HI SRM Gurus,
In SRM Web, after the creation and apporval of shopping cart, the buyer checked the items in carry out sourcing (professional purchaser- Sourcing- carry out sourcing). In find tab, seacrh using extended seacrh and then filling out the shopping cart number. The items should show under requirements, but in our case the system did not behave normally as expected because only one of the three items appeared.
I have checked the items using transaction code: BBP_PD then in the table, the sourcing status is "Y" and not "X". Wherein "X" is the ideal status before doing sourcing.
In our company business process is:
1. create Shopping cart (requisitioner)
2. Approval (approvers)
3. Carry out sourcing (to bid invitation-rfi) (buyer)- were some items in shopping cart did not show
4. Process bid invitation (buyer)
5. Vendor quation (buyer)
6. so forth....
please help. What are the possible causes of this error and solution. Please
thanks in advance!

HI Mutmu,
SAP MEssage as follows:
Thank you very much for your information.
We check the issue and found there is not any change log about the flag.
The flag Y is not set automatically but set by clicking
completing button.type 3 means when there is not source of supply
set ,sourcing will run.
Could you please confirm the following things for us ?
1. are all the SC have this kind of issue ?
2. Could you please reproduce in your system :" when you create another
SC with item 2 ,3 , after approving , the Source_rel_ind is set
automatic as "Y"" with the screenshot of each step?
If the problem could be reproduced in your
non-Production system , coud you please also open the non-production
with a reproducing user and provide us the reproducing Steps in
detail so that we could reproduce the issue in your non-production
system to check the issue ?

Similar Messages

  • PO Attachments using Carry Out Sourcing not transferred to Backend

    Hi SDN Team,
    I have an issue with PO Attachments using Carry Out Sourcing.
    The version I am using is SRM 5.0 which is connected to SAP ECC 6.0.
    The necessary configurations for attachments are made in ECC.
    When I create a SC through the normal procedure, with PR and PO getting created, the Attachments are getting transferred to the backend ECC, with the following code in the BADI BBP_CREATE_PO_BACK, method FILL_PO_INTERFACE.
    Code :
      clear cv_attach_use_url.
      cv_attach_transfer_active = 'X'.
      cv_attach_be_doc_type     = 'SRM'.
      cv_attach_be_storage_cat  = 'DMS_C1_ST'.
    But, when I create a SC, then create a PO via Carry Out Sourcing, that is the direct PO without PR getting created, the attachments are not flowing to the backend system.
    1. Now, is there any specific settings which needs to be made for PO Attachments using Carry out sourcing?
    2. I am aware of the BADI "BBP_CREATE_BE_PO_NEW", but even that is not helping me at the moment.
    3. There are no entries created in the table BBP_PDATT too, also no document is created in CV02N tcode in ECC.
    Since I am new to SRM, your valuable suggestions, would be of great help.
    Thanks for your assistance in advance.
    Best Regards,
    Arun.

    Please use program BBP_REQREQ_TRANSFER to create PO in R/3.Let me know you face further problem.
    Sanjay

  • SHC not appearing in Buyeru2019s worklist

    Hi SRM Gurus,,
    In SRM Web, after the creation and apporval of shopping cart, the buyer checked the items in carry out sourcing (professional purchaser- Sourcing- carry out sourcing). In find tab, seacrh using extended seacrh and then filling out the shopping cart number. The items should show under requirements, but in  our case the system did not behave normally as expected because only one of the three items appeared.
    I have checked the items using transaction code: BBP_PD then in the table, the sourcing status is "Y" and not "X". Wherein "X" is the ideal status before doing sourcing.
    Please need your help.
    Thanks!!

    Hi Hein
    NMK could be right. since purchaser might have clicked one right tick mark( it means real completed of sc). it means complete. it will be no longer in soco. sc is dead now. Thanks NMK for the clue .
    he would have pressed a tick mark before he added into work area .
    *SAP Note 1068497 -BBPSC04: Incorrect status for items completed in sourcingYou create a shopping cart which is sent to sourcing cockpit. You create a*follow-on document. For eg: Bid invitation. You delete the same and
    complete the item in sourcing. The status of the item in check status is
    shown as 'Approved' instead of 'Cannot be ordered'.
    copied from sdn thread.
    X     Sourcing-Relevant
    Y     Sourcing Completed
    A     Relevant for Automatic Grouping of POs
    D     Relevant for Automatic Grouping of RFQs
    N     Relevant for RFQ from Shopping Cart
    M     Relevant for RFQ from SOCO
    T     Temporary: Not Sourcing-Relevant
    an X-item can be seen in the Sourcing Cockpit, you need to process this requirement from here.
    Y means, the sourcing process is closed (can be forced with the button 'Complete item' in the SoCo).
    You will see no more this item in the sourcing cockpit.
    A - items cannot be seen in the sourcing cockpit. This must have already a vendor. The report BBP_SC_TRANSFER_GROUPED will do the automatic grouping and create the follow-on purchase order
    regards
    muthu

