Approach on Cost Center for Vehicles

Hi Experts,
I have a requirement to analyze the cost and profit of the vehicles internally. These vehicles can be assigned from one plant to another every month. Right now the setup for cost centers is grouped by the company site only. What is the best approach on this requirement?
I have listed some solution and one of the approach was to create cost centers for each vehicle. So for each vehicle counting at around 200 should be maintained in the cost center hierarchy. Is this the best possible solution?
Also what about the Report that shows the cost center vehicles profit and loss? it should show under a specific cost center group but because of the behavior of the vehicle cost center, every time the vehicle cost center is reassigned to another cost center group, it should also show in the report that it has been maintained in the right cost center in that duration. So the report will reflect the cost center under cost center group A, example last month and another cost center group B, this month.
Also I am considering Profit Center but I am not familiar with the idea.
Please help on this solution. Thank you so much.

Hi
1. I am not sure how your vehicles are going to earn revenue.. From your question, I assume yours is a mfg concern, then how and why does the profitability of vehicles is important for your business, unless yours is a transport business.. Correct my understanding, incase wrong
2. Cost centers (CC) would not be the right approach... You cant post revenues in a cost center... They can be posted only statistically in a CC
3. Use Internal Orders (IO).. In IO Type (T Code KOT2_OPA), allow for revenue postings as well.
4.
a. Your numbering of the IOs can be same as vehicle no for the sake of simplicity.
b. Or Else, you can capture your vehicle no in any of the free fields and create a New Search (F4) help based on this field in T code OKO1...
c. Or Else, you can create new fields for IO to capture Vehicle no, include them in Structure CI_AUFK. For this use exit COOPA003
5. Once you post your costs and revenues in IOs, you can derive prof reports either from standard IO reports or create a new one using report painter
6. Now Coming to your question of identifying the vehicles under plants in which they were under a certain period - I would suggest to drop this requirement. However, if you still want to have it, then maintain a Z table in which you have fields like IO, Plant, Dates From and To. Based on this info, you need to create an ABAP report
Regards
Ajay M

Similar Messages

  • Automatically populating cost center for 551 posting

    Hi MM Experts,
    Is there any way the cost center for the 551 movement type can be automatically populated into the field without the user entering it? We are posting a 551 posting from a legacy system and jsut want to find out if I can do any OBYC settings to make the cost center come up automatically?

    I believe the above answer is best approach, assuming you are always scrapping to the same Cost Centre. You can default a Cost Centre indirectly, by linking it to the defauled GL (if it's valuated stock then technically I believe it is a General Ledger code, rather than a Cost Element).
    If you're going to do this for 551 you preumably want to do it for the other scrapping movement types 552, 553 etc. too.

  • Control G/L account and Cost Center for movement type 251

    Dear Friends,
    I would like to use mov. type 251 for GI for sale and like to control over G/L account and Cost center.
    The G/L account is by default from the valuation class of the the material and if the user will enter wrong G/L
    we had done the customising in OMJJ movement type 251 - Account grouping - Unchecked the check box of column
    "Check account assignment" - Impact is " the system always uses the G/L accounts or account assignments determined automatically"
    I also made default cost center for G/L account and plant wise through OKB9.
    Now I would like to suppress/dispaly the G/L account and cost center - for same I had done Setting in Entry control menu of OMJJ for 251 of field Account control - Value  - "-" field is suppressed. But it is not working.
    Please advise to solve this situation.
    Thanks & Regards
    Rajan

    Dear Rajan
    Yes, I have checked in MB1A earlier. We have separate node for Field seletion layout for Enjoy transaction MIGO for mvt type in which the G/L account (KONTO) an Cost center (KOSTL) have only optional or required entry selection.
    warm regards
    Ramakrishna.

  • Creation of multiple cost center for one emplyee

    HI All,
    I have requirement . one emplyee is working two projects so need create two cost centers for one employee.
    please tell me how create multiple cost center for one employee.
    Thanks&Regards
    ramesh

    hai.
    if he works half the time... u can give 50%.. or just get it confirmed from core team member..
    manu

  • How to get the cost center for the retro balance.

