Hi, i have a query created in 3.5 query designer and created a variant in RSRT.
The query running fine from BEX analyzer as well as from RSRT. But when i include the APD in my process chain (as pocess type apd not as an abap program), it takes a lot time to run. I means hours to run, whereas it runs less than a minute in my Analyzer or RSRT or RSANWB.
Any solution? Do we need to run APD via ABAP program only?

Hi Lakshmi
There is no process type available in BI system to execute automatically.
so you has to use ABAP Program to run it
Steps to be followed :
1. Create the APD with t-code RSANWB.
2. Standard program name is RSAN_PROCESS_EXECUTE.
3. The program RSAN_PROCESS_EXECUTE is use to execute the APD (Analysis Process) in different actions.
Thanks & Regards ,
Vishall

Similar Messages

  • How to incorporate time in the Process chain messages

    Hi,
    I would like to create message after success or failure of process chain with time of failure in the subject.How to put system variable in the message subject?.
    Your help will be appreciated.
    thanks in advance.
    Manju

    raj,
    thanks for your quick reply but i would like to incorporate the finish time in the mail subject.
    for example mail subject is as follows.
    "GL process chain has been finished at xx:xx time".
    Here time (xx:xx) should automatically read and fill as per the finish time of the process chain.
    hope now it is clear.any idea how it can be done?.
    manju

  • The 0co_om_opa_6 ip in the process chains takes long time to run

    Hi experts,
    The 0co_om_opa_6 ip in the process chains takes long time to run around 5 hours in production
    I have checked the note 382329,
    -> where the indexes 1 and 4 are active
    -> index 4 was not "Index does not exist in database system ORACLE"- i have assgined to " Indexes on all database systems and ran the delta load in development system, but guess there are not much data in dev it took 2-1/2 hrs to run as it was taking earlier. so didnt find much differnce in performance.
    As per the note Note 549552 - CO line item extractors: performance, i have checked in the table BWOM_SETTINGS these are the settings that are there in the ECC system.
    -> OLTPSOURCE -  is blank
       PARAM_NAME - OBJSELSIZE
       PARAM_VALUE- is blank
    -> OLTPSOURCE - is blank
       PARAM_NAME - NOTSSELECT
       PARAM_VALUE- is blank
    -> OLTPSOURCE- 0CO_OM_OPA_6
       PARAM_NAME - NOBLOCKING
       PARAM_VALUE- is blank.
    Could you please check if any other settings needs to be done .
    Also for the IP there is selction criteris for FISCALYEAR/PERIOD from 2004-2099, also an inti is done for the same period as a result it becoming difficult for me to load for a single year.
    Please suggest.

    The problem was the index 4 was not active in the database level..it was recommended by the SAP team to activate it in se14..however while doing so we face few issues se14 is a very sensitive transaction should be handled carefully ... it should be activate not created.
    The OBJSELSIZE in the table BWOM_SETTINGS has to be Marked 'X' to improve the quality as well as the indexe 4 should be activate at the abap level i.e in the table COEP -> INDEXES-> INDEX 4 -> Select the  u201Cindex on all database systemu201D in place of u201CNo database indexu201D, once it is activated in the table abap level you can activate the same indexes in the database level.
    Be very carefull while you execute it in se14 best is to use db02 to do the same , basis tend to make less mistake there.
    Thanks Hope this helps ..

  • How can u know the process chain total time, individual time?

    Hi guru's
    How can u know the process chain total time, individual time?
    and what options will available in sm37?
    Thanks
    prabha reddy

    Hi Prabha
    Iam not very sure about total time and individual times.
    But you can go to tcode rspcm for monitoring the daily process chains. it gives you details like 1. status  2.start date & time  3. Log ID  of each process chain.
    or you can go to log view of particular individual chain to know how long it has run.
    SM37: tcode for simple job selection.
    here you check the status of job.
    you can select for certain conditions like
    1. scheduled
    2. released
    3. ready
    4.active
    5. cancelled
    Assign points if it was helpful
    Revert back if you need further info/
    regards
    AP

  • Why the process chain always run twice when triggered from R3?

