APO and BW

Hi Group
We have BW 2.1 installed at the moment just for reporting purposes. We are in the process of migrating the reporting to another software. In 3 months we will fully complete the migration to the new reporting software. Thus we will not be using BW anymore.
At the same time, we are going to implement APO. I understand APO comes with BW also.
1) My question is, can we expire the existing BW and not use the BW that comes with APO?
2) I also hearing that APO needs BW engine? Is this true?
Our intention is to expire the BW completely and use the new reporting software. Also want to use APO for VMI.
Kindly advice.
Thanks
Yuva

Hi,
       You get BW along with SAP SCM-APO system and cannot be separated. The SAP BW system is fully integrated in APO and can be installed on the same server. The version of BW depends on version of SCM. It can be used to store data but cannot be so performance effective for reporting. You may use the external BW system to report but not needed. You can use BW in APO system to use for all purposes such as storing history from other systems, get the data from APO and store etc. If you dont want an independent SAP BW system, you can still workout. You can store the required data in APO-BW and using reporting tools such as cognos and report on them. SAP BW has a technology named OPEN HUB that lets it send the data from cubes to other systems.
Finally:
1) My question is, can we expire the existing BW and not use the BW that comes with APO?
A: Yes you can expire your independent BW system but cannot live without APO_BW as BW in APO is not separately. You have to use BW atleast the one that comes with APO.
2) I also hearing that APO needs BW engine? Is this true?
A: Not completely true. As I said, if you don't want to report using BW, leave the independent BW system and use an external reporting tool to report in BW in APO.
             In V5.0, there is more flexibility. You can load data to planning area from flat file directly bypassing BW. But if you want to avoid BW all together, you life could be miserable!
For more information see service.sap.com/scm.
Let me know if you have any questions.

Similar Messages

  • GATP in APO and Free Goods Pricing Records in R/3

    We have set up Free Goods in SAP R/3. These free goods are granted based upon a series of access sequences in pricing.
    We also have our Order Entry system using GATP on our APO box. In that APO instance, we have set up a large number of product substitutions to occur at order time.
    When an item is ordered that is NOT subbed to different item by APO and that item has Free Goods associated with it, the Free Goods are granted by R/3 and placed onto the sales order.
    When an item is ordered that IS subbed to different item by APO and that item has Free Goods associated with it, the Free Goods are NOT granted by R/3.
    Why are the Free Goods being ignored after the substitution? We have Free Goods records in pricing for BOTH items, and neither one is granting the Free Goods.
    Is this a bug, a feature, or an oversight ?
    Any help in this area will be GREATLY appreciated!!!

    Hi John,
    GATP in APO does not supports Free Goods.
    Rohit
    Edited by: rohit kumar on Feb 20, 2009 1:33 AM

  • SNP planned order availability date difference between APO and ECC

    Hi,
    I have observed that SNP Planned order availability date is not matching between APO and ECC. Details are as follows.
    I ran SNP Optimizer with bucket offset of 0.5. After publishing the optimizer created planned orders to ECC, only start date is matching.
    Example:
    I am using PDS as a source of supply.
    Fixed production activity in SNP PDS is 1 day.
    GR processing time: 3 day
    After running optimizer planned order is created with dates explained below.
    Start date/time: 09.05.2011 00:00:00
    End date/time: 12.05.2011 23:59:59
    Availability date: 16.05.2011 00:00:00
    Because of bucket offset defined as 0.5 optimizer planned order availability is start of next monday.
    After publishing this planned order to ECC dates on the planned order is as follows.
    Start date: 09.05.2011
    End date: 09.05.2011
    Availability date: 12.05.2011
    I have not maintained any scheduling margin key in ECC. Also if I dont define the GR processing time, planned dates between APO and ECC always match. Can anyone explain the impact of GR time on the availability date.
    Regards,
    Venkat

    Hi Venkadesh,
    What's "state stamp"? Do you mean different time zone?
    note : 645597  mentioned by Nandha is very helpful:
    In standard, CCR will use duedate - "the available date of the output product".
    Nandha's words "In SAP APO, if the receipt date of the primary product deviates from the
    end date of the last activity of the order, the receipt date
    always identifies this as inconsistent. You cannot rectify
    inconsistencies of this type by using CCR."
    I guess in your PDS or PPM, the output product is not assigned to the End of the last activity. Someone changed it?
    Please CIF the PDS or PPM again.
    If you really want to apply a note, please use note 815509 as you're using planned order,
    and system will use order end  date in CCR instead.
    GR time is always considered. BR/Tiemin