  • Customization to "Carry Out Sourcing" & "Process Purchase Order" Screens

    Hi, we are using SRM 4.0 and wondering if following screen customizations are possible
    <b>Carry Out Sourcing queue</b>
    Is it possible to use some of the existing Fields/Area to show key information within the queue that are important to Buyers such as Total PR Value, Required Date, Comment Field (for Buyer to write notes or status)? The fields Category and Quantity are not that important to us than the other fields mentioned above.
    <b>Process Purchase Order queue</b>
    Is it possible to use some of the existing Fields/Area to show key information within the queue such as Requestor Name, Required Date, Comment Field (for Buyer to write notes/status)? These are more important to us than the Purchasing Org. and Purchasing Group fields.
    The above requested fields will tremendously help the Buyer in managing the queue by making it easier to assign low value orders; by enbaling other Buyer/s to view cart status when covering for someone without drilling down per requisition/line. The comment field within the queue will help to immediately show why the order is on hold, etc.
    I would be interested to know as well if you have any suggestions on how we can assign low value orders to junior buyers faster and more efficiently and if there is an automated way to do it.

    Thanks - Here is the quick clarification. We are not using Sourcing Cockpit (eSourcing, Bidding) functionality in SRM. By "Carry Out Sourcing", I meant the area where Buyers look for workload and add approved requisitions to their work area. That is the screen we are trying to customize. Is there a template for that as well and is it easy to customize without breaking the code.
    Also please advice on customizing "Process Purchase Order" screen.
    Lastly, is there an option to autoamtically assign the Approved Shopping Cart to a Buyer based on the dollar amount?
    Thanks in advance;
    A

  • Document contains no items - Carry Out Sourcing From External Requirements

    Hello Experts,
    I have a problem in carrying-out sourcing in SRM 701 with external requirements come from ECC 6.0
    I want to process the requirements into purchase order, everything is OK because I see the line item of requirement is there. But when I check the document, this error occurs
    Back-End Error:Document contains no items
    Back-End Error:Please enter items first
    It seems SRM didn't bring the item displayed to the back-end so it keeps sending error message.
    How could that happen when I can see the document clearly contains item?
    Appreciate all the answers
    Regards,
    Ted

    Hi Dinesh / Pradeep
    Could you get a fix to this issue, we are facing the same error after we have successfully distributed the SRM Central Contract to ECC and then trying to fullfil the MRP generated PR that we used for sourcing
    We are in the classic scenario and in the classic scenario, we cannot create a Purchase ORder in ECC from SRM, it only creates local SRM PO
    Hence we are doing the following process steps for PDP with PM scenario
    1) MRP Run
    2) Push the PR as a Shopping Cart to SRM
    3) Select the Shopping Cart and create RFx
    4) Publish the RFx and Award the Vendor with the SRM Central Contract
    5) Distribute the SRM Central Contract to a ECC contract
    6) Use ME57 to turn the MRP PR to a ECC PO by assigning the Distributed backend contract as a source of supply in ECC
    We are failing step 6
    Your answer was below, but it did not end in a resolutuoin
    Please let me know the resolution to this step
    Regards
    Tridip
    Your earlier unfinished answer
    " How could we disable the error message so that we could create PO in ECC with reference to contract and purchase req. "
    - this message is due to standard config we do in ECC for matl grp & pur grp for PR transfer in table T160EX
    ECC books the combo of matl grp & pgrp for external system (SRM) and will not allow to process the PR in it.
    a procurement profile is allotted in EBAN.
    Don't think you can change the message type to Warning or info.

  • Find tab in the Carry out sourcing

    Hi experts,
    I'm working with the SRM Bidding Engine. In the Find tab in the Carry out sourcing menu there are two bottons:
    a) Add to work area
    b) Assign to me
    Could you please explain what is the difference between these two options?
    Thanks in advanced!!!
    Mar

    Hi Mar,
    both buttons support two different things:
    Add to work area needs to be pushed by everybody who wants to process a SC.
    Everybody with the authorizations can put a visibile SC into his/her work area
    and process the shopping cart; with the information given within the SC, like the
    Purchasing Group.
    Assign to me only changes the Purchasing Group (new screen follows), but does
    not move the SC into the workarea for processing. It is only an assignment change,
    to enable the assignment to a different purchaser and therefore enable the
    SC to be visible to that purchaser.
    Thanks,
    Claudia

  • In SRM Portal, while doing carry out sourcing, unable to select "Create Draft" Button Choice.