    Hi All
    I have this report that gives the retro balance. I get the information from RT and BAL. The problem is it doesn't show the Cost Center for the retro amounts. C1 holds the current periods payments not the retro ones.
    Does any one know how can i get the Cost Center of the the amounts that wage type /552 is showing in the RT?
    Please Help!!!

    Hi
    I am not sure on the requirement. You are developing a FI report and accessing VA03 which is sales transaction. Anyway for getting cost center you can go to table VBAK,VBAP for line items.
    Hope solves ur problem
    Thiru

  • Override Company and Cost Center for FI Posting from HR Payroll

    Hello all. I have this scenario with a company that was merged into another and retroactive payroll occurs for absences and extra time in the "old" company, but the "old" merged company is closed so no postings can occur.
    I also found this unanswered post:  How to Override Company and Cost Center for FI Posting from HR Payroll
    We suppose that retroactive differences could be accounted in the new company code but I didnu2019t found any way to do it even in the BADI SMOD_PCPO0001 I couldnu2019t find a way to change the company code/cost center....
    Does anyone have dealt with the same problem? What is the solution?

    Amosha, thank you for your response.  Here is PCP0 that shows what I mean by 'header company code' that I don't see how to change (I re-ran pd 26 2008--bi-weekly payroll, btw):
    06/30/2009 Posting Document
    Run                      0000002791
    Company Code    0057
    Document            0000008174
    PostingCurrency  USD
    Reference           HRPAY00009
    Doc. Type            ZB
    Run Type             PP
    Posting Date        12/01/2008
    Documant Type   G/L Account Document   
    Document Date    06/30/2009
    Bus. Transaction HRP1
        There are error messages for this document
    Account Number with Text
    21301000   Accrued Salaries & Wages   CCTR 14515      ...
    20303998   HR P/R Doc Split                                               ...
    Messages for Document 000008174
    Error in document: HRPAY 0000008174
    The CO account assignment object belongs to company code 0001, not 0057
    Company code 0057 is now closed and has been merged into 0001.  Cost center 14515 in the above doc was populated by my clone of RPCIPE00 and call to my BAdI which retrieved current company and cost center from PA0001.  You can see from above that the 'header' data still shows 0057 and indeed, my version of RPCIPE00 only changes P_ITEM-BUKRS, P_ITEM-KOSTL and P_ITEM-SGTXT.  It looks to me that fm HRPP_TRANSLATE_FICO gets the 'header' company code afresh.  I was planning to leave WPBP-BUKRS (and all other Payroll data) alone (ie, not override company code).
    As for your other question, we post retros to /551 and /552. 
    Thanks again.

  • Acc.assignment object replaced by current master cost center for employee

    Hi,
    I am facing a peculiar warning message while running the payroll posting run for only 2 employees.  The warning message s as follows:
    "Acc.assignment object replaced by current master cost center for employee
    Message no. 3G399"
    Prior to this, there were an error saying the
    "Account assignment objects are incorrect. No substitution is possible.
    Message no. 3G209"
    Later we found that the Position was not assigned to that employee properly.  I later assigned the correct position.. but still during the posting run the warning message appears.
    Please let me know if this is okay or is this an error which restricts the postings.
    Regards,
    Balaji TR

    Your postings will go through with the first warning message. However, please be warned that any account assignment related entries (IT 0027, 2001, 2002) will be wholly ignored.
    Check if any entries have been made to different cost centers for the erroring employees. If so, check for the reason why those entries have been made (since it is evident that the configuration does not support such entries). You may need to tie in with a CO consultant to ensure that there are no loose ends.

  • Best praxis for determining a  cost center for an HR org unit in PPM ?

    Hello all.
    We have defined the HR Org structure directly in PPM backend. Later the intention is that an interface should transfer this data from HR.
    The HR orgstructure defined works fine for the staffing process (with "resource manager via responsible organization"). 
    We have however run into some problems with the MLC & costing part.  The intention is to use manual MLC linking tasks/phases to PS WBS-elements (task based controlling).
    If we leave the org unit field blank in the cProject project project definition  we run into the message "No account assignment exists for the project defintion - no costing" and the systems rolls back from the assignment made.
    If we however assign an orgunit in the project defintion we instead get the message "No cost center could be determined for org unit 123...".
    <u>We therefore need to be able to determine a cost center for the Org Unit assigned to be able to proceed. How is this then best done?</u>
    There is a master cost center assigned to the orgunit in HR but not in PPM backend where this option does not seem to be available.
    With task based controlling the cost center does not really matter so it could possibly be hardcoded via a BADI (?) but is this really the way this should be done?
    Any suggestions?
    Thanks / Anders