  • Problem with call-offs between APO and R/3 system

    Hi, gurus.
    We have following problem:
    APO system receives DELINS idocs. They are processed correctly (status 53). But sometimes the call-offs in R/3 system are not updated. I do not know much about the underlaying process but how can I check where the problem is?
    I suppose it can be caused by blocking of particular material or order or whatever in R/3 system when the call-off is being processed. But then the system should give some warning. I need to know where it could be found.
    The only workaround at the moment we do is to create copies of DELINS in APO system and let them be processed.by APO and consequently by R/3 system.
    Thank you.
    Stano Letko

    Hi Stano,
    When ever IDOC fail you can trigger a workflow to the respective person through Partner profile and message type setting .(we20) as Post processing permitted agent .
    Get in touch with techincal person who have idea of  IDOC configuration.
    Message type : DELINS
    Partner number : XXX
    Workflow tcode : PPOSE
    Manish

  • Dangerous APO and BI Transaction codes

    Hi experts,
    I have question Dangerous APO and  Transaction codes
    Background :
    We are in the process of implementing SOX controls for the new APO and BI Systems
    Questions :
    What are the Dangerous APO Transaction codes which should not be assigned to any one in Production system
    What are the Dangerous BI Transaction codes which should not be assigned to any one in Production system
    Additional Notes
    System which we are having
    APO
    Version  : SCM 5.0
    BI
    Version : BI 7.0

    Praveen,
    I am a puzzled that you would ask such a question.
    Authorizations ALWAYS derive from requirements.  In this case, Sarbanes-Oxley speaks of control mechanisms.  Your SOX auditors should tell you what they consider to be critical, and they should advise the client company as to which transactions should be controlled, and how best to control them.
    There is no transaction that should be disallowed to everyone.  That would eventually make the system unusable.  The question is, "how many people should have these critical transactions, and how should the execution of these transactions be monitored and controlled".
    Generally, the APO portion of SCM should require less SOX controls than ERP, since APO is mostly a planning system, and not an execution system (there are some exceptions here though).  Likewise, the BI portion of SCM usually contains no financial reports, and therefore should have relaxed controls over, say, the main BI instance used by your company.  
    Don't make the mistake of strangling yourself to satisfy your perception of what you think an auditor may require.  Make them tell you the minimum requirements for compliance.  Anything beyond minimum compliance with SOX is costly.  This question is then a matter of your company's policies.  I usually vote for 'no additional restrictions' (but my poor vote doesn't usually count for much).
    Rgds,
    DB49

  • Data from R/3 to APO and vice versa

    Hi,
       Does anyone know what data is usually sent from R/3 to APO and from APO to R/3?
    Thanks

    Hi Disha,
        could you please let me know what is PPM and also what data is transferred back to R/3?

  • PPDS production order dates mismatch between APO and R3

    Hi Friends,
    We are facing one problem regarding production order date mish match between R3 and APO systems specific to a product.
    The product is planned in PPDS and the order automatically transfer to R3 through online CIF.
    PPM has got two operations 0010 and 0020 and activity relationships are like this:
    P(0010) - P(0020) Start - Start relation ship
    S(0010) - P(0010) End - Start relationship.
    In PPDS dates are shown as :
    on operation 0010 the start/end  dates are shown as  08.15.09 to 08.22.09
    on operation 0020 the start/end  dates are shown as 08.15.09 to 08.22.09
    Overall order start date is  08.15.09
    Overall order finish date is 08.22.09
    and in R3 dates are shown as:
    on operation 0010 the start/end  date are shown as  08.15.09 to 08.22.09
    on operation 0020 the start/end dates are shown as 08.22.09 to 08.29.09
    Overall order start date is  08.15.09
    Overall order finish date is 08.29.09
    The order is off one week (APO vs R3) with start and finish dates.  
    if we change DS Board settings to ignore internal relationships manually then the dates are matching exactly in APO and R3.
    We want the production order dates to be matched without manual intervention.
    Could some one please provide some hints on what is happening here and how to correct it.
    Thanks.
    Krish

    Hi Friends,
    Thanks a lot for your valuable replies in this regard.
    Actually this problem is in production environment and it took some time to test the problem with the master data modifications
    you suggested.
    As DB and Siddhrath mentioned, the problem was with routing definition. There is no parallel sequence maintained in the routing but there is start-start relation maintained in APO PPM.
    We corrected the routing definition and checked the order dates. Now the dates  are matching in R3 and APO.
    I am awarding DB and Siddharth each five points in this regard.
    Once again thank you all for your time and valuable replies.
    -Regards
    Krish.

