Allocation Structure in CO Assignment Settlement Missing

Hi,
Pls help i am facing an issue to allocation Structure in CO Assignment Settlement while CO88
For referance error massage no. KD506. i got to know i need to assign the cost elements but where and which ? That help i need from experts with bit more understandable. If possible document with screenshots is help to get resolve the issue.
Thanks in advance.
Milind Joshi

Hi...
if you double-click on the message it will show you what are the cost elements that are not assigned yet.
You need to access the allocation structure you use (it should be in the error message) and proceed with adding the respective cost element to complete the settlement. (transaction OKO6->pick allocation structure)
Hope it helps.
Panagiotis
ps...in case you still have issues could you write down the entire message as it appears when you double click on it?

Similar Messages

  • Error : complete allocation structure while doing Ko88 settlement.

    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element S10100 cannot be assigned to a settlement cost assignment in allocation structure A2, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element S10100 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure A2

    Dear,
    Please refer my reply in this thread,
    Error in Rework order settlement
    Regards,
    R.Brahmankar

  • While Doing Production Order Settlement "Complete Allocation structure" :

    Dear Experts
    I am Getting This Problem ,
    please give me A suitable Solution.
    I am created Another Allocation Structure And Assigned to Settllement Profile . But it is not trigering. Not Capturing That allocation
    Complete allocation structure Z1
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 40512006 cannot be assigned to a settlement cost assignment in allocation structure Z1, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    u2022     If the posting under cost element 40512006 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    Edited by: rajamallu on Jul 2, 2010 10:41 AM

    Hi,
    within allocation structure customizing you create assignments for allocation structure Z1.
    Each assignment has a source (cost element, cost element range, cost element group).
    The cost element 40512006 is not included in the source definition of allocation structure Z1 but there are values to be settled available on your sender.
    Thus they cannot be settled and thats why the message occurs. So maintain alloc. structure Z1 completely.
    Best regards, Christian

  • Message no. KD503 - Complete allocation structure K1 for Internal Order

    Hi,
    During Internal order settlement through KO88 I am getting this error as :
    Message no. KD503 - Complete allocation structure K1
    Diagnosis :
    During settlement, the system puts the sender debits into groups  (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters). Cost element 430500 cannot be assigned to a settlement cost assignment in allocation structure K1, and therefore it cannot be assigned to a  settlement cost element.
    Procedure :
        Possible solutions are as follows:
        o   If the posting under cost element 430500 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
        o   If the posting was made correctly, you can do the following:
    a)  You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose
        "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.  If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted  in the settlement profile when you create sender master data or when you maintain the settlement  rule.
    -   You can update allocation structure K1
    The same configuration in  Development Server there is no error but problem occurs in Quality server. Here the process is Internal Order creation - Creation of Reservation through MB21- Goods Issue against reservation  through MB1A and finally settlement through KO88.  During settlement this error occur. In configuration setting of allocation structure under Internal Order I have mentioned only revenue settlement (as per business) against assignments. Under source mentioned cost element group and under settlement cost elment Receiver Cat is "CTR" and tick "By Cost Element".
    During MB1A i.e, goods issue accounting entry is generated as
    81(Dr). 430500 Constimptuion Saprae and Stores
    99(Cr). 310411 Inventory Machinery and Spare.
    During settlement this debit figure should credit. But not allowiing to credit. Even in configuration under settlement cost element if I remove the tick of "By cost element" and mention secondary gl account whose cost element category is 21, still showing the same error in QA server. What may be the probabale solution ? Even if i remove allocation structure K1 from settlement profile 20 still same error exist. How this link gets during settlment inspite of removing allocation structure from settlement profile...
    NB.. COPA is not implemented in our company. So PA structure should not arrise here....
    Thanks & regards,
    Samrat
    Edited by: Samrat Roy on Aug 30, 2010 7:28 PM

    Hi Samrat,
    The issue is very simple.. Cost element 430500  is posted in your IO...
    While settling you have 2 options... Either you can credit the original GL account 430500.. This happens when you tick "By Cost element".. This you have done already...
    2nd option is not to tick "By Cost element" and assign a secondary cost ele category 21...
    But for any of these options to work, you have to include GL 430500 in the "source"... The above 2 options apply only to those GL accounts which are mentioned in the "Source".... for rest of the GL accounts, system gives this error
    Include 430500 in your "source" cost ele group.. Error will be resolved
    Regards
    Ajay M

  • Allocation Structure in Inetrnal Order

    Hi Friends,
    Can any one explain me what is the function of Allocation Structue, which is assigned ( A1, P1 etc)to Settlement profile in Internal Orders.