    I run a program from R3 by calling the remote function 'RSSM_EVENT_RAISE' on BW to trigger an event and in turn the event on BW bring up the running of a process chain.  But whenever I run the program on R3 to bring up the running of the process chain, I find the process chain always run twice at the same time.  Does anybody knows the answer? 
    And also I would like to know the functionalities of the two picture buttons "Activate" and "Activate and Schedule" in process chain.  In which case the "Activate" button should be used and in which case, the "Activate and Schedule" button should be used?   If we click the Start variant of a process chain, then click "Change Selections" button which bring up the window "Start Time" where the buttons "Immediate", "Date/Time", "After job", and "After event" are listed at the top.  If we modify at any of the above buttons, then after save this modification, we will have to click "Activate and Schedule" button to make it work, right? 
    Thanks a lot and everyone's idea is greatly appreciated!

    Kevin, make sure there is only one job scehduled for the Start Process of your Process Chain.  If you bring up the Process Chain (not the log view), right click on the Start Process and select "Displaying Scheduled Job(s)...".  There should only be one scheduled job with name BI_PROCESS_TRIGGER.  If there is more than one, then when triggered, it would execute more than once at the same time.  If there is only one job, then maybe your R/3 program is triggering the event more than once? 
    As far as the Start conditions for the Start Process, it works off the same principals as a scheduled job.  These start conditions determine when or how the Process Chain is to be executed.  You also have control over frequency.  These start conditions determine the scheduling of the Start Process of your Process Chain.
    When you schedule a Process Chain, a separate scheduled job is created for "each" process in the Chain.  BW controls the triggering of these jobs based upon how the processes in the Chain are linked.  All the jobs associated with Process Chains have strict naming conventions and all begin with BI_PROCESS_...  If you use SM37 to view all jobs that begin with BI_PROCESS_ you will find alot of scheduled jobs associated with your process chains.  Each job represents one of the processes within your process chains. 
    Does this help?
    Another tip might be to trigger the event manually in BW (use tx SM64).  If the process chain executes twice again, then maybe there is a separate scheduled job in BW that triggers the process chain that is triggered by the same event as the start process of the process chain.
    Message was edited by: George Shannon

  • How can i understand the Process Chain management in real time!!!

    Hi,
    now i am learning BW concepts. now i would like to know the real time scenarios regarding Process chains. can any body help me in this matter?.
    thanks,
    stikanth.ch

    Hi,
    A process chain is a defined sequence of interdependent processes required to perform acomplex task in an SAPBW environment. Data maintenance tasks in SAPBW are notrestricted to uploading data. Aggregate rollups, index maintenance, master data and ODS activation, and a variety of other jobs are required to update data, guarantee best-possible performance, and maintain data integrity. Typical SAPBW implementa-tions have complex interdependent networks of jobs in place that run every night, week,or month.Previous releases of SAPBW did not provide an integrated solution for scheduling and monitoring those kinds of job networks. This has changed with the introduction of process chains in release 3.0. Process chains allow you to define complex job networks consisting of standard SAPBW jobs, as well as custom jobs; they support visualizing the job network and centrally controlling and monitoring the processes.
    (from "Mastering the SAP BIW")
    New Features in BI 2004s Process Chains
    /people/mallikarjuna.reddy7/blog/2007/02/08/new-features-in-bi-2004s-process-chains
    Designing
    /people/vishvesh.bahirat/blog/2006/11/29/bw-process-chain-design
    Process chain creation in 2004s - step by step
    /people/juergen.noe/blog/2008/01/11/process-chain-creation--step-by-step
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    http://help.sap.com/saphelp_erp2005/helpdata/en/87/13843b74f7be0fe10000000a114084/frameset.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/67/13843b74f7be0fe10000000a114084/content.htm
    Process Chain Errors
    /people/mona.kapur/blog/2008/01/14/process-chain-errors
    Common Process chain errors
    process chain issues or errors
    Try Searching in SDN for this Topic and you will find much detailed info as this is discussed very frequently.
    Hope this helps.
    Thanks,
    JituK

  • How to Run the process chain

    Deal all,
    I have a doubt:
    How to exclude a process from a process chain which has a daily loads.
    Ex: We have a problem with 0FI_GL_4 data source and that problem will take more time to solve..but till that time  i want to run the remaining processes which are in the process chain (i.e meta chain). i mean to say is i have to exclude the Process which is in problem (0FI_GL_4) but remaining everything should go smooth.
    once the problem is rectified again i have to include the process which is in problem in the process chain.
    Please help me
    Regards
    Venu

    Hi Venu,
    U just bring the chain in Change Mode and then RightClick on that Process which u want to exclude and say delete.
    Once u are done with this Activate ur Process chain and schedule ur Process chain for the time which u want.
    Assign Points if this helps u.....
    Thanks,
    Nagesh.

