Apportionment of semi variable cost

Dear SAP Gurus,
We define the cost components in the cost component structure (OKTZ) with attributes as variable or fixed and variable costs.
Suppose if we define one component with attribute as fixed and variable - where do we maintain the settings as to how much is fixed and how much portion goes to variable -  Please clarify.
Please provide example as to how KP06 and KP26 differentiates fixed and variable costs and how it is displayed in the output of CK13N.
Please explain.
Regards
Rajya Lakshmi

Hi,
Thanks for the reply.
My client requirement is to show the costs under variable costs.  For which I have defined the cost component as variable and planned them in KP06 and KP26.
Still while performing KSS2 and KSSI system is showing values under control costs fixed.
I need the solution as to what shall I do to show them under the variable control  costs alone.
Please Help ASAP.
Regards
Rajya Lakshmi

Similar Messages

  • Set Up Costs - Semi Variable

    Dear Experts,
    We incur set up costs that are semi variable.
    In other words for $1000 is incurred for every 500 units produced ( $2 per unit). Suppose a product is produced only 100 units in a month, that means $200 ( $2*100 units) is absorbed on the product and remaining $800( $1000-$200) will be unabsorbed.
    How this unabsorbed $800 , should be treated during correspondind month end.
    2. My set up costs includes Labour, Machine & Power . We have captured set up costs under a single activity type.
        Say we incurred $200 in a month, how can we split labour , machine & Power. what is the solution to split set up costs and post to  
       corresponding Labour , Machine and power cost center.
    Thanks
    Sanjai

    Hi
    1. When you calculate actual activity price: It will be higher than Plan Price of 2$ because of lower utilization... Later on when you revaluate prod orders from CON2, there will be No Under abs of overhead
    2. Usually, in your case, Set up cost is better represented by machine hrs than Labour hrs.. So, it is advisable to track Set Up cost as one single cost instead of Splitting up into three
    You can create 6 Act types i.e. Set Up - Machine, Labor, Power and Other Machine, Labor, power... But that will only complicate the things
    br, Ajay M

  • Fixed & Variable cost of the Material at CK11N

    Hello Experts,
    Before posting this thread, i have gone through several threads about my query.  Still I have a doubt.
    Material Cost always should be Variable.  Cost Component Structure OKTZ also the Inventory Valuation would be Variable Cost as per as Std SAP.
    But where as the Raw Material Price control would be "S" & the Cost Component Structure of OKTZ having Inventory Valuation Fixed + Variable Cost then what would be the effect..?
    I have run a SCE for a Material & both Material having standard price 140.6 & 1.09. Then how come the Fixed Value shows here as 10.37 & 0.9 & How can it be divided into Total & Fixed Value..?
    Regards
    Raj

    Dear Raj,
    Please check the following settings in OKTZ:
    Materials are of 3 types:
    Finished: Valuation (Fixed + Variable)
    Semi Finished:Valuation (Fixed + Variable)
    Raw Materials: Variable
    Why Inventory Valuation (Fixed + Variable) for Finished Goods:
    It contains material price as well as overheads.
    Overheads may contain fixed portion also in addition to variable nature.
    So Finished goods valuation should be (Fixed + Variable).
    For Raw materials valuation  should always variable:
    You can make the settings in OKTZ as mentioned below:
    Please check these settings and change the settings accordingly.
    Hope this will helps you.
    Regards,
    Pavan Kumar Arvapally

  • Fixed & variable cost!

    Hi,
    Could anyone show me how fixed and variable cost are treated in SAP
    In case commercial enterprise, (not implementing Product costing sub-module), how to take care fixed and variable cost ?
    If it possible, could you show me the documents relevant my concern!
    Thanks very much for any help!

    Thanks Ashok,
    Yes, I am clear what you mean now.
    But My concern is mixed-cost (semi-fixed or semi-variable), how the system dealt with this?
    For example:
    salary of sales man: Cost element 627000
    fixed salary: 500
    If he sells more than 20 product a month, he will receive 10 for each addition one.
    So 500 is fixed cost, and the bonus is variable.
    This CE 627000 is called mixed cost element.
    In many cases, the accountant can not know which part is fixed, which one is variable as my example.
    So at the end of period, she will use some ways to calculate
    And, another problem i care: except drawing statement , what more can SAP do about fixed & variable?
    Thanks very much Ashok!

  • Variable Costs using SKF in Indirect Activity Allocation

    Hello
    I am trying to use indirect activity allocations and KSPI to transfer costs from an activity in an indirect cost center to multiple direct cost centers. The Receiver tracing factor is planned SKF (i.e. number of employees). The issue I have is that when doing this allocation, the variable cost at the indirect cost center gets transferred as a fixed cost to the direct cost centers. We need to have this as a variable cost on the direct cost centers. Can anyone suggest anything or let me know if I'm doing something wrong?
    Here are my sender/receivers:
    Sender:
    Quantities Calculated Inversely
    Plan Values
    Receiver tracing factor:
    variable Portions
    Planned SKF
    No Scaling
    Thank you