  • APO and BW on separate systems

    Hi guys,
    we are currently setting up a new landscape our company.
    We'll have one APO (newest version, 7.0) with life-cache and one BW (7.0). I am just wondering, why we create two systems and not just one, because APO is based on the BW technology. I had already a look in the notes but didn't find any proposals.
    Has someone an opinion or a link for me?
    Thx in advance
    Harald.

    Hi Harald,
    you are right, APO has a built-in BW system. basically, it is possible to do reporting (APO related) on the same box. However, there are serval reasons that some customers would prefer to have APO and reporting platform separated:
    1. For performance reason (APO vs BW)
    2. Internal BW system is not recommended for other reporting (R/3, or legacy reporting) also for performance reason, because to load and report additional data means additional overhead for the system.
    3. in the past (prior to SCM 5.0), APO has had only current BW release - 1 ->> with limited reporting capability.
    Hope it helps.
    Lilly

  • Step by step screen shots fro APO and SRM, CRM , SCM extractions.

    hi friends,
    can i get step by step screen shots fro APO and SRM, CRM , SCM extractions.
    Thanking u
    suneel.

    Hi,
    I am not sure that you can find something like you asked but from my point of view BI Content is enough.
    Regards,
    ®

  • Inconsistent forecast consumption in APO and R/3

    Hi Experts,
    We have a couple of issues with consumption in our system.
    We have a situation where APO is showing us consumption in the /SAPAPO/DMP1 view but no consumption showing in the planning books and the RRP3 requirements screen. Interestingly, when we go and change the sales order in R/3, the consumption then gets triggered in APO. So there seems to be some kind of delay and the consumption seems to be lagging a step behind or somehow a trigger isnt hapenning first time around.
    The other is more a question...
    If you do the F1 help on Fwd consumption in APO and R/3, it tells us that in R/3 consumption is based on workdays as defined by the factory calendar whereas in APO, it talks about consumption considering calendar days and not workdays and that its not possible to define a calendar to make it work with workdays.
    We have fwd consumption set to 2 days and we have noticed that if e.g the order comes on a Friday, consumption gets lost due to the following two days being Saturday and Sunday. Whereas in R/3 it jumps forward and consumes Monday and Tuesday and ignores Satuday and Sunday (We are using 5day calendars). This is causing a big headache and consumption is all over the place.
    any ideas?

    OK, I have found the solution to half the problem. It was a system bug and the last sales order wasnt being consumed and there is already a note out for that.
    Still confused about the workday vs calendar day issue in R/3 and APO. How do we align the two systems and get the consumption happening in APO for 5 days and not 7 days?
    Regards,
    Usman

  • Linking between APO and PLM

    hi experts
    i am doing linking between APO and PLM so can any body please throw some lights regarding this like how this happens what are required for that.
    waiting for reply
    thanks in advance
    regards
    anand bende

    hi every body
    i need the information regarding linking between APO and PLM.
    so please kindly help me regrding this.
    thanks in advance
    regards
    anand bende

  • Differences between APO and R3 sysytem.

    Hi everybody,
                        Can anyone list out the differences between the APO system and the R3 system.A detailed explanation will be helpful.