    Hi,
    Basically there are 3 basis types of structures that are defined in settlement parameters.
    1. Allocation structure
    2. PA transfer str
    3. Source structure
    Allocation structure is basically a tool that allocates the costs incurred on a sender by cost element or cost element group.
    The allocation structure is used for settlement and for assessment.
    An assignment assigns a cost element or cost element group to a settlement or assessment cost element. Each allocation structure contains a number of such assignments.
    The allocation structure must meet the following criteria:
    Completeness -
    For a settlement or assessment to be executed correctly, the allocation structure must represent all cost elements under which costs are incurred.
    Unambiguity -
    There must be only one cost element in an allocation structure.
    Hope this helps.
    Reward suitable points if helps.
    Regards
    Tushar A.Vhora

  • Allocation Structure, Settlement issue

    Dear All,
    I have created a Allocation Structure with following details:
    Allocation Structure: XX
    Assignment: 01, 02, 03...
    Co AREA: YYYY
    In Source: I assigned relevant Cosat element groups
    In Settelment Cost Elements: I assigned Secondary Cost elements
    I have maintained the Settlement rule to settle WBS to CTR in CJ20N.
    I have also checked that Allocation Structure XX is comming in Settlement paramters in the WBS (CJ20N)
    After few postings on WBS element i get an error "Maintain sources for allocation structure A1 (this is pointing to a different allocation structure) in controlling area YYYY"
    Ques 1: Is there any other config to be maintained required to Settle the Project to CTR.
    Ques 2: In the settlement Profile what Document type i need to maintain?? Is this mandatory?
    Ques 3: Is it must to create a source structure? 
    Warm Regards,
    Jatinder

    Dear Gokul,
    Yes this is newly configured allocation structure.
    I have created a new settlement profile (where i have also assigned the new allocation structure) and assigned the Project profile. 
    Regards,
    Jatinder

  • WBS settlement issue:Complete allocation structure A1.Message no. KD503

    hi all
    I created an WBS  600041 and through FB60 posted the JV by assigning the WBS 600041.
    Then I saw in CJI3 the posting is done and it is showing there and I created a settlement rule and gave the 100 % cost settlement on AUC and saved it. Now when I go to CJ88 and do the actual settlement and gave all the parameters for full settlement and execute it is giving the following error
    Complete allocation structure A1.Message no. KD503
    Is this problem due to cost elements? How do I go about it.please suggest.
    kind regards
    Aman

    HI,
    Check  your allocation structure OKO6 transaction. see whether your allocation structure is having the expense cost element  you posted listed in it
    OKO6- select your allocation structure-Assignments-source
    Here the GL account should be listed
    Regards,
    Radha

  • Error In allocation Structure when doing settlement to GL from WBS

    Hi All,
    I got this error message. What should i do? I try to check my allocation structure...but it seem correct.
    Complete allocation structure Z3
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 901000 cannot be assigned to a settlement cost assignment in allocation structure Z3, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element 901000 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure Z3

    Hi Sreenivas ,
    The accounting document looks weird :
    Hi,
    Settlement profile : ZPS001
    GL, CC, Order, WBSE and FXA optional
    Document type : SA (GL Account doc)
    Distribution rule : 10
    Residence time : 24
    Allocation strucutre Z3
    Default object type : FXA
    tick on % settlement and equivalence no
    to be settled in full
    Allocation structure : Z3
    Assignment : 1.Labour ,2.MAterial, 3. Subcontract
    Source       : 1. PSlabour , 2.PSmaterial 3. PSsubcon 4.Cost
    Settlement cost center : FXA (ticl by CE), CTR (settlement cost element 90200) ; ORD (Settlement cost element 902001); GL put 747100f
    I already successfully settle from WBS to GL 747100(settlement receiver)  However, when i check FB03 it shows that
    GL account 747100 
    Posting key 40
    Amount 25000
    GL Account 747100
    Posting key 50
    Amount -25000
    What the problem ?
    Cheers,
    Nies

  • Allocation structure changes at settlement (KO88)

    Guys,
    Here's a question from the PM contingent...
    Is it possible to determine the <i>allocation structure</i> at the point of performing <i>settlement</i> for a PM order (e.g. KO88).
    I've had a quick look for user-exits, but couldn't find anything.
    Thanks in advance

    Allocation Structure is define under settlement profile and this settlement profile is assigned to PM order Type.
    Pl check and define your allocation structure and assinged to you allocation rule .
    Thanks
    Rajiv Pandey

  • Assignment under Allocation Structure.

    Hi SAP Gurus,
    I would like to know the functionality of Assignment under allocation structure.  Let us consider one ex:, I have 10 accounts (cost elements) and I divided those into 2 groups.  I considered one group under one assignment and another group under another assignment. 
    I want to settle expenditure related to first group to one g/l account and another group expenditure to another g/l account.  I don't want to consider % in settlement rule. 
    In that case, how I have to proceed, please let me know at the earliest.
    Regards.