    Hi Mark
    I was able to achieve this in the past...as below
    1. On the indirect Cost center - Use an activity type Catg 2 (indirect entry indirect allocation)
    2. On the receiver cost centers - Use an act type Catg 4 (Instead of SKF)
    3. Enter the Plan Act Qty for this Act Type on the receiver direct cost centers in KP26 and Actual Qty in KB51N
    4. In cycle definition - Var Portion Type would be based on Plan Act Qty instead of SKF
    5. Execute KSCB - Folllowed by KSPI.....
    You can also try the above using SKF on receiver cost centers - But Act Type Catg 2 on the Sender Indirect cost center.... I guess, this is what you have done... In my opinion, this should also work...
    I believe, to transfer the costs as variable - You need to plan them in KP06 as variable (i.e. Activity Dependant Planning)....
    So, Plan your expenses on the indirect cost center in KP06 with reference to the Act Type Category 2
    br, Ajay M

  • Landed Cost variable cost

    Experts,
    What is the Variable Cost tab in Landed Cost, Cost meant for?
    I only have the Fixed Cost that is active, the Variable Cost is not active. How do I get this active?
    Thanks,
    Marli

    Here is the answer:
    The tab consists of two subtabs: Fixed Costs and Variable Costs. If your company manages a perpetual inventory system, the Variable Costs subtab is disabled.

  • Material cost as variable cost

    While viewing the cost analysis of the standard cost estimate of a material after costing run, we find that the material cost is coming as a fixed value.  No value in the variable column.  Material cost is always a variable cost, right ?  But how this is coming ?

    Hi ,
    Please check wether BOM has a fixed quantity tick on that material .
    For that go to BOM , and click on the item and see the details for the material . In Basic Data tab  , you have the fixed quantity indicator.
    Regards
    Sarada

  • Fixed and variable cost component break up in PCA

    Hi,
    Is it possible to get fixed and variable cost component break up and contribution report in PCA at each product group level and lower level of node. I think this requires development. As my client requires the report to have cost break up into fixed and variable in PCA at each line item level. Can anyone solve this

    Hello
    You can get the report by using the  report painter, no development will be required.
    Regards
    Madhav

  • Cost center planning data-Plan Variable Costs in Object Currency

    Dear All:
    I have copied a standard planning layout and for the field, 'Planned Fixed Cost' and 'Planned Variable Cost', I have selected 'Plan Variable Costs in Object Currency' and 'Plan Fixed Costs in Object Currency' as the Key Figure.
    I am doing this because our Controlling Area currency is TWD and the other company will upload the planning data in RMB .
    However when I do the above settings and try to save, I am getting the following errors.
    The column 'Plan Fixed Costs in Object Currency' can input correctly but the column 'Plan Variable Costs in Object Currency' canu2019t be update in KP06 .
    ex.
    Planner profile: SAPALL
    layout :1-101
    I can't update the column "Plan Variable Costs "
    I copy the layout 1-101 and change the column to  'Plan Fixed Costs in Object Currency' and it  still can't input variable cost
    BR,
    Carol

    Hi Carol
    I have done this many times and never faced this issue
    Just delete the copied layout and Copy it again from 1-101....
    May be delete the existing columns of the layout and choose the desired key figure of object currency
    Then assign the layout to Planner Profile
    Regards
    Ajay M

  • Reposting fixed costs to variable costs

    Hi Gurus,
    one of our subsidiary company uses target=actual method in the cost center accounting. Sometimes they forget to plan some cost elements during the planning process. If some costs incurred on these unplanned cost elements, SAP put all of these costs to the fixed costs during the period-end closing (activity allocation).
    So far so good, but is there any possibility to repost these costs to variable costs on cost center level???
    Thx

    Thanks a lot for the quick reply.
    We know the splitting method but this company don't use it. For this reason I asked about a possibility if it is possible to repost the amounts from fixed to variable costs afterwards.
    I would be grateful for an other solution.

  • Product Costs Split is required, that is fixed and Variable costs

    Hi All,
    In a Sales Order screen (VA03), if we check the Costing, by clicking on EXTRAS -> COSTING, we get Total Costs, Fixed Costs  and Variable Costs.
    Can someone please help me in getting these costs, I have used Table KEKO,
    In KEKO (filtered based on Material, Plant, Sales Document, Item) and executed it, taken the resultant ProdCstgNo (KALNR)
    In KEPH used that KALNR, as a result I am getting 4 records, However 2 records are not correct, and 2 are correct. 
    In correct ones I have to add few costs to get FIXED COSTS and few costs to get VARIABLE COSTS.
    My question is, which filter should I use to get the correct record (probably just one record) ?
    Can I in some table get the summed up VARIABLE COSTS and FIXED COSTS, rather that I have to add them seperately ?
    Please help, will award points promptly. Thanks

    Hi,
    In KEKO (filtered based on Material, Plant, Sales Document, Item) and executed it, taken the resultantProdCstgNo (KALNR)
    In KEPH used that KALNR, as a result I am getting 4 records, However 2 records are not correct, and 2 are correct.
    The table you mentioned CKMLKEPH is used for Material Ledger actual cost components.
    Regd,
    Khan.