    Hi,
    In SRM Portal, while doing carry out sourcing, we are unable to select option "CREATE DRAFT"  Button choice. We have two users, one with standard role "/SAPSRM/ST_PURCHASER - SAP SRM: Strategic Purchaser" for whom Create draft is working fine. Another user who has the custom copied version of this role is not able to Create Draft since the button choice option is not opening for him.
    Web dynpro component - /SAPSRM/WDC_DO_SOCO_GAF_2
    View                            -  V_AO_SOCO_GAF_2
    Could you please help me to locate the code where this button choice is populated? What are the parameters that need to be checked in Roles to identify the reason for this wrong behaviour with custom role?
    Regards,
    Jeena

    Hi,
    Check entries in SM30 --> /SAPSRM/V_SOCO but, there should not be any issues here, as you are telling that it is working for Standard Role.
    Please overwrite the Z role one more time, and ensure that you have given proper authorization in the Org Level of the Role and regenerate the profile. It should work.
    Ganapathi

  • Part of a SC item carried out sourcing , another part can be sourcing too?

    we used SRM 7.0.
    part of a SC item carried out sourcing , another part can be sourcing too?
    for example , SC item 01 which include 1000 pc A.
        1st, we create RFx reference item 01 with 600 pc A
        2ed, can we create another RFx with remaining 400pc A ??
    regards
       claud

    Hi Claud,,
    Jay is absolutely right. You cant source the item even if you have left over quantities. Infact I was curious to try out your scenario and for me it did not work out like you mentioned. Once I created a PO for 60, I could not find the SC back in SOCO for the remaining 40. Wondering how you managed it.
    Regards,
    Nikhil

  • The default value of purchasing group in "carry out Sourcing "

    Dear , expert :
         I work in SRM7.0 ,ECS!
       I have two questions about the screen of    "carry out Sourcing ":
    1,How can set the default value of purchasing group ?Now the default is empty .
    2.The purchaser can select many purchaser group here ,I want to know what controls this .in the group responsibility ?
    Thanks!

    Hi Alex
    If there are more purchase group responsible for one product category. the end user (requestor) can select which purchase group before he order a cart.
    so that sc goes to respective purchaser cockpit  in the sc ?
    if you have only one purchase group responsible . no probem
    or
    redistribute workload
    you can distribute your cart to another purchaser
    for eg. initailly ALEX is purchase group in the sc.
    now you can transfer MASA purchase group  via redistribution workload
    so now the sc shows in the MASA cockpit with new purchase group as MASA instead of ALEX purchase group name
    br
    muthu

  • SRM 7.0 Extended Classic - Add Search Fields to Carry Out Sourcing

    Does anyone know how to add company code and location to the search critera screen in carry out sourcing?

    Dear Poster,
    As no response has been provided to the thread in some time I must assume the issue is resolved, if the question is still valid please create a new thread rephrasing the query and providing as much data as possible to promote response from the community.
    Best Regards,
    SDN SRM Moderation Team

  • Carry out sourcing

    Hi all
    I am new to SRM.
    We are having an  issue:
    Shopping cart is created in srm
    under define sourcing for product category we have maintained:
    category id      sourcesyst                                             sourcing
    300002                   SEDCLNT203(this is our r/3 system)      sourcing always carry out
    even though the SC are created i search it in  carry out sourcing, and i find it and after i assigned a vendor to my sc and i click on next button but when i want to created PO in trancaction type i have this error: No transaction types available in SAP SRM
    pls guide me with this issue.
    Thanks,
    Elham

    Hi Elham,
    Are you running SRM One Client with ERP?
    If so, please customize your system as per the configuration guide from SAP Service Market Place below.
    http://service.sap.com
    -> Release & Upgrade Info
    - Installation & Upgrade Guides
    - SAP Business Suite Applications
    - SAP SRM
    - SAP SRM Server 7.01
    - Configuration Guides for SAP SRM 7.0 EHP1
    - SAP SRM 7.0 EHP1: SAP SRM on One Client with SAP ERP
    Regards,
    Wendy

