Hi,
Is it possible to setup approvals for publishing Bid Invitations? We only see one WF (79000006 - One-Step Approval of Bid Invitation). We tried and it did not trigger a approval step. Appreciate any suggestions on how to setup approvals for Bid Invitations.
We are using SRM 4 with Classic Scenario.
Regards,
Ashwani

have you activated the workflow?
(indicated by green button.)
in the beginning try using simple start condition
e.g.
&_EVT_CREATION_DATE& >= 01.01.2008
also remove any currency if it is there in SWB_COND for sub WF
BR
Dinesh

Similar Messages

  • Reviewer functionality for Bid Invitation

    Hi,
      We have activated the 0-step approval WS14500026 for Bid invitation. We need to add only Reviewer for the the Bid invitation. I dont want the approver. But if i try try adding only Reviewer, it is not going to the reviewer's inbox as the automatic approval is carried out.
      1) If I add an approver, it is going to the reviewer's inbox. But when approval is completed, it is removed from the reviewer's inbox. Also if i try to execute the workitem before approval, there is no option to enter any comments by the reviewer.
    do i need to do anything for that?
    2) I need only the reviewer functionality and not the approval functionality.Is it possible? If so wht shld i do for this?
    Regards,
    Sivagami.R

    hi,
    can you please check the authority of the reviewer you are entering in your system?
    if he is authorized , then it should be possible for him to make changes in the workitem.
    check wether the reviewer has got the same authority of the manager you are using.

  • WS14500028 BADI WF for Bid Invitation:  No workitem is sent to the inbox

    Hi All,
    I was tasked to troubleshoot the existing workflow of the client.  The workflow was able to determine the approver who will receive the workitem for his/her approval. However, the workitem is not seen in his inbox.  Since there has been no workitem passed on to the approver's inbox, the workflow stays hanging and the document could not be converted to PO and Confirmation.
    What do you think may cause the problem? Does it also involve the implemented BADI? Does the BADI only determine the approver or does it also control the workitem to be passed to the approver?
    Please let me know your recommendations and suggestions to this problem.
    I'll generously reward points for helpful answers.
    Kindest regards,
    Reymar

    Hi Masa,
    How are you?
    I think I've met you before here in the Philippines (I just started learning workflow that time). 
    I was able to do those steps. However, the log says that the BADI WF for BID Invitation No. xxxx, GUID xxx has a waiting status and there is no icon present under the agent column.
    What do you think is the problem?
    Thanks for your response.
    Regards,
    Reymar
    Edited by: Reymar Ellazo on Mar 12, 2008 11:57 AM

  • Defaulting dynamic attributes and weightings for BID INVITATION

    Hi Friends
    I have a task at hand to default the dynamic attributes( some custom defined fields for the bidder) for bid invitation.
    Can anyone help me with this?
    Thanks in Advance
    Regards

    Hi Ankur,
    I assume you are looking for attributes automatically populated, when a user
    creates a bid invitation. Did you try to work with a template and define the
    bid invitation in the way required and create a bid invitation based on the template?
    Another option is to define the attributes for well defined categories and let the
    users use the "propose" button.
    Thanks,
    Claudia

  • User status for bid invitation

    Hi all!
    Could you give me a hand with user status for bid invitation? I made some statuses for Bid and allowed them to transaction type u201Cbid invitationu201D u2013 it seems OK. But when I try to create a bit invitation, Iu2019ve got a system error u201Cstatus profile is not allowed for bidding headeru201D
    What can I do to settle this problem?
    Thanks

    Everything OK, I select object type for u201CBidding Headeru201D

  • Mails for Bid invitations

    Hello everyone,
    I have a problem with sending mails to the bidders.
    i have created a vendor. The output format for this vendor is mail. I have given the email id also.
    when a request is created, it gets automatically converted to a bidding invitation. but the mail does not go to the bidder.
    Could someone tell me what i should do about this?
    Regards,
    Vidhya

    Hi,
        In SPRO -> Supplier Relationship Management -> SRM Server -> Cross-Application Basic Settings -> Set Output Actions and Output Format -> Define Actions for Document Output.
    In this for Bid Invitation (BBP_PD_BID) action profile in action defintion Processing time we have chagned from "Processing from selection report " to "Processing when saving document".
    Then mails are getting generated automatically.Also you need to have the SCOT settings in place for the mails.
    BR,
    Disha.
    Pls reward full points for useful answers.

