Alternate BOM & Alternate Routing

Hi All,
       What is Alternate BOM ?
       What is Alternate Routing ?
       How do I create Alternate BOM ? [Please give me a step by step procedure]
       How do I create Alternate Routing ? [Please give me a step by step procedure]
       What are all the configuration set-up is required to automatically and manually select the Alternative BOM while creating a Planned and Production Order ?
   What are all the configuration set-up is required to automatically and manually select the Alternative Routing while creating a Planned and Production Order ?
Please provide me an understanding on above questions will be grateful.
Thanks in Advance

Dear Madhan Shah,
If  you are new to the FORUM kinly read the rules first, so that in future you wil avoid posting mulitple questions in same thread.
What is Alternate BOM ?
If you have more than one BOM for same material then each BOM is created as alternate BOM
EX - The BOM for producing sample will not be same as BULK so based on lot size you will have this.
What is Alternate Routing ?
If you have more than one ROUTING for same material then each ROUTING is created as alternate ROUTING
EX - The ROUTING for producing samplING will not be same as BULK so based on lot size you will have this.
How do I create Alternate BOM ? Please give me a step by step procedure
First create a BOM in the CS01 and save it.
Again create a BOM for the same material, the system will give you a message telling Alternate bom created.
You can see the alternate bom number.
How do I create Alternate Routing ? Please give me a step by step procedure
First Create a Group and Group counter 1
Add the second routing as Group counter 2
You can define the Alternate routing / group counters based on the lot size or validity
What are all the configuration set-up is required to automatically and manually select the Alternative BOM while creating a Planned and Production Order ?
What are all the configuration set-up is required to automatically and manually select the Alternative Routing while creating a Planned and Production Order ?
For above 2 questions
NO configuration is requried
Creat PRoduction version in C223
Here you define in each production version which is the BOM and routing it has to use.
Each production version you can define it with a lot size or valdiity period.
IN the MRP4 against the selection method you can define how the production version has to be selected.
Kindly let me know your feedback , if answered kindly close the thread.
reg
Dsk

Similar Messages

  • Production order for alternate BOM and Routing

    Hi All,
             In my business(Discrete) scenario I have alternate bom and routing has group counters. some times i should use first BOM and First group counter. Then next Bom and next group counter. But lotsize is same( prodcution version how to assign).
    When creating production order i should select which ever i need.
    Regards,
    S.Suresh.

    >          In my business(Discrete) scenario I have alternate bom and routing has group counters. some times i should use first BOM and First group counter. Then next Bom and next group counter. But lotsize is same( prodcution version how to assign).
    >
    >  When creating production order i should select which ever i need.
    >
    Hi,
    For your requirement you can define your Order Type Dependent parameters OPL8 as:
    Production Version : 1 Manual Selection of production Version.
    In this case every time when you creat your Production order System will ask for the Production version to be selected. You need to select the PV manually then only you can proceed further.
    This setting is applicable only when the Production Order is Created.
    It will not effect the Planned Oredr creation via. MRP Run..
    Hope this helps..
    Regards,
    Siva

  • Standard cost with material with alternate BOM and Routing

    I have a set up where the same material can be manufactured in 2 different production lines and each production line has two different BOMs and Routings. If I want to have a blended standard cost for the material what are our options?
    We do not want to do split valuation.
    thanks a lot

    Hi
    You can different PCC (Product cost collector) for both lines of the same product (Product cost by period).
    You can define a production process within a product cost collector for each line of production with a combination of BOM and Routing. TCode KKF6n. It would generate a order number for each production process.
    You can use each order within the PCC for each production line to capture the costs for seperate lines.
    Regards,
    Suraj