  • How to know the process chain start time and end time

    Hi Experts,
                   How to know the process chain start time  and end time .
    Thanks in advance
    Regards
    Gutti
    Edited by: guttireddy on Feb 23, 2012 11:30 PM

    Hi Reddy,
    You may find the run time of a PC using below steps.
    1. Call SE38 > /SSA/BWT > Execute  > Enter your PC , choose the date and time > Execute. Here Run-time of a PC is displayed. (or)
    2. Call RSPC1 > Enter your PC > Execute > Goto Log view > Right click on the start Variant > Displaying Messages > Note down the start time in Chain Tab. Now Right click on the last Process type of the PC > Displaying Messages > Note down the End time in Chain Tab. The Difference b/w start time and end time gives the Run-time of your PC.
    Hope this helps.
    Regards
    Sai

  • To find the time required by the process chain to complete

    Hi Experts,
    I am calulating the average time required by the process chain to compete.
    Is there any way to find the time required by the process chain to complete..
    Thanks in advance.
    Regards,
    Ashwin

    Hi,
    There is a Tool provided by SAP to do the Process Chain Analysis.
    It is basically a ABAP Program /SSA/BWT which provides the following BW Tools:
    a)Process Chain Analysis : this tool is used to perform the Runtime analysis of the Process Chains. The analysis can be performed not only at Process Chain level but also at the Process Type level.
    b)Detailed Request Analysis
    c)Aggregate Toolset
    d)Infoprovider BPPO Analysis
    So you can go through the program and analyse the runtime of your Process Chains.
    Regards,
    Abhishek
    Edited by: Abhishek Dutta on Aug 13, 2008 7:13 AM

  • Error while running the process chain

    Hi, I am getting following error while running the process chain.
    "Lock NOT set for: Deleting the data completely from a data target"
    Please suggest.
    amit

    hi,
    This is due to a lock on the objects which is being used by ur load.
    Even if master data used by this would be in a lock by an attribute change run. wait till that attribute change run finishes and then repeat.
    If this target itself is locked by someother process like rollup , compression , this error would appear. In this case also repeat the step after those locking process finish.
    some general locks during loading:
    Sometimes parallel processing in DTP might lead to this, its better set the DTP and infopackage in serial processing. In this case change the settings and then repeat the process.
    There is a specific case in which the Serial DTP gets locked by itself, in this case repeat it untill it succeeds.
    You can identify the above scenario as below. This is applicable only if the DTPs processing mode is serial.
    if u see in SM 37 this load would have three DTP processes running.
    it should have only two.
    In this case cancel the process and repeat it untill u get it right.
    hope this helps u
    regard,
    ranjith
    Edited by: Ranjith  Kumar Murugesan on Sep 12, 2008 10:44 AM
    Edited by: Ranjith  Kumar Murugesan on Sep 12, 2008 10:46 AM

  • Program is not sending emails if I run it within the process chain

    Hi All,
    I am facing a weird issue; I have an ABAP program which compares tables and sends the results in an email. It is working fine if I run it standalone. However, if I run it within the process chain it still runs but doesn't send the email.
    Any idea on how to troubleshoot this?
    Thanks

    maybe because it's ran under a different user (ALEREMOTE)?
    the user that executes the "mail" needs a valid emailaddress to be able to send...

  • HOW TO STOP THE PROCESS CHAIN WHICH IS RUNNING IN THE PRODUCTION?