    Hi Raman ,
    Cost Center Accounting , Profit Center Accounting and COPA Reporting are all distincts .
    Cost Center Accounting cycles ( assessment and distribution) will not effect Profit Center Accounting ..
    Wether you use Assessment or Distribution in cost center accounting will deciede upon what costs are there is your sender cost centers. If you have only primary costs ( from 1-2 GL A/c) only.. then use distribution otheriwse you have to use  CCA assessment cycles..
    For COPA Assessment cycles.. source and asessment cycle ... must be different in order to trace the costs later on ...
    Your Design must be
    1. Assessment/Distribution cycle to transfer the costs from pool CC to down CC
    2. COPA assessment cycle sto transfer the Costs to COPA .
    3. PCA cycles to distribute between profit centers .. to have profit center reports..
    Please revert back for any further clarifications
    Regards
    Sarada

  • Complete allocation structure Z4 Message no. KD503

    Complete allocation structure Z4
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 90001000 cannot be assigned to a settlement cost assignment in allocation structure Z4, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element 90001000 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure Z4
    Please help resolve error below.
    What do I need to reverse?
    Is there a different way to enter actual cost for this?
    What do you think is missing in my allocation structure?

    Hi paul
    This error message you are getting KD503
    This message comes up at the time of settlement of the order when you are transferring the cost from on cost object to the other. Here you are giving the final cost settlement on the asset so the final asset is where all the cost is going to get settle for the cost which you have taken in the internal order. you have to define a roadmap for the cost elements which is carrying the cost from the IO to the final asset.
    The resolution Is do the following: go to KO88 and explore the juke box where you have booked all the jv take note of all those cost elements now come to KSES and here under Z4 allocation structure give CO  area and go to source tab and give the range of cost elements that you have used in ko88 and save it
    This will resolve your issue.
    Kind regards
    Arman
    SAP FICO

  • Enter an existing allocation structure - Message No: KD013

    Hi Experts,
    While creating the Internal Order I am getting below error. We are using SAP from last 7 years with same Internal Order Types
    Enter an existing allocation structure
    Message no. KD013
    Diagnosis
    You have entered a settlement structure which does not exist.
    Procedure
    Enter an existing settlement structure or define a new one in the implementation guide.

    thanks for your quick reply. 
    I find out the solution.
    T.CODE: OKO6
    SPRO - Controlling - Internal Orders - Actual Postings - Settlement - Maintain Allocation Structures
    We have maintained Allocation Structure which we have assigned in Order Types.
    T.CODE: KOAL
    Thanks & Regards,
    Vijay

  • Allocation Structure

    Hi,
    When we execute the T.code KO88(Order Settlement for AUC), showing the below Error Message.
    Complete allocation structure A1
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 410006 cannot be assigned to a settlement cost assignment in allocation structure A1, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element 410006 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure A1
    We have assigned Cost element for Receiver Cat. FXA.
    What is the Problem?
    Thanks in advance

    In the allocation structure you need to include the source CE 410006.
    Allocation Structure>Assignments (double click)>Source (double click)
    Here in source you should have the CE mention in From else you should have created a CE group including this CE.
    And now for this source ensure you've maintained the Settlement cost element (for FXA) either 'By Cost Element' or Settlement cost element.
    Regards
    Sreenivas

  • Complete Allocation Structure A1

    Hi everyone,
    I have a problem concerning settlement of orders. Running transaction va88 gives me an error message stating that I should complete allocation structure a1. However, this is not the allocation structure I want to use. The message says that I can assign a different allocaton structure to the sender by chosing Settlement Rule --> Goto --> Settlement Parameters in the master data of the sender.
    Now my question is where to find the master data of the sender!? Thanks for your help!
    Regards,
    Martin

    Hi,
    I have solved this issue now. Changed the allocation structure. Now I still have one problem concerning an account which is not maintained in the strucutre. However, to assign this cost element to the right part of the structure is something my controlling people have to figure out.
    Thanks anyway for all you help.
    Regards,
    martin

  • Complete Allocation Structure A1 in K088

    Every month end, we settle IO unused supplies to inventory accounts (using KO88) but last July 2011 until today, system prompts this error: "Complete Allocation Structure A1"? Can anyone please help me resolve the error? Upon checking the settlement allocation structure, the master data and parameters seems all accurate. Please help resolve this issue. Thank you all in advance.

    hi Gracey
    your error msg. must be showing some cost element missing in the allocation structure.
    Kindly maintain the same in A1...
    Check the link below
    Message no. KD503 - Complete allocation structure K1 for Internal Order
    Regards,
    Divraj