ADSUBCON with multiple batches to transfer the material to vendor

Dear Gurus,
I am using ADSUBCON tcode for subcontracting process , my problem is i am not able to transfer material to Vendor or received material ,  from multiple batches.
please guide how to incorporate this functionality in ADSUBCON. (same available in MIGO)
Thanks & Regards,
Akshay

Hi Jurgen ,
Sorry for my way to raise the discussion , this will not happen next time ...
Moving Further - In ADSUBCON I am not getting any option to multiply the same line items for multiple batches , like MIGO is having that option , if i am clicking on new items ,sales order no. and special stock E is missing for movement type 541... please check following screenshots.
Thanks & Regards
Akshay

Similar Messages

  • TRANSFER OF MATERIAL FROM VENDOR TO VENDOR

    Hi *SAP MM GUYS*  Please check my scenario .
    I have send some material to a vendor for subcontracting jobbwork.
    after as he is delaying the work I want to send the material to another vendor.The first vendor has no problem with this.So how to transfer the material from vendor to vendor.Please give me detailed explanation.
    Awaiting your reply
    Veer

    Dear,
    Case1) Process flow IF material is Excisable:
    Do 542 of material
    Reconcile the challan with that dpcument
    Complete the challan
    Do 541 for second vendor
    Raise the s/c Challan
    Case 2) Process flow if material is non excisable
    Do 542 of material
    Do 541 to the second vendor
    OR u can do
    542 in MB1B wherein u can put the vendor where u want material to be sent.
    Regards,
    SNB

  • Create inbound delivery for same material with multiple batches

    Hi Experts,
    An ASN( advanced shipping notification) contains multiple batch numbers for same material or line item.An IDOC has different segments with batch numbers but in SAP while creating Inbound delivery(VL31N) only batch number ( segment) get posted automatically in SAP other batches are need to post manuaaly.
    I am using IDoc type : Delivery03 ,Message type: DESADV
    How to resolve this problem?
    Thanks,
    Anil

    Hi Anil,
    Welcome to SCN for your first post. Did you check with your functional people about this.
    Regards,
    Madhu.

  • Handling Unit with multiple batches

    HI,
    Is it possible to create a Handling Unit with multiple batches, when packing a Handling Unit in a Production Order (COWBPACK)?
    Thanks

    When I create a  packing instruction (transaction POP1), I can set indicator "Indicator Batch Mix Allowed".
    Explenation:
    If this indicator is set, then several batches of the same material may be packed in one handling unit.
    Otherwise, only one batch may be packed.
    Use
    When determining the packing status, the system checks for batch mix violation.
    But I still can not create an HU with different batches.
    Can anyone help me?

  • Move SU with multiple batches

    In the client's WH there can be pallets (storage units) with multiple batches. This is configured and works OK. However these storage units cannot be moved. Obviously when moved, they must keep their SU number.
    If I try to move only 1 batch, the movement is not allowed because then a duplicate SU will result.
    If I try to move the whole quantity, the data in the TO will not be consistent.
    Actually in both cases I get the message
    Storage unit XXXXXis not consistent with other transfer order data
    I have tried moving them in LT01. I also tried in LT10 - here the system moved both but assigned a new SU to one of the batches. (?!?!?!?!)
    Is there a way to move such pallets? And if not , why is there a config option for mixed batches for SU, IF IT DOES NOT WORK???
    Edited by: HunLogistic on Feb 10, 2010 3:34 PM

    In the client's WH there can be pallets (storage units) with multiple batches. This is configured and works OK. However these storage units cannot be moved. Obviously when moved, they must keep their SU number.
    This is obviously not true.
    The storage unit number uinquely identifies the storage unit within your warehouse. If you pick up goods from your storage unit you cannot use the same ID for the new unit since in this case you would have two SUs with same ID in your WH.
    Standard system is working poperly, you can have mixed storage units with different materials and batches and you can use complete and partial stock removal w/o any problem - please see online help.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/c6/f846eb4afa11d182b90000e829fbfe/frameset.htm
    If you only transfer a part of the storage unit into another SU-managed storage type, the system assigns a new SU number for this part of the original SU...
    Isn't it possible that there's a developemnt which want to use the existing SU number for the new one?
    Regards,
    Csaba
    Edited by: Csaba Szommer on Feb 10, 2010 4:08 PM

  • Looking to create delivery with multiple batch line items

    Hi,
       Can you please suggest me BAPI / FM to create a delivery with multiple batches. like ... i have 1 mail line item in the delivery and n sub line items. If possible can you please post req parameters too. Thanks in advance.

    solved my own

  • TO Confirmation. Handling units with multiple batches.