  • Table store Cost of Good Sold (Variable cost) like CK13n

    Hi,
    I need to extract the Cost of Good Sold (Variable cost ) by material as show in CK13n, what is the table I should go for ?
    I have already check KEKO & KEPH but it does not have the same figure

    Dear,
    All the data Profit Center related data for Materials is available in GLPCA.
    Cost of Goods Sold will not be directly avaialabe as a field in this table. You will have to calculate based on the business logic.
    Regards,
    Sandeep

  • Fixed & Variable Cost flow to COPA Value fields

    Hi All,
    I am using the Fixed & Variable Cost option that has to flow to COPA (under which mechanism it will flow to COPA Value fields).
    as structure based sample from OKTZ to KE4R
    OKTZ
    KE4R
    01
    10
    Raw Material
    3
    Sum of Fixed & Var
    ROHST
    Raw Material Cost
    01
    20
    Power
    1
    Fixed Amt
    VVPOW
    Power
    01
    30
    Labour
    1
    Fixed Amt
    VVLAB
    Labour
    02
    10
    Raw Material
    3
    Sum of Fixed & Var
    ROHST
    Raw Material Cost
    02
    20
    Power
    2
    Var Amt
    VVPOW
    Power
    02
    30
    Labour
    2
    Var Amt
    VVLAB
    Labour
    While I run Std cost estimate it will show me "Power & Labour" -as per KP26 Fixed & Variable
    Power
    Fixed Cost 
    15
    Variable Cost
    8
    Labour
    Fixed Cost 
    10
    Variable Cost
    5
    How it ditribute to COPA Value Fields the below amounts

    Any replies ...........pls

  • Fixed and variable cost element's cost

    hi,
    i would like to clarify. need your kind advice.
    1) can direct cost has both fixed and variable cost? can have example?
    2) can indirect cost has both fixed and variable cost? can have example?
    3) direct cost only happens in direct cost center and indirect cost only happens in indirect cost center?
    4) can direct cost center assign to fixed cost element and variable cost element? Likewise, indirect cost center assign to fixed cost element and variable cost element?
    thanks

    Hi,
    As per my understanding
    Direct cost  to a department could be variable or fixed.
    Example:  A supervisor in the X department would be a direct cost to the Dept A department. Since the X salary is likely to be the same amount each month regardless of the quantity of products manufactured, it is a fixed cost to the department. The supplies furnished to the X department will be a direct cost to the department, but will be a variable cost to the department if the total amount of supplies used in the department increases as the volume or activity in the department increases.
    Indirect cost is the Power used to operate a production machine.
    Example: The cost of the Power is variable because the total Power used is greater when more products are manufactured on the machine. Depreciation on the production machine is also an indirect product cost, except it is usually a fixed cost. That is, the machineu2019s total depreciation expense is the same each year regardless of volume produced on the machine.
    As you can see, costs can be direct and indirect depending on the cost object: product, department. The cost is fixed if the total amount of the cost does not change as volume changes. If the total cost does change in proportion to the change in the activity or volume, it is a variable cost.

  • Variable costs - KP06, KP26

    Hi,
    We have an interesting situation here - it seems as if when the user runs the KSPI transaction, it adjusts the total variable costs on the KP06 screen, and not the price on the KP26 screen, when the volumes are changed.
    Now I can see the advantage for being able to do things this way, but do not know where to do this.
    Have anybody seen the system behave like this?

    What happens, is that the adjustment to the total variable cost happens at the time of KPSI, not KSPI. So if a price has already been created, and changes in the volumes take place, then KPSI will adjust the total variable overheads, to reflect the new volumes.
    However, I have found instances during testing, where the total variable costs change, even though there has been no change in the activity hours. One reason that suggest itself, is that because of change in the capacity resource utilisation, the activity takes place in a different month than previously, even though the total activity for the year is unchanged.
    But we ar emaking use of average prices for activity price calculations, so this should not be causing the problem.
    Any ideas?
    Thanks in advance
    Piet

Maybe you are looking for

  • I cannot increase volume on Voice Memo

    Does anyone know how to increase volume on Voice Memo? I almost do not hear my messages (unless I shout or put my phone in front of my lips and talk loud).

  • How to specify the AI version which file shall be compatible with?

    With AI 12.0.0 I need to save AI files so that they are compatible with AI version 10. Adobe help Center says: "Illustrator format options: When you save artwork to Illustrator format, you can set the following options: Version Specifies the version

  • Update an object in the XIR2 repository

    One of my customers has a bad practice in place of having multiple copies of a same document in several folders. I am trying in Java to take the latest version of the document and update all the old copies with it. At this point, I have an IInfoObjec

  • [Solved] Cannot delete folder in Gnome

    I get an error when trying to delete some folders that are in the trash.  The error states it is a permission problem.  Do I need to add my user to another group?  I took a look at the groups wiki and didn't find anything relating to deleting files,

  • How do I launch firefox so that private browsing is set by default in android?

    On a desktop pc it is possible to set preferences so that firefox always starts in private browsing. I would like to have the same also on android but I couldn't figure out how to get it: I couldn't find anything relevant in the preferences. If it is