurement
Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level. -
My Iphone4 replaced by iphone4s from Apple!?
Hey guys
I wanted to know if anyone else has had thier iphone4 replaced by iphone4S from Apple!!?
I have had too many problems with my iphone4 an got it replaced 4 times from apple store in manchester, but each time there was a problem with the phone!!
So i had enough and called iphone uk apple care line yesterday, women down the phone said i can only reccommend just to go store and get it replaced, unless you want to talk to a senior collegue an make a complaint!! An i did!!!
The 2nd women offered me a brand new iphone 4s with one year warrenty!!
So she told me that she will send me the new phone deliverd an i will have to send my old phone back to them, ( therefore took my bank card details) just incase they think i dont return my old phone.
But i just hope this new iphone4s is better than iphone4 an i dont have the same problems!!
Ps, 00800<was the phone code number! Is that US!?Did you ask for an unlocked iphone?
What does the receipt say? -
I recently ordered a iPhone 6 plus 128 on the 13/09/2014 the web site is quoting me 3 to 4 weeks, a friend of mine ordered his phone on the 12th when orderimg first opened, he's been quotated a similar time frame. do you think I'll be given a more realistic delivery time when apple opens it's doors to its shops tomorrow?
If ive got to wait of 3 - 4 weeks so be it - however it would be fantastic to think Apple already have my order sitting on a shelf in the UK and it's ready to ship?What color did you order?
It appears the iPhone 6 Plus 128GB and 64GB in Gold are the most favored and ran out of stock the quickest.
I ordered my (iPhone 6 Plus Space Gray 64GB) on 9-12-14 at 4 A.M. and my estimated shipping date is Oct 1 - Oct 6th. I check the status constantly and it still says its "processing items" and no shipping updates yet.
Apple Support said they are expediting all iPhone pre orders to get the orders filled as quickly as possible. -
Planned delivery time & GR Processing time
Hi all,
I would require a clarification on this one,
Scenario - After an MRP run, the Purchase Requisitions for materials are generated & the order release date is being calculated by subtracting only the planned delivery time from the requirement date. But to the best of my knowledge
"Purchase Order release date = Requirement date - (Planned delivery date + GR Processing time)"
Solution required - Is my understanding correct & if so, where should i make the changes to include the GR processing time for the computation of order release date. Is there any other field which i need to add to my PO release date computation. An early response in this regard would be highly appreciated.
Regards,
VivekHi,
The order release date simply takes the requirement date and subtracts the planned delivery period (as you have indicated).
But this has ALREADY taken the GRP time into account and so you don't nedd to (and shouldn't) add it in again.
For example,
Material A has a Planned delivery period of 10 days and a GRP time of 3 Days. The date that the production order is to be started is 30 July.
The MRP run sees the requirement date as 30 July but it also sees the 3 days GRP and so it asks for the item to be delivered 3 days prior to this date (27th July).
The planned delivery period is 10 days and so the PO will need to be created by the 17th July.
So the dates are correct and do not need any further changes.
If you were to take the GRP time off again this would be wrong.
Steve B -
Planned delivery time in purchase agreement (contract)
Hello,
When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
Can anybody explain why? And how to prevent this?
Thanks,
IsabelHi,
If you enter planned delivery time in Info record, it automatically copied to contract. Make the planned delivery time in info record as blank. Or you can remove the planned delivery time in Contract when creating it
~Thanks!
Rajesh -
Planned delivery time in purchase agreement
Hello,
When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
Can anybody explain why? And how to prevent this?
Thanks,
Isabeldeleted
-
I have a imac g5. It's running off version 10.4.11. How do I update it to a higher version? Do I have to buy that software or can I download it from apple?
Does the computer's installed version of OS X (Tiger 10.4.11) have an install
+ restore DVD, or is that missing? The original disc set usually would include
the extra applications not found on a retail version OS X install DVD; and a
bonus is the original software kit included the version Apple Hardware Test
for your computer model. This also is not included in a retail OS X install DVD.