    HI ALL,
    CAN ANYONE TELL ME HOW TO STOP THE PROCESS CHAIN WHICH IS RUNNING DAILY AT 5.00 PM. I NEED TO STOP THE PROCESS CHAIN FOR COUPLE OF DAYS AND THEN RESTART IT AGAIN.
    cAN ANYONE TELL ME THE PROCEDURE TO STOP THE ENTIRE PROCESS CHAIN RUNNING IN THE PRODUCTION.
    THANKS
    HARITHA

    Hi,
    First and foremost let me advice you to be very careful while doing this.
    For Rescheduling
    RSPC> chain > Goto > Planning view and
    click on Execution tab > select > Remove from Schedule and then in Maintain variant of start process reschedule for the day you require it to run.
    For terminating active chain
    You can start from SM37, find the process WID/PID then go to SM50 or SM51 and kill it. Once its done come back to RSMO and check the request, it should be red but again manually force to red and save by clicking on the total status button in the status tab. This shuld ensure that the process is killed properly.
    The next step will be to go to targets that you were loading and remove the red requests from those targets.
    Note: For source system loads you may have to check if the request is running in the source system and kill if needed and pull it again.
    But for BW datamart delta loads u may have reset the datamarts in case u are going to pull the delta again.
    Re: Kill a Job
    Re: Killing a process chain.
    Regards,
    JituK

  • ABAP program to add in the process chain before the attribute change run

    Hi
    I need a ABAP program to add in the process chain before the attribute change run(process) to avoid the locks, can any one send me the program
    Regards,
    Satish

    I am not sure of any standard program .... but you can write your own... should be a small one..
    you can check if the table RSDMDENQ has entry for your InfoObject... if yes, then its locked.. if not.. its not locked

  • How to extend the execution time of an ABAP Program using the Process chain

    Hello Sapians,
    Our Environment has got 600seconds = 10 mintues as the execution time.
    My ABAP Program is taking more than this 600 seconds, to show the result, I found this when I tried to execute in debug mode, it shows the result.
    If I execute in background also it shows the results succesfully.
    Only issue is when I execute this report in foreground it has been taking ages and goes on Time OUT Error.
    It has been decided that we can extend the execution time only for this report, and it will reset the time back to 10mintues once the report has been executed successfully or failed in between for any other reasons.
    And we can achieve this by using the process chains.
    Can any body help me please in this regard
    Thanks,

    Hi,,,,,,,,,,
    Besides Process Chain There is another way out for this........
    Resetting time counter of dialog process so that time-out does not
    happen. Use this fm within your program at appropriate locations to
    reset time counter.
    "CALL FUNCTION 'TH_REDISPATCH'."
    Thanks
    Saurabh

  • Authorizations setting for running the process chain

    Hai
    Iam planning to run the process chain for loading the data into ODS. But i dont have authorization for it.
    so what are the authorizations i need to run the process chain in my system. And how can i set all those authorizations to my user-id.  I have all authorization rights .
    Pls let me knw
    kumar