  • BUS???? for Bid Invitation

    hi experts
    is there someone who knows what is the number of BUS for Bid Invitation?
    Inside BBP_PD i cannot find it.
    Thanks
    regards
    andrea

    Hi,
    BUS2200
    Kind regards,
    Yann

  • Alert for Bid Invitation

    Hello Folks,
    We have a requirement were alerts needs to be sent to Bidder i.e. 24 hours before the deadline (time/limit) as maintained under Bid Invitation.
    For this the following configuration is doneu2026
    Maintain the event and event schema for Bid Invitation (BUS2200). Under Event schema you specify the triggering event: No Bid Submitted, Published_Again etc. and also the deadline value.
    Then assign this event schema to transaction type Bid Invitation.
    Then maintain the Alert category SRM_BID_INV for Bid invitation here you specify the recipient either fixed one or role specific.
    Currently the triggering event set is No Bid Submitted for alert category SRM_BID_INV and the deadline value is minus 24.
    Issue 1:
    When a Bid Invitation already published, reaches its deadline limit i.e. 24 hours before the deadline limit. System should trigger alert and notify bidder that only 24 hours remaining to react hence please submit the bid.
    Currently this alert is not getting triggered for the deadline. Does it have something to do with Negative Deadline value?
    Issue 2:
    A new triggering event u201CPublish againu201D was set with deadline value Zerou201D0u201D.
    Now when a bid Invitation was published again system sends alerts to the Bidder notifying of the changes which is correct.
    But then system is sending the same alert thrice. How can we control this so that only one alert is sent per Object ID.?
    Issue 3:
    As specified earlier we had set up the recipient for Alert Category either on a fixed basis or role specific.
    As a result of this every alert for Bid Invitation is routing to the same list of recipients.
    Wanted to know, is there any other way apart from implementing Badi or setting rules to determine the recipient at runtime for a particular Bid invitation.Only these recipients should be notified via alert.
    Awaiting for your response.
    Thanks & Regards,
    Yatin

    rawat may be useful for you
    Bidder Alert  Notifications By Ramakrishna Rallapalli
    http://wiki.sdn.sap.com/wiki/display/SRM/Blogs
    br
    muthu

  • How to set up time zone for Bid Invitation

    Hi,
    Our client is using Surrogate Biddding. Buyer send bid invitation in SRM and when he enter Quotation after recieving in SRM, System showing "Bid is already closed", thought it has time to close.
    Where i have to maintain this time zones in SRM system for Bid Invitation.
    Thanks
    Ravi

    Hello,
    You can find the timezones of the BP's in the ADRC table, field TIME_ZONE. You can set the timezones in Tx STZBC.
    Hope this helps.
    Thanks
    Ashutosh

  • Tables for Bid Invitation in SRM 5.0

    Hello,
    Im looking for the tables in which are stored the information of the BID Invitation.
    I already found:
    CRMD_ORDERADM_H
    CRMD_ORDERADM_I
    BBP_PDIGP
    BBP_PDORG 
    But I can not find the tables in which are stored:
    - Vendor information (bidders)
    - Opening and Closing dates of the Bidding process
    - Information about Purchasing Organisation and Company responsable for the bidding process. (= names, not the org.unit code!)
    Thanks for any answer.
    Aart

    Hi,
    You can use the FM "BBP_PD_BID_GETDETAIL"  TO get all the details for a bid invitation.
    Also see these threads for more info/pointers:
    Re: How to get list of bidders registered/non registered for a bid invitation
    Re: Finding Published date of bid invitation
    Publish date of a bid invitation
    BR,
    Disha.

  • Sending  documents for Bid Invitation

    Hi All,
    What type of documents can we send with Bid Invitation? What are the advantages using cFolders with Bid Invitations.
    Thanks,
    Ravi

    Hi,
    Foll are the settings reqd:
    --.define a LS for cFolders( you have to duplicate SRM LS if it is on the same server)
    -->define an RFC destination for this system (even if same as SRM)
    -->define a backend system of type cFolders in SRM SPRO
    -->activate SICF cFolders service (with external alias)
    Normally the collaboration area should be displayed in document tab in the Bid inv screen.
    See these related links;
    http://help.sap.com/saphelp_srm50/helpdata/en/c1/c3fe3930a34b2ae10000000a114084/frameset.htm
    http://help.sap.com/saphelp_ppm400/helpdata/en/e7/1fc30727cd4ddeb7f6351416ebf591/frameset.htm
    BR,
    Disha.
    Do  reward points for useful answers.