    Hi all!!
    I have a problem when i try to confirm an outbound TO with several positions. The problem is that the proposed handling unit is different than the original one. This problem only occurs when the handling unit has several batches, if there's only one this doesn't happen.
    This is configured in the customizing of the movement(601), but I don't know why it doesn´t work with multiple batches.
    Any idea?
    Thanks a lot.

    Hi!
    I have had the same problem and I put a note to sap. Their answer was:
    "As per my previous reply, the functionality you are requesting is not
    available in the standard system.  When processing a TO, each item is
    confirmed line by line.  There is no check on the remaining TO items
    if there is remaining stock in the source HU."
    Hope this help.
    Regards,
    Tatiana

  • How do you download all chapters of a video at once?  I purchased a yoga video with multiple chapters and only the first one loaded.  It says I can't download another chapter for 90 days.

    I purchased a yoga video with multiple chapters and only the first one loaded.  It says I can't download another chapter for 90 days.  How do I get all chapters to download?

    Once a device or computer is associated with your Apple ID, you cannot associate that device or computer with another Apple ID for 90 days.
    http://support.apple.com/kb/ht4627

  • Howto deal with multiple source files having the same filename...?

    Ahoi again.
    I'm currently trying to make a package for the recent version of subversive for Eclipse Ganymede and I'm almost finished.
    Some time ago the svn.connector components have been split from the official subversive distribution and have to be packed/packaged extra. And here is where my problem arises.
    The svn.connector consists (among other things) of two files which are named the same:
    http://www.polarion.org/projects/subversive/download/eclipse/2.0/update-site/features/org.polarion.eclipse.team.svn.connector_2.0.3.I20080814-1500.jar
    http://www.polarion.org/projects/subversive/download/eclipse/2.0/update-site/plugins/org.polarion.eclipse.team.svn.connector_2.0.3.I20080814-1500.jar
    At the moment makepkg downloads the first one, looks at its cache, and thinks that it already has the second file, too, because it has the same name. As a result, I can neither fetch both files nor use both of them in the build()-function...
    Are there currently any mechanisms in makepkg to deal with multiple source files having the same name?
    The only solution I see at the moment would be to only include the first file in the source array, install it in the build()-function and then manually download the second one via wget and install it after that (AKA Quick & Dirty).
    But of course I would prefer a nicer solution to this problem if possible. ^^
    TIA!
    G_Syme

    Allan wrote:I think you should file a bug report asking for a way to deal with this (but I'm not sure how to fix this at the moment...)
    OK, I've filed a bug report and have also included a suggestion how to solve this problem.

  • For the cm with multiple bps, what are the options for workaround?

    For the cm with multiple bps, what are the options for workaround?
    customer a purchases 1000
    and returns 800 at POS
    customer b was used at SAP related to  this transaction, purchase amounting to 2000,what can we do to apply the returns of customer a to customer b of 800 return transaction at pos?customer a and customer b code pertains to just one client---but were given different codes at POS and at SAP

    Hi,
    If one customer has two codes, you can only do manual journal entry to adjust their accounts.
    Thanks,
    Gordon

  • Transfer the material from one plant(non valuated) to another plant valuat

    Hi All,
    How to transfer the material from one plant(non valuated) to another plant valuated.
    Which Goods Movement type we required to use.
    Regards,
    Amit Shah

    Hello,
    Please refer the link below. hope it could be a help.
    stock transfer plant to plant
    split valuation
    Regards,
    Jana

  • How to integrate cProjects with R/3 to get the Material Classification Data

    Hi all,
       We are installing the cProjects and we have to integrate it with R/3 to get the Material Classification data.
      Is any one has developed the object link, which links cProject and Material Classification data in R/3?
      Thanks in advance.
    Regards.

    Hi Venkat,
    Refer SAP cProjects Guide for Implementing an Object Link. This Guide also includes User Defined Object Links.
    You should be able to find it on SAP Service Marketplace. In case you cannot, pl send me your email ID, I will mail the same to you.
    Regards,
    Reema.
    Pl award points to all useful answers.