    Hi and thanks for the reply.
    We will test with an ALE replicated structure so that the object ID becomes the same in the two systems as soon as possible.
    Pending that we will try the BADI option. Here I am however not sure what it is we really expect the BADI to do.  Which field should be populated with the cost center (the fields available are mainly project characteristics)?
    I also eventually found some information regarding this in the PPM 4.0 help.  I enclose info regarding this below.
    a) http://help.sap.com/saphelp_ppm400/helpdata/en/index.htm
    b) choose Collaboration projects>Accounting Integration>General Information about Accounting integration>Derivation of Organizational data.
    As I read this the system derives this as follows in case of task-based or role-based costing with no resource assignment:
    1) Look for the two BADIs mentioned to derive the cost center
    2) If no result there it looks for an org unit in the cProject header (where I assume having the Org Unit with the same Object ID in backend and ERP enables this option)
    3) If no result there the system looks for a "requesting cost center" in the account assignment object (WBS element or internal order)
    Regards / Anders

  • Assign Cost center for Price differences

    Hi,
    How to assign Cost Centre as default Cost Center for Price differences on any account?
    Thank in advance.
    Swetha

    Hi Shwetha,
    Goto OKB9 and assign your cost element to Cost center.
    e.g. My price difference cost element is 60000 and cost center is 1234.
    goto OKB9.
    Company code,cost element and Cost center.
    1000                  60000                  1234
    If you have any issue with this,let me know i can help you.
    Thanks,
    Rau

  • Direct GRN (non order items) to cost center for Non Stackable Materials

    Hi All,
    We can do direct GRN (non order items) to cost center for Non Stackable Materials.
    If it is possible.Please advice me
    Thanks In adance

    Hi,
    Your question is not clear.
    Ok.
    If you want to issue goods to cost center you can use 201 movement type.
    If you want do create automatic PO in back ground during goods receipt, you can do it with customization. For automatic PO creation during goods receipt, you can search in SDN, you can get the answer.
    Regards,
    Biju K

  • Select cost center for physical inventory difference posting

    Hello,
    While posting physical inventory differences (transactions MI07 or MI10) the choice of cost center is not offered. A default cost center is used by the system.
    Is there a way to choose the cost center for inventory difference postings? This is useful considering we have several inventories managed by several business units with different cost centers.
    Kind regards,
    Sergei Volkov

    this is from OSS note 13423:
    Symptom
    Key word: Inv acct assign
    No account assignment can be entered when posting inventory
    discrepancies.
    Additional key words
    MI07
    Cause and prerequisites
    This function is not implemented.
    Solution
    In Customizing an account assignment can be made for every inventory
    adjustment account. To do this the inventory adjustment account must
    first be defined as a cost element (Transaction KA01 / KA06):
    Accounting -> Controlling -> Cost centers -> Master data -> Cost element
    -> Create primary / secondary. Then an account assignment can be made
    for the cost element (Transaction OKB9):
    Tools -> Customizing -> Setup menu -> Accounting -> Controlling -> Cost
    centers -> Actual postings -> Automatic account assignment.
    If this account assignment is implemented every posting to the
    particular inventory adjustment account will automatically receive the
    appropriate account assignment.

  • Finding Cost Center for Position

    Dear Gurus,
        Wish you happy new year.
       I had assigned Cost Center for a position for infotype 1018. So it should store in HRP1018. Am unable to find the filed in HRP1018. Where can I find that Cost center in table so that I can make a report based on that. I searched in HRP1001 also. It is not there in HRP1001.
      Please help me where can i find the cost center for a position.
    Thanks,
    Ravi

    The Funding Approver is responsible for updating and maintaining Infotype 1018 (Cost Distribution infotype) and Infotype 9018 (Budget infotype).  The Funding Approver  is responsible for approving funds for positions.
    The cost distribution record of a Position is held on Infotype 1018, and the budget information is held on Infotype 9018 (not available in this display).
    Access Transaction:
    Via Menu Path
    SAP menu ==> Human Resources ==> Organizational Management ==> Expert Mode ==> PO13 - Position
    Via Transaction Code
    PO13

  • Block cost center for overhead account

    Dear Experts,
    My user would like to block the cost center for overhead account, gl account number 3xxxx.
    My question is, should the cost center blocked to be changed to other account? If yes, where to change the setting/configuration for overhead account to cost center? And what is the effect for this changes.
    Kindly advice.
    Thank you in advance.