    Hi,
    Authorizations for Process Chains
    Use
    You use authorization checks in process chain maintenance to lock the process chain, and the processes of the chain, against actions by unauthorized users.
    ·        You control whether a user is allowed to perform specific activities.
    ·        You control whether a user is allowed to schedule the processes in a chain.
    The authorization check for the processes in a chain runs when the system performs the check. This takes place upon scheduling or during synchronous execution. The check is performed in display mode. The check is performed for each user that schedules the chain; it is not performed for the user who executes the chain. The user who executes the chain is usually the BI background user. The BI background user automatically has the required authorizations for executing all BI process types. In attribute maintenance for the process chain, you can determine the user who is to execute the process chain.
    See also: Display/Maintenance of Process Chain Attributes ®  Execution User.
    Features
    For the administration processes that are bundled in a process chain, you require authorization for authorization object S_RS_ADMWB.
    To work with process chains, you require authorization for authorization object S_RS_PC. You use this authorization object to determine whether process chains can be displayed, changed or executed, and whether logs can be deleted. You can use the name of the process chain as the basis for the restriction, or restrict authorizations to chains using the application components to which they are assigned.
    Display/Maintain Process Chain Attributes
    Use
    You can display technical attributes, display or create documentation for a process chain, and determine the response of process chains during execution.
    Features
    You can display or maintain the following attributes for a process chain:
    Process Chain ® Attribute ® ...
    Information
    Description
    ( Rename)
    You can change the name of the process chain.
    Display Components
    Display components are the evaluation criterion in the process chain maintenance. Assigning the process chains to display components makes it easier to access the chain you want.
    To create a new display component, choose Assign Display Components in the input help window and assign a technical name and description for the display component in the Display Grouping dialog box that appears.
    Documents
    You can create and display documents for a process chain.
    For more information, see Documents.
    Last Changed By
    Displays the technical attributes of the process chain:
    ·        When it was last changed and who by
    ·        When it was last activated and who by
    ·        Object directory entry
    Evaluation of Process Status
    If you set this indicator, all the incorrect processes in this chain and in the overall status of the run are evaluated as successful; if you have scheduled a successor process upon error or always.
    The indicator is relevant when using metachains: Errors in the processes of the subchains can be evaluated as “unimportant” for the metachain run. The subchain is evaluated as successful, despite errors in such processes of the subchain. If, in the metachain, the successor of the subchain is scheduled upon success, the metachain run continues despite errors in “unimportant” processes of the subchain.
    Mailing and alerting are not affected by this indicator and are still triggered for incorrect processes if they have an upon error successor.
    Polling Indicator
    With this indicator you can control the response of the main process for distributed processes. Distributed processes, such as the load process, are characterized as having different work processes involved in specific tasks.
    With the polling indicator you determine whether the main process needs to be kept until the actual process has ended.
    By selecting the indicator:
    -         A high level of process security is guaranteed, and
    -         External scheduling tools can be provided with the status of the distributed processes.
    However, the system uses more resources; and a background process is required.
    Monitoring
    With the indicator in the dialog box Remove Chain from Automatic Monitoring?, you can specify that a process chain be removed from the automatic monitoring using CCMS.
    By default CCMS switches on the automatic process chain monitoring.
    For more information about the CCMS context Process Chains, see the section BW Monitor in CCMS.
    Alerting
    You can send alerts using alert management when errors occur in a process chain.
    For more information, see Send Alerts for Process Chains.
    Background Server
    You can specify here on which server or server group all of the jobs of a chain are scheduled. If you do not make an entry, the background management distributes the jobs between the available servers.
    Processing Client
    If you use process chains in a client-dependent application, you can determine here in which client the chain is to be used. You can only display, edit, schedule or execute the chain in this client.
    If you do not maintain this attribute, you can display, edit, schedule or execute the process chain in all clients.
    Process variants of type General Services that are contained in a process chain with this attribute set will only be displayed in the specified client.
    This attribute is transported. You can change it by specifying an import client during import. You must create a destination to the client set here in the target system for the import post processing (transaction RSTPRFC)  The chain is activated after import and scheduled, if necessary, in this client.
    Execution User
    In the standard setting a BI background user executes the process chain (BWREMOTE).
    You can change the default setting so that you can see the user that executes the process chain and therefore the processes, in the Job Overview. You can select the current dialog user who schedules the process chain job, or specify a different user.
    The setting is transported.
    The BI background user has all the necessary authorizations to execute all BI process types. Other users must assign themselves these authorizations so that authorization errors do not occur during processing.
    Job Priority
    You use this attribute to set the job priority for all of the jobs in a process chain.
    Hareesh

Maybe you are looking for

  • Internet Problems: Websites are not loaded

    Hi everyone, since the Mavericks-Update I got some problems with my Internet-Connection: 1. Often the websites are not loaded. There comes no error-page or something else, its just a white page and I can see the Browser is loading but nothing happens

  • GR against STO (Purchase Order)

    Hi Gurus, When I am doing GR  against STO (Purchase Order) , I am getting the inspection lot origin is from 08 -Stock tfr inspn. Why it is not taking 01- GR Inspn for Purchase Order. Throw me some light on this.

  • Output determination analysis for Handling Unit

    Hi Friends, Can any body help me on how to check the output determination analysis for  Handling unit outputs. I tried checking the document flow through delivery of the Handling unit but could not check. thank you for your help in advance.

  • Interesting angle on 'Provider cannot be found. It may not be properly installed' error

    Hi, I am getting the "Provider cannot be found. It may not be properly installed" message when running a .bat->VBScript script using Windows Task Scheduler. I am not seeing a solution in Google searches. Possibly I am not seeing the similarities beca

  • Some questions for K8N Neo2 Platinum

    Hi guys I'm quite new to Amd64 and just got the Neo2 plat and 3000+ from garage sales 2 days back. Just wanna ask the experts here is it true that sata 1 and 2 for this board doesn't have pci locked? I read this in 1 of the reviews before and it stat