  • Approval links not appearing in approver's outlook mail box

    Friends,
    I am facing a problem with the approval mails of shopping carts to approvers. The approval links in the outlook mails are not appearing -
    Error is :
    Document contains errors. Log on to the system to process the document
        - Approval or rejection via e-mail not possible
    The shopping cart has been approved by 1 approver  and awaiting approval by the next approver , who receives the approval mail but the approve/reject link is not appearing in the mail.
    Any help will be highly appreciated.
    Thanks
    sparsh

    Hi,
    Check whether the deafult printer has been mainatined for that approver user and also the FORWARD WORKITEM attribute has been checked in the org structure in PPOMA_BBP.
    if you are using program RBBP_NOTIFICATION_OFFAPP to generate offline approval email.. if yes then select checkboxes HTML text and approval links.
    See this thread for more details:
    Re: Approver is not getting Approve/Reject links in his email
    BR,
    Disha.

  • Contract item not appearing in Shopping cart sourcing

    Hi Team,
    I created a contract from External Catalog that has  Description and Product Category, but no product ID for the item selected.
    Now, I created a Shopping cart from the same catalog. I need this Contract to appear in the Sourcing area of the shopping cart, but since there is no product Id, the contract is not appearing.
    How can I resolve this. This works perfect if I create a Contract for item with Product ID.
    Please help.

    Hi,
    In your case, Vendor Product Number (Supplier Parts Number) is required.
    Please make sure that Vendor Product Number is in catalog and contract.
    Regards,
    Masa

  • Carry our Sourcing link not present in EP for SRM 7.0

    Hi
    We are using SRM 7.0. When we create a Shopping Cart then as per the configurations made it should be present in Purchaser's Sourcing cockpit for further action. However when we log in as Purchaser we do not see the "Carry Out Sourcing" link at all even though all the possible roles have been assigned to him in Portal. We get the Strategic Purchasing link but there isn't anything within it.
    Can someone kindly give us a few leads to solve the issue.
    Regards
    Manoj

    Hi,
    Please logon as administrator to Portal and check the Role in Portal contents.
    pcd:portal_content/com.sap.pct/specialist/com.sap.pct.srm.srm70/com.sap.pct.srm.core.fl_core/com.sap.pct.srm.core.fl_roles/com.sap.pct.srm.core.ro_operationalpurchaser
    If the iView is missing, you can add it.
    portal_content/com.sap.pct/specialist/com.sap.pct.srm.srm70/com.sap.pct.srm.core.fl_core/com.sap.pct.srm.core.fl_roles/com.sap.pct.srm.core.ro_operationalpurchaser/fl_purchasing/fl_overview/com.sap.pct.srm.core.ws_purchasing/fl_central_functions/com.sap.pct.srm.core.iv_soco
    Regards,
    Masa

  • Service PO sub line items not appearing in PO print out

    Hi,
    Service PO line items under item details are not appearing on print out...
    Where are they stored ..means in which table?
    Regards

    Hi SSingh,
      Has this problem been solved? we have a similar problem here --- after upgrading from 4.6c to ECC6.0, we found that the service PO line items are not being shown in the PO printout.  This happens for items that have been marked 'delivery complete'.
      How do we get the service lines to print out again?  Appreciate any help out there!

Maybe you are looking for

  • Can't get sound from USB input device

    I've got an Alesis iMultiMix 8 USB mixer plugged into my shiny new MacBook Pro (running Leopard). The Mac properly recognizes the USB Audio Codec as a sound input device, and in fact shows a signal being received from the mixer. However, I don't actu

  • TIMECAPSULE IS AN EXTERNAL HARDRIVE

    spiritlevel wrote: Oh God ,ur gona hate me, my Timecapsule is an external hardrive ! No, it isn't. It's a combination of wireless router and network hard drive. Why would i need to spend more money on another external hardrive,my TC was the most expe

  • 23.98 frame rate

    I have HD footage that has a frame rate of 23.98 fps. Can I edit Final Cut Express 4.0.1 without it converting the frame rate to 25fps? There's no setting in the Esy Setup for 24fps, so I am assuming it will have to re-render everything to 25fps ever

  • DBAdapter Import Errors of OSB 10.3.1 projects in OSB 11.1.1.5 Eclipse

    Hi, I am in th eprocess of upgrading OSB 10.3.1 to 11.1.1.5. I am also using DBAdapter in the OSb Services. To upgrade the projects went to sbconsole of 10.3.1 and selected Export Resources and also selected Include Dependencies. Once the jar was exp

  • XMLDataSet and Dynamic XML using JSP

    I am trying to use the XMLDataSet function to call a jsp page instead of an xml file. The jsp page fetches records out of a db and creates xml to return to the spry function. Nothing seems to be returned, and blank spry data region on page. If i supp