  • Issue in Exploding Alternate BOM while creating Planned Order to PR

    Hiii All,,
    I have maintained a two BOM's for a finished material one for In House production and one for Sub contracting the components for the Two BOM's are different.
    i have maintained Two Versions for the finished material also.
    when i covnvert a planned Order to an Sub Contracting Purchase Requisition alternate BOM doesnt explode. i have also maintained a production version in the Purchase info record. Still the main BOM explodes.
    i have to manually change the planned order and give the other production version ie not the Inhouse BOM.
    After creating the PR then again i have to go planned order and change to the normal InHouse  BOM.
    Please Provide me the solution.
    Thanx & Regards,
    Kumar Rayudu

    Hi
    In order to explode your alt BOM in your PR do the following.
    1. Maintian alt BOM
    2.Maintain a Version using this alt BOM only. Do not select any routing /rcp group.
    3.Give this Version name in your Inforecord (ME11).
    4.Set the "MRP" field as "Record Relevant to MRP " in your Source List for the material.
    5.In the material master, select the procurement type (MRP2) as " X " ( ie, both proc types).
    I am sure it will work for you
    Regards
    Krishna

  • Alternate BOMs and Purchase Requisitions

    Hi
    The scenario is that the material M1 has two alternate BOMs. These two alternate BOMs(A1 & A2) are specific to two different vendors(V1 & V2). During the planned order conversion to a Purchase Requisition, the business needs to decide/assign the vendor based on the component material availability as per the BOM. We creatred production versions(P1 & P2 ) for A1 & A2 and and assigned them to the respective PIRs.
    (1) M1>P1>A1>PIR1>V1 
    (2) M1>P2>A2>PIR2>V2.
    When the user picks vendor V2 at the pur req., the system defualts to the A1 BOM but NOT to A2 BOM. However, on converting the pur req to a PO, the BOM picked up is A2.
    The question is, the release strategy id defined at the pur req level and not at the PO level (business decision), the person who releases the pur req does not know if A2 BOM is assigned to it or not. Is there a way to show that the A2 bom is picked up at the pur req level?
    thanks
    BE.
    Edited by: Brian Elfie on Jan 23, 2008 7:45 PM

    Hi,
    For BOM selection, system will check BOM selection method in material master of MRP4 view.
    BOM selection by Lot size, Date, Production version & Only by prod version.
    Addition to that BOM selection by Selection ID defined in plant parameter. This selection ID consists of BOM priority & Usage.
    Manually you can not control BOM selection.
    For routing selection, system will check Lot size. If lot size not matched with required qty, system avoid the lot size & consider the date.
    In addition to that system will consider Task list type, priority, Usage & Status.
    In Order type dependent parameter(OPL8), you can configure whether system should select routing automatically or manually.
    Regards,
    Dharma

  • Alternate BOMs and Routings

    Hello Gurus,
    I had a question. I have created Alternate BOMs and Routings for a Material. How through Configuration/or Material Master settings Can I control, as to when MRP derives result from Primary BOM/Routing or Alternative BOM/Routing.
    Thanks,
    Sachin

    Hi,
    For BOM selection, system will check BOM selection method in material master of MRP4 view.
    BOM selection by Lot size, Date, Production version & Only by prod version.
    Addition to that BOM selection by Selection ID defined in plant parameter. This selection ID consists of BOM priority & Usage.
    Manually you can not control BOM selection.
    For routing selection, system will check Lot size. If lot size not matched with required qty, system avoid the lot size & consider the date.
    In addition to that system will consider Task list type, priority, Usage & Status.
    In Order type dependent parameter(OPL8), you can configure whether system should select routing automatically or manually.
    Regards,
    Dharma

  • Alternate BOM explosion in planned order creation

    Dear Experts,
    We have maintained a alternate BOM 1 and 2 of a assembly which is defined as a Phantom (E-50). User wants a option of selecting the alternate BOM of this phantom assembly while creating the planned order of Header assembly. Is it possible?How?
    Thanking you,
    SR

    Dear Sachin,
    In my understanding it's not possible to select the different alternative BOM of a phantom assembly when creating the planned
    order for a header material.
    But give a try in this way,create 2 production version with different lot size or validity date for each laternative BOM and assign
    the value as 2 in BOM selection method in MRP4 view for the phantom assembly.
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • *URGENT -Alternate BOM selection in MRP*