    Hi,
    In KS02 you can block the cost centre for secondary postings only, if this is what you mean by 'overhead' accounting. In OKB9, you set a default of a cost object for G/L account. If you want to block the postings to cost centre completely, obviously, you will have to change the default to other cost centre. Otherwise, you will be receiving errors when trying to post to the account in question. The impact of the change will be, that every new posting to this account will be done with a new cost centre.
    Regards,
    Eli

  • HOW TO CHANGE COST CENTER FOR AN INDIVIDUAL EMPLOYEE

    HI ALL
    I WANNA CHANGE A COST CENTER FOR AN EMPLOYEE WITH OUT CHANGING THE GROUP OR HIERARCHY
    CAN U HELP ME? .....................
    I TRIED THRU PA30,PA20 BUT COST CENTER FIELD IN GREY COULOUR.

    Hi,
    We can assing the CC in two ways.
    1. is for position.
    2. or for a Org unit.
    In your case if it is for Position. GOTO PP02 enter the details as
    Plan Version    HI
    Object Type     s
    Object ID       50018133
    Object abbr.
    Infotype        1001
    Subtype         A011
    Planning status 1
    Validity        06/23/2008  to     12/31/9999
    Data sample.
    Then goto change and change the CC. this will also updates the IT0001.
    If not, You can also change through Org unit.
    Where goto PPos_old> select the org unit> then goto staff assignments> select the required position> and there is a option called goto from top menu> there you can check accoutn assignment>  there you will get diff screen to be displayed--> there select the position if you want to change and select the option maste cost center and change the CC by giving dates, this will also updates the IT0001.
    Reward me if hleps.
    Thanks,
    Vasu.

  • How to change cost center for employee

    Hi,
    I want the engineering groups to change to different cost centers for this new year.I was able to change the home cost center for a work center through IR02. But not able to change the home cost center assignment for specific personnel through PA30. SAP allows to enter the cost center but while saving it gives the error message as "Start date after initial entry date (01/01/2010)" when I used a 01/01/2011 start date and "Cost Center does not exist on 01/01/2010" when I used 01/01/2010 start date
    Could please tell how to change the cost center for the personnel?
    Thanks & Regards,
    Jegashree

    Hi Jegashree!
    The Cost Centre is always assigned in creating Position. So If you want to change Cost Centre, please using T-Code PPOME and find the position and change the Cost Centre.
    The another way, you use t-code PP01 (create) PP02 (edit) to change the relationship (IT 1001) and A-011.
    Hope you can solve it.
    Regards!
    Woody.

Maybe you are looking for

  • Error while creating Goods Receipt.

    Hi all, I am generating a goods receipt against the purchase order but the system is showing me an error message when i click the check button, the message is: Number range for Trans/event type WE in year 2011 does not exist. Now when i go in the det

  • Getting Inconsistent catalog view error  while invoking OCI.

    Hi, I am using OCI calls in my java application for communicating with the Oracle database. I am facing a problem while invoking the function "CHANGE_PACKAGE". The problem that i'm facing is: e : java.sql.SQLException: Internal Error: Inconsistent ca

  • 10.0.2 monitor delay

    I'm getting a short delay/latency with 10.0.2 but I can't figure out how to get rid of it. Just recording voice and a DI acoustic guitar. 

  • What kind of approach for new XML-based clients

    Hi. Our firm is using Oracle-technology everywhere, and now we would like to find out what kind of XML-based technology would suit us best for a new generation of our products. Our products are now using old Forms 3-clients and we're doing a research

  • How to get iWord to use hotkeys for runic letters and accents . . . ????

    Hi - Just got my first mac ever (an MBP) last week, and I'm working away on my PhD in medieval literature and loving this new computer! In MS Word, my PC has flexible hotkey options, which allow me to choose combinations to produce runic letters (the