  • How to remove Batch Management in the Material

    Hi All,
    The Batch Management indicator for a Material was accidentally activated, thus upon goods movement the system required user to enter a Batch Number. The user, not knowing the implications, entered a Batch Number.
    Now we want to remove the Batch Management indicator, I already asked the user to reverse the goods movement posted and have the Batch Number flagged for deletion at both Plant and Storage Location Level via MSC2N.
    MM02 still won't allow the removal of the tick mark in the indicator.
    There are options I have looked at:
    1) Create a new Material Code in place of the old one.
    2) Archive the Batch Number then try to remove the tick mark via MM02 - will this even work out?
    But the priority is still to retain the same Material Code. Is there any other way/option?
    Thanks a lot!!! =)

    It is a little painful but here are the basic steps.
    Remove all stock.
    Cancel all demand, no requisitions, no purchase orders,
    production orders etc. Transaction MD04 must be empty.
    Use transaction MSC2N to place a deletion indicator on every
    past batch for that material prior to the end of your fiscal period or
    month.
    Run transaction MM74 to archive the "flagged for deletion" batch
    numbers.
    In the next period or month go to transaction MM02 and remove
    the batch flag from the material master.
    hope it helps

  • Excise invoice capture with multiple batches

    Hi
    We have created a Purchase order for Material X and carried out the transfer posting(MB1B)and selected two different batched of stocks, and created excise invoice using
    t code J1IS.
    When I am capturing the excise invoice in J1IEX. with ref to Purchase order, system is showing only one line item.
    It is not capturing multiple batches.this. we are doing it before goods receipts.
    Regards
    Suresh

    Hi,
    Point1)
    Ur material directly goes to the site for site work right ?
    My question is why are u not taking the credit and dont want to update the part1 and part2.....???
    ur are the consignee(purchaser) for the same so u can take credit...!!!
    again one thing if ur not taking the credit then why r u bother about the excise settelement...Do the vendor invoice settelement. and inventorised the total excise.......
    Point 2)U need to maitain the excise master i.e J1ID...( it is as important as maitaining material master for procurement).If u want excise related transaction to be happened.
    Point 3) if ur not interested in maitaining the excise master then use ME51 report for analysis for excise settelement.
    regards,
    sujit borse

  • Inbound Delivery Creation Problem with multiple batches

    I would appreciate if you can guide me if there is any BAPI or FM to create the inbound delivery (VL31N) with the multiple purchase orders and with the multiple batches for the materials.
    Regards
    Prasad

    TRY THIS ONE.
    BAPI_INB_DELIVERY_CONFIRM_DEC
    *& Report  ZZ_BAPI_OUTB_DELIVERY_CONF_DEC
    REPORT  ZZ_BAPI_OUTB_DELIVERY_CONF_DEC.
    data HEADER_DATA like BAPIOBDLVHDRCON.
    data HEADER_CONTROL like BAPIOBDLVHDRCTRLCON.
    data DELIVERY like BAPIOBDLVHDRCON-DELIV_NUMB.
    data HANDLING_UNIT_HEADER_CROSS type table of BAPIDLVHDUNHDR.
    data gs_HANDLING_UNIT_HEADER_CROSS type BAPIDLVHDUNHDR.
    data RETURN type table of BAPIRET2.
    parameters:
    * Delivery number
    p_deliv like BAPIOBDLVHDRCON-DELIV_NUMB default '0080015271',
    * External Handling Unit Identifikation
    p_hunr like BAPIDLVHDUNHDR-HDL_UNIT_EXID default '60000000000000000000',
    * Handling Unit Material Number
    p_humat like BAPIDLVHDUNHDR-SHIP_MAT default '000000000000002387'.
    * Work on clean data. Allways.
    clear:
    header_data,
    header_control,
    delivery,
    gs_HANDLING_UNIT_HEADER_CROSS.
    refresh:
    HANDLING_UNIT_HEADER_CROSS.
    * set data values
    header_data-DELIV_NUMB = p_deliv.
    header_control-DELIV_NUMB = p_deliv.
    delivery = p_deliv.
    gs_HANDLING_UNIT_HEADER_CROSS-DELIV_NUMB = p_deliv.
    gs_HANDLING_UNIT_HEADER_CROSS-HDL_UNIT_EXID = p_hunr.
    gs_HANDLING_UNIT_HEADER_CROSS-SHIP_MAT = p_humat.
    append
    gs_HANDLING_UNIT_HEADER_CROSS
    to
    HANDLING_UNIT_HEADER_CROSS.
    * Call Function
    CALL FUNCTION 'BAPI_OUTB_DELIVERY_CONFIRM_DEC'
      EXPORTING
        HEADER_DATA                      = header_data
        HEADER_CONTROL                   = header_control
        DELIVERY                         = p_deliv
      TABLES
        RETURN                           = return
        HANDLING_UNIT_HEADER_CROSS       = HANDLING_UNIT_HEADER_CROSS
    commit work.
    write: 'Finished'.