    Hi,
    APO
    APO is the supply chain tool from SAP.
    BW is the data layer for APO.
    SAP APO is for Demand Planning and is a component of mySAP SCM. It enables dynamic supply chain management and which in turn includes applications for detailed planning, optimization and scheduling, allowing the supply chain to be accurately and globally monitored even beyond enterprise boundaries.
    SAP BI is a reporting tool in SAP. It provides a complete view of the company. The solution is part of SAP NetWeaver and provides the tools needed to make the right decisions, optimize processes, and measure strategic success: data from all enterprise sources are merged effectively and can be comprehensively analyzed, business-critical factors can be monitored using external and internal benchmarks, the most important KPIs can be passed on to all the relevant forces in a company in real time, strategies can be rapidly adapted to changed market conditions, and the results of analyses can be graphically represented in a wide variety of formats, such as grids, graphs, and maps
    Check this:
    What is APO and how it is related to BW
    SAP Advanced Planner and Optimizer is a component of the mySAP Supply Chain Management solution that you use for planning and optimizing supply chain processes at a strategic, tactical, and operational planning level.
    With APO - Simultaneous Material & Capacity Planning is possible, as against R/3 PP
    APO Planning is capable of taking all the constraints into consideration with Planning for Capacities/Scheduling
    APO Resource (workcenter in R/3) does a Capacity availability check before scheduling an activity, if capacity is not available, it finds the immediate next available slot & schedules the activity there. This is not possible with R/3
    http://www.sap.com/solutions/business-suite/scm/pdf/BWP_APO40.pdf
    http://help.sap.com/saphelp_apo/helpdata/en/7e/63fc37004d0a1ee10000009b38f8cf/frameset.htm
    http://help.sap.com/bp_biv133/documentation/BW/I18_Scen_InstallGuide_EN_DE.doc
    http://help.sap.com/saphelp_scm41/helpdata/en/92/dd013872af2946e10000009b38f8cf/content.htm
    http://help.sap.com/saphelp_apo/helpdata/en/7e/63fc37004d0a1ee10000009b38f8cf/frameset.htm
    R/3 OLTP
    Online Transactional data processing.
    Designed to efficiently process high volumes of transactions, instantly recording business events (such as a sales invoice payment) and reflecting changes as they occur.
    Current data
    Short database transactions
    Online update/insert/delete
    Normalization is promoted
    High volume transactions
    Transaction recovery is necessary
    http://en.wikipedia.org/wiki/OLTP
    Refer for OLTP Vs OLAP
    compare to r/3, what are the benefits available for b/w
    R/3 and BW reports
    http://www.geekinterview.com/question_details/209
    http://blogs.netindonesia.net/kiki/archive/2006/02/28/8822.aspx
    What's the Difference Between OLAP and OLTP?
    Thanks,
    JituK

  • Integration connections to bring master data into APO and BW system.

    Hi All,
    Can somebody give step by stip activities to be done FOR creating integration connection for following requriment.
    1)  To bring master data from R3 System to APO system through BI CUBES using BI type connection
    2) APO/R3 type connection R3 system to APO system.
    Regards

    Nikhil,
    Request you to let me know how can basis person helps in this.
      If this is an existing system, the applications team (APO and BW) will not require much assistance from you.  You can mostly sit back and watch them do all the work.
    I suggest that you read the help link in its entirety provided by expert Datta.  Much of the info there is helpful for both solutions.
    For the APO interface (question 2 in your original post) there is a complete step-by-step guide provided by SAP.  Check these two docs out.
    http://help.sap.com/bp_scmv250/BBLibrary/Documentation/B02_BB_ConfigGuide_EN_DE.doc
    http://help.sap.com/bp_scmv250/BBLibrary/Documentation/B05_BB_ConfigGuide_EN_DE.doc
    If you are being asked to select from one of the two scenarios you outlined, the standard Core interface is by far the simpler to implement.  Plus, it has the advantage that SAP will support you when something goes wrong.
    The BW solution is different, in that the developer (you?) MUST have detailed specifications before he can proceed.  Which master data?  At what organizational levels?  How often refreshed?  What will be the ultimate use of the data, and how must it be stored?  Where will it be stored? How to deal with inconsistencies?  Etc etc. SAP support will only solve technical problems in your solution, they won't solve errors of design or logic, unless you happen to get a very accommodating support person when you raise your message.
    But in case a basis person need to create RFC how can it be done for above scenario.
    The instructions for creating all the RFC stuff is contained in the connectivity doc I cited above.
    Best Regards,
    DB49

  • APO and BI Integration

    Hi All,
    Is their any BW application in APO embedded??
    Is it totally different from normal BI(the one which is connected to ECC and other source systems)?
    regards,
    Rajendra

    Hi Rajendra,
    As per my understanding ,
    There can be BW application Embedded in APO if we are using it for Planning data and to laod from Legacy system for Data comparision.
    It is same as Normal BI,infact BI is only ONE but it will divided  as Core BI and APO BI by Basis Team.
    But BI will be one server as such divided into two applications based on need.There will be authorization restrictions done by the basis team for the Server like PARTITIONING  this much space for APO and this much for Core BIW Tems.The linking is done through RFC connections between Core BIW and APO.
    Ultimately it is one Server !!!!!!!!!!1
    Rgds
    SVU123
    Edited by: svu123 on Jan 27, 2009 11:57 AM

  • APO and CRM security

    i have never worked with APO and CRM security. can anyone walk me through them. thanks

    >
    george G wrote:
    > Neither Have I ..but could wrk  on them after  reading few books on Security  from SAP
    >
    > Thanks
    famous last words .....APO & CRM are full of "features" when it comes to security.  Once bitten, twice shy

Maybe you are looking for