If you have your computer serial number and model information available,
and try calling Apple (main number, not local store) and ask to speak to an
Operating System Specialist, when you get someone matching that position
on the phone ask what they can do for you regarding a Replacement DVD
install disc for a system that can run in your computer.
If your computer shipped with a Tiger version, that would have been originally
on a grey-label DVD set include with the computer, with a part number on it.
A replacement may be harder to get, than say, a white label Replacement
DVD install disc for Leopard 10.5. There had been a white label non-retail
full install version of both Tiger and Leopard, available for a time from Apple
sales support main numbers (or applecare?) for a reasonable fee. Maybe still.
Perhaps if one kind of replacement system disc is not available, they may
have some other option at Apple. The main store number may not be the
correct place to ask, but they may be able to redirect you to an OS Specialist.
(in US 1-800-MY-APPLE is the main #. There is another number I don't recall.)
Good luck & happy computing! -
Consider planned delivery time field in MRP Areas
Hi,
I would like to know if the "Consider Planned Delivery Time" field in the MRP areas is taken into the scheduling of materials during MRP run? From the help documentation, it seems to be yes. Otherwise the system will take the Planned Delivery Time from the Plant level. May I ask how we can tick this field for all materials? We are currently in the process of activating the MRP areas in our system. Before, we didn't use the MRP areas but we think the need for it has arrived. Is there a mass maintenance tool to do this? Or do I have to use LSMW? Thanks!
Regards,
ChesterHello Chester
If you flag the field "consider planned delivery time" the planned delivery time defined on the MRP area will be considered by MRP. You should tick it for all the materials if the value from the MRP area should be considered.
Also, the report RMMDDIBE can be used for mass processing of MRP areas.
BR
Caetano -
User exit for copying planned delivery time
Hi
My requirement is to copy the value in field Planned delivery time from contract to planned delivery time field in MRP2 view in material master. Please let me know which user exit or enhancement may be used for the purpose.
TIA.Hi
Check BADI_MATERIAL_CHECK
Regards
Sanil -
Hi Experts,
Normally we CIF planned delivery time from R/3 to Apo. Instead of planned delivery time, shall we use Transportation lead time offset to be maintained on the transporttaion line itself in APO?, which one is better?.is Both (TLD or PDT) are same.
Regards,
MadhuHi
As I mentioned it depends on your business case in which cases you want to create a TL.
In our case we only create TL in intercompany planning scenario, in third party supplier we do not create TL and we directly user planned delivery time which is getting CIF from ECC system.
I think both should able to server the respective purpose. Only one clue for you lead time defined TL will overwrite the planned delivery time in ECC during planning run
Thanks
Amol
Maybe you are looking for
-
How to delete screenshots in Network Magic 5.5?
I am running Network Magic version 5.5.9195.0 on my home network. One of its features is the ability to take desktop screenshots of connected computers. NM will store up to 100 screenshots before overwriting the oldest ones. Rather than accumulating
-
Page numbers are not generated correctly when print from Word to PDF
Whenever I print my Word document to PDF, my page numbers do not reflect the page numbers shown in Print Preview. For example, I have a Word document with 10 pages and after generating it as PDF, the page number shows Page 1 of 1; Page 2 of 2; Page 3
-
Unable to install 1.6.0_17 JRE in Linux FC12
Hi, I am having Linux FC(Fedora) 12 - 64 bit system. I am trying to install JRE 1.6.0_17, and get the following error when trying to install ( jre-6u17-linux-x64.bin). Do you agree to the above license terms? [yes or no] yes Unpacking... Checksumming
-
Microsoft Word doesn't respond too frequently
Everytime I try to compose something on Word it freezes within 30 minutes (I suddenly notice sluggishness and then I have to force quit Word). solution?
-
I have started getting this error every time I download anything to my computer. I want to know how to fix the issue so it dosen't happen anymore. The error is as follows: The system extension "/System/Library/Extensions/IOBDStorageFamily.kext" was i