  • Grouping functionality for Bid Invitations.

    Is there any way to group external requirements to Bid invitations.

    Hi,
    When you press the Submit to Grouping button in the Carry Out Sourcing option ,report BBP_SC_TRANSFER_GROUPED must be executed.
    Read the Documentation given in the report BBP_SC_TRANSFER_GROUPED .
    Short text
    Automatic Grouping of Requirements for POs and Bid Invitations
    Purpose
    This report groups together requirement items to which a valid source of supply has been assigned (for grouping into purchase orders) and whose product category has been enabled for grouping (sourcing option in Customizing).
    In cases where assignment is automatic, the system sets the requirement as Transferred to Grouping.
    In cases where a source of supply is assigned manually, the purchaser has to choose the function Transfer to Grouping in the sourcing application for the requirements.
    You should schedule this report periodically, and make sure that the report is run separately for each document type (purchase order, bid invitation).
    Prerequisites
    You have assigned each relevant product category to a sourcing option for grouping, for example, Automatic Grouping, Sourcing for Item Without Assigned Source of Supply.
    For more information, see the Implementation Guide (IMG) for Supplier Relationship Management: SRM Server -> Sourcing -> Define Sourcing for Product Categories.
    Features
    Report BBP_SC_TRANSFER_GROUPED provides the following functions:
    For automatically grouping requirements into purchase orders:
    It selects all requirements that have a unique valid source of supply, and have been set up for grouping. You can use selection criteria to further restrict the requirements that are selected.
    It groups requirements by vendor. In other words, it groups together all of the requirements that can be sent to the same vendor.
    You can use a Business Add-In (BAdI) to make additional groupings. If the standard system groups together certain requirements, but you want to create them in separate local purchase orders, use the BAdI BBP_GROUP_LOC_PO for this purpose.
    Note that there are some limitations to creating purchase orders this way. For example, it is not possible to group together requirements with different vendors in the same purchase order. This report uses the same differentiation criteria as the sourcing application (for example, business partner, company code, product type).
    It uses function module BBP_PD_PO_CHECK to check the assignment to a source of supply. The report passes on requirements to function module BBP_PD_SC_TRANS_MULTI_LOC_PO, where they are grouped, and converted into a purchase order.
    In a production run (that is, not a test run), the system issues error messages to the Application Monitor. Example: A contract item assigned during sourcing is no longer valid when grouping is about to occur. This error appears in the Application Monitor. The system moves the requirement item to the worklist of the sourcing application.
    The Application Monitor assigns errors to one of the following categories:
    Shopping Cart: Automatic Grouping
    Purchase Order: Automatic Grouping
    If necessary, you can copy this report, and change the selection criteria to suit your needs. You can start the report in test mode.
    Note: In the sourcing application, you can determine which requirements are planned for the next report run by choosing Find -> For Grouping.
    For automatically grouping requirements into bid invitations:
    It selects all requirements that have been set up for grouping. A source of supply is not required. You can use selection criteria to further restrict the requirements that are selected.
    You can use the BAdI BBP_TRANSFER_GROUP to take bid invitations that have been grouped by the system, and then split them up on the basis of your own customer-specific criteria. You can use the BAdI BBP_SAVE_BID_ON_HOLD to determine whether or not a bid invitation should be published automatically.
    The report passes on requirements to function module BBP_PD_SC_TRANSFER_MULTI_RFQ, where they are grouped, and converted into a bid invitation.
    In a production run (that is, not a test run), the system issues error messages to the Application Monitor.
    If necessary, you can copy this report, and change the selection criteria to suit your needs. You can start the report in test mode.
    Note: In the sourcing application, you can determine which requirements are planned for the next report run by choosing Find -> For Grouping.
    Output
    The report displays the purchase orders or bid invitations resulting from the grouping of the requirements. It also shows incorrect requirements that the system was unable to group into a purchase order or bid invitation.
    Related thread:
    SOCO Submit to Grouping functionality?
    Re: Bid invitation
    BR,
    Disha.
    <b>Pls reward points for useful answers.</b>