    Dear gurus
    I have an urgent requirement regarding alternate bom selection.
    our scenarion is complete subcontracting and no production versions are maintained and for suppose i have a product X which has 3 alternative boms during the sales order creation iam able to select the required alternative but during the mrp run the system is selecting the alternative "1" by default.I want that during the mrp run also the system should explode the bom which  i have selected during the sales order creation not the alternate "1".
    please reply.
    regards
    Kumar

    Dear Dharma
    in my previous post I havent got suitable reply from my previous post so i have posted again waiting for answers.
    regards
    Kumar

  • Alternate Sequences in Routing?

    Dear Guru's,
    In our production process some of the operation we will perform externally by sending it to vendor. For this we are maintaining the alternate sequences in routing. So, when ever we want send the material to vendor to perform the external operation will exchange the sequence in routing.
    So, in some cases we have to do it in mass. I hope is there any t-code or any other way to do it.
    Need valuable inputs please.
    Thanks & Regards,
    Madhu.G
    Edited by: madhu333mac on Feb 13, 2012 9:14 PM

    Dear Madhu,
    Is it only a manual decision whether to process the operations in-house or else to be sent to the external party or is it based on
    the lot size say if the order quantity is for more than 100 it's to be given to the external party means then define a lot size for
    the alternative sequence for a lot size rangining from 101 to 9999999(For example).
    In this case during order creation the system copies the alternative sequences automatically.
    Check whether this works out for your requirement or not.
    Regards
    Mangalraj.S

  • SUB CONTRACTING PO FOR MATERIAL HAVING ALTERNATE BOM

    Hi,
    we are having following scenario for subcontracting process.
    FIN1 material can be produced either from RAW1 or RAW2.
    In PO for FIN1, in BOM assignment , BOM for FIN1 with RAW2 as sub component  is  assigned. But when thay want to make FIN1 from RAW1, system allows to issue RAW1 to subcontractor as it is maintained as subcomponent in alternate BOM of FIN1(not in PO) but while doing GR it gives message of " DEFICIT OF STOCK W. VENDOR UNR. 10 EA : RAW2 1000 O"
    I thot that this msg is arrising as component RAW2 is not provided to vendor ( as it is maintained in PO a subcomponent for FIN1). So what I did , I added another item as FIN1 in same PO with sub component as RAW1, and then carried out the process, so it worked. But this makes confussion to user as there are severel items in PO, and to judge against which item he will hav to make GR.
    So my question is, is there any setting or scenario in SAP to solve this issue?
    Regards

    1. You will definitely create two subcontracting info records for two raw materials say RAW1 and RAW2.
    2. There will be two seperate production versions for these two materials.
    3. Update respective production versions in respective subcontracting info-records.
    4. This will help to upload the alternate BOM even you changed the material from PO
    Amol

  • Use of Alternate BOM in Plant Maintenance

    Hi All,
    Please let me know the use of Alternate BOM in SAP PM.
    Sundar

    From SAP Help.
    The BOM structure is reflected in the different technical categories of BOM provided in the PM system:
    Simple BOM
    The first BOM that you create for a technical object or material has no defined technical category and a simple structure. It is described as a "simple BOM".
    Variant BOM
    Variant BOMs have a more complex structure. They are used to group together several BOMs to describe different objects that have a high proportion of identical parts.
    Multiple BOM
    Multiple BOMs have the most complex structure. They are used to group together several BOMs to describe one object, for which different combinations of materials are used for different production methods. Multiple BOMs are usually used in production planning and have little or no use for plant maintenance.
    Note: There is no concept of Alternative BoM for PM.