  • Subsequent Document for Bid Invitation - Dumpt

    Hello SRM Seniors!
    I had created a shopping cart and by this shopping cart I made a bid invitation.
    Vendors send to me the quotations and the data and time finished. ok!
    Now, I would like to transform my quotation in a purchase order or contract. How can I do this?
    Take a look in this .ppt documento what I'm have doing: [Process|http://geocities.yahoo.com.br/pedrosapmm/soco02.ppt]
    Thanks,
    Pedro Marques
    Edited by: Mr. Pedro Marques on Jun 27, 2008 7:22 PM

    Hi,
    Where can I accept the quotation in Bidder/Bids?
    [Bidders/Bids|http://geocities.yahoo.com.br/pedrosapmm/bidinv_bidder.jpg]
    [Basic Data|http://geocities.yahoo.com.br/pedrosapmm/basic_tab.jpg]
    Where can I choice PO or Contract?
    Follow-On Document was locked.
    Thanks,
    Pedro marques
    Edited by: Mr. Pedro Marques on Jun 27, 2008 7:51 PM

  • Direct Approval/Rejection buttons bid invitation

    Hi,
    The Direct Approval/Rejection buttons are disabbled while approving Bid in users Approval inbox.
    Actually I have activated wf 14500026, and the wf is only activated manually for the creator.
    I have added in tcode SWL1, tasks
    TS79007914
    TS79007919
    TS79007920
    and maintained the entry for Attributes EC_DECISION.
    however, buttons still disabled.
    Many thanks!!
    Patricia

    Hi,
    This is not my solution.
    Let me explain clearly
    1. After SC created, Buyer will add Bidders.
    2. Click on approval preview.
    3. It will be showing one concerned approver for Ex: ( MGR1)
    4. A mail will be sending to MGR1.
    5. After that MGR1 should log in and clicked on " approve all items " button.
    6. In the next screen it is asking final confirmation with YES/NO buttons.
    Here my requirement is " I need to be displayed a text above these buttons(YES/NO) ".
      So, Where do i need to do that, I mean where it is maintianing.
    Please do the needful...!
    I will be very much grateful to you..!
    Regards,
    Chandu

  • Change document for bid invitation

    Hello!
    I have created some customer fields in a bid inv header. Now I need to track changes in these fields. How can I do it? (because in CDHDR I don't see any changes for cust fields)

    Now I see changes in cdpos cdhdr tables
    But changes are not shown in the version tab
    The version management in SRM is a different concept from the "change document" you observed in CDHDR, CDPOS tables, even though they are both options for tracking changes. If you have seen change entries in CDHDR, CDPOS tables, chances are you would be able to see them by clicking the button "Display Change Document" in your document header tab, next to the "Changed On" field.

Maybe you are looking for

  • Problem switching devices

    Hello guys, trying to switch config from a 8310 to a 8900 using desktop manager 5.0.0.11. It gave an error and finished. The problem is that it cleaned information from source device. Do you know where is saved the temporary backup? Thanks in advance

  • 4K Graphics Card @60Hz for Mid-2012 Mac Pro

    Does anyone know which aftermarket graphics card supports 4K at 60Hz on the Mid-2012 Mac Pro? I can't seem to find one that does in any current forums.

  • SRM 7.0 PO Condition are not copied in ECC po

    Hi Experts!!! i am facing the problem SRM 7.0 PO Condition are not copied in ECC po, Net price is Coming instead of Gross price. & is there any BADI why which i can Fecth the Condition Data From SRM Quotation to ECC. pls help me it is go-live critica

  • Upgrading  Oracle AS from 10.1.3.0 to 10.1.3.5 during 12.0.6 to12.1.3 upgrd

    In the process upgrading the 12.0.6 to 12.1.3. WHen running the runInstaller, around 83% I get the error OPMN could not start. Any help is highly appreciated. Thanks

  • Is my installation of SQL Server Fail Over cluster correct?

    I made a 2 node SQL Server 2012 fail over cluster but having some problems during installation so I wanted to know if the steps below I performed are correct. Hardware Node1 192.168.1.10 Node2 192.168.1.11 Added following entries in DNS cluster.domai