  • Scheduling Agreement Alternate BOM usage

    Hi all,
    For a FG material , i have 2 BOMs available for that.
    I make a scheduling agreement for  Subcontracting process while maintaining schedules ME38 , automatically system is picking the first BOM present for that material , but i want to use the alternate BOM to be picked for that particular vendor or for that Scheduling agreement. So should I maintain any thing else for that agreement .
    With Rgds,
    Vamsi

    Hi,
    Maintain two production versions, one for each BOM you have, Assign the default production version to the subcontracting info record
    When you create subcon PO, the default production version is used. If you want to change it, go in the item level "Material Data" Tab,
    click "Re-explode" and choose the production version you want
    Thanks
    Diwakar

  • Alternate BOM Text from sales order

    Hi ,In My report I need alternate BOM Text.
    The scenatrio is : when we create Sales order it will ask for Alternate BOM ( 1 or 2 or 3 ).
    Based on selection it will assign the BOM and Sales order will be saved.
    I want how to link the sales order doc no with Alternate BOM.
    I have tried so many tables : MAST,VBAP,VBAP.STPO,STKO,STAS etc but not getting the Link.
    Can anybody suggest me ?
    Thanks
    Kumar

    Hello Kumar ,
    you need to Link VBAP-STLNR -->STPO-STLNR.
    regards
    Prabhu

  • Alternate Bom for a finished product has huge varience in cost estimate

    Hi all
    I have created alternate BOMs for a finished material. One is local raw materials and another has imported raw materials. Goods are produced using both these boms but in one period i can release cost estimate of one BOM. Thats why there is a huge variance in cost estimate when alternate BOM is used for the material. kindly give me a solution as to how i can fix this issue.
    regards,
    shahzad

    Dear,
    Please refer this link for,
    [Costing with alternative BOM |Re: Costing with alternative BOM]
    One thing you can do it with split valuation with batch managment please take help from CO person.
    Regards,
    R.Brahmankar

  • Multiple Alternate BOM and activate least one

    Hi Experts
    Any possibilty to activate the Current Activate BOM in case of 3 or 4 alternate BOM
    like if FG is having 3 alternate BOM 1,2,3 with BOM usage 1 than system will check at the time of production order or reservation only 3 with usage 1.
    Rgds
    Pankaj Agarwal

    Hi Pankaj,
    If I got your issue right than you want to have 3 alternative BOMs for a one material (all active) under same usage but you want to select only 3rd alternative during production order.
    If this is the case, then its possible in SAP SFC.
    You need to go to customizing, tcode OS32 - Alternative BOM determination. make new entry as Material with plant, usage, current date and "ALT BOM as 3". You also need to go to MM02 MRP4 view and change BOM selection to "1" selection by explosion date.
    Please try to create production order. This time system will pick Alt BOM 3 with same usage.
    Regards,
    Rohit
    Edited by: Rohit Singh on Jan 5, 2012 12:52 PM

Maybe you are looking for

  • How can I add recording time to a single recording not a series recording?

    If I set-up a series recording it allows me to add minutes to the recording time why can't I add time to a single recording? For example if I want to record a single show tomorrow I find it on the guide and hit record. Now I want to add a few minutes

  • HOw to collect a balanced scorecard

    Hi Gurus, How to collect a balance scorecard. Thanks Best Regards, Reddy.

  • Data entry in the table

    Hi All, I havae a scenario.. I have one ztable with the foloowing fields: 1. enum 2. Ecnum 3. Add 4. Date 5. erole what I did is I made enum and ecnum fields as the key fields in the table and rest I didn't make as key fields. Now when I tried to ent

  • Writing UTF8 encoded data on file system.

    Hi, Could some one tell me what is wrong with the following code. try fos = new FileOutputStream(new File ("A.txt")) ; catch(FileNotFoundException fnfe) throw new Exception ("FileUtility constructor 2 - FileNotFoundException ", fnfe); try // Create O

  • Video loading too slow

    Hi, I've added some video to my Captivate7 module. The video loads too slow, so by the time it comes on the timeline has already past all the vital parts. The module was generated in SWF, which is what is required by my customer. Any advice? Thanks,