Assessments expenses and revenues / orders and wbs elements

Hello gurus,
I have created two different structures:
- Statistical WBS Elements for allocating all the planing data.
- Internal Orders assigned to the WBS Elements for allocating all the actual data (expenses and reveues: item category of cost elements is 1).
The issue is that periodically i need to distribute these things:
- Plan data from one Statistical WBS element to others Statistical WBS elements. As the WBS Elements are statstical i really do not know how i can distribute those plan costs, i mean, how i can create the assessment cycle? which steps i must follow up? which transactions allow me to do this?
- Actual data from internal orders to others internal orders. Exactly the same questions that in the paragraph before... The problem here is that i know how to create assessment cycles using cost centres as senders, but the transaction (KSV5, KSU5) do not allow me put order as a sender
Thanks in advance for your help.

Plan data for Statistical wbs elements are not eligible for assesments/distributions and settlements.
In actuals , orders can be set as senders and receivers. Use trans KCAU to customize yur assesments.
I hope it helps.
Pan

Similar Messages

  • Internal orders to WBS Element

    Hi,
    I,m working in a Project System implementation project, where all other modules are already in use.As per the existing process, Internal orders are created for asset accounting.Those are of statistical. All the purchase orders & costs are booked referring to the internal orders, the same cost is directly settled to Asset Under Construction or Asset.As the internal orders are created as statistical, there is no seperate settlement process & all the costs are directly settled either in AUC or in Asset as & when they are incurred(posted).
    Now as we are implementing Project Systems, Internal orders are going to be replaced by WBS Elements. Customer requirement is the same process of online settlement of costs to Assets from WBS Element & he doen't want to settle seperately.
    Now the issue is, 1) how the process can be mapped in SAP?
    I feel creating the WBS elements as statistical, the same process can be mapped. Is it possible/
    2) As one project is already in progress & some postings have been taken place against internal orders, customer wants to see all those postings on new WBS element, now how to migrate the same to respective WBS element in the new system?
    Thanks
    Kishore

    Hi Kishore Ji,
    For your question, simple answer is, you want to continue all AUC under Project Systems.  So far, you have considered statistical internal orders, anyway, which is not possible for you to settle directly.  So, please take that amount generate uploading document by using same account and using WBS element as debit and internal order as credit and status you release for internal orders.
    WBS elements you create as statistical without selecting account assignment category.
    Your problem will be solved.
    Assign points without fail.
    ALL THE BEST.

  • Link of vendor in sales order through WBS element

    Hi
    My sales order line items are having WBS assigned.All these line items are direct bought out items from vendors and supplied to customer.
    Please suggest me link of vendor in sales order through WBS element.
    I want to use the same logic for billing split criteria for individual line items(hence for individual vendors) Presently my client is getting common invoice for all line items but they want separate invoice for each line items.
    Awaiting for your valuable inputs
    Thanks
    Manoj

    Hi Manoj,
    I need to understand your process in more detail.
    How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
    Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

  • Uploding the order to wbs element

    Hi Guru's
    Plase any one suggest me
    How to make data transfer orders to WBS elements.
    Thanks and Regards
    siva ala

    Yes you can....if you use Easy cost planning & Execution services....In ECP you will add materials to WBSE...and use Execution service to create PR directly for the material assigned to WBSE

  • Sales Order with WBS Elements

    Hi,
    I have a sales order having lot of WBS elements assigned.....but I am not able to generate revenue  for one WBS element out of them.
    Can anyone tell what should I do for the same.
    Regards,
    Krishna Singh.
    Edited by: Krishna Prakash Singh on Oct 30, 2008 7:53 AM

    Hi,
    Please check in CJ20N , whether this WBS e has been marked as a billing element or not.
    I think this is not marked as a billing element.
    Thanks,
    Dhruv Kumar Malhotra

  • Creation of Documents and assigning it to WBS Elements

    Hi all,
    I have a question regarding creation of documents.
    I am using T-code CV01N.....
    How to create the document and how to assign it to a WBS Element?
    Do we have any BAPIs or FM available for this?
    Thanks in advance....

    Hi Raj,
    Documents can be created/checkin  from WBS/activity without going to CV01N. For this, you need to have the DMS configured.
    Another way, Create document using transaction CV01N and attach manually in WBS/activity from Project Builder.
    Srinivasan Desingh

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • Tables for Budget allocated and spent for a WBS element

    Dear experts,
    I am new to PS domain, kindly tell me the table names where I can find the Budget allocated to a WBS element and Open budget for a WBS element.
    Thanks & Regards,
    Murthy.

    Hi,
    I think by conversion cost you mean Production cost of the turbine.
    Since you do both the actvities Material procurement and production under the same WBS. The budget cannot be tracked separelty.
    Have 2 different WBS strucute one for procurement and one for production. However you can add the existing Nwk activities to these WBS.
    Regards,
    Ramesh-

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • Getting Billing Element in Purchase Order Using WBS element.

    Hi,
    What is the process and logic to get the billing element and the corresponding Sales order details using the WBS element or network of the account assignment category in the Purchase order line item.Please suggest the tables to be used to fetch the Sales order details using this procedure.
    Thanks
    Anand

    Project PO can be generated in following methods.
    1.When a Material attached to Activity in the Project, PR can be generated with A/C assignement Q. System wil copy the WBS element to which activity is assigned in the account assignment tab of PR. When PO is created with reference to PR, system wil automatically copy the  WBS from the PR in to PO account assignment tab.
    2. U can directly create PO with account assignment Q and assign WBS in account assignment tab.

  • Settling of Cost for Production Order via WBS Element

    Hi Gurus,
    Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
    I have a scenario here as below:
    I have various types of production orders:
    PO 1 = Production A
    PO 2 = Production B
    PO 3 = Production C
    And for each of the above, I will individually have a WBS Element.
    PO1 - WBS Element A
    PO2 - WBS Element B
    PO3 - WBS Element C
    And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
    Appreciate your kind feedback on the above on how I can make it work in the PP Order.
    Thanks.
    Rgds.

    Hi Manoj,
    I need to understand your process in more detail.
    How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
    Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

  • Copy partner function from sales order to WBS element

    Hello
    Does someone know if it is possible to copy the partner function and its assignment from the sales order to the WBS element?
    In our project, we create sales order with article having a strategy group (85) view MRP3. Thanks to that a network and a WBS element is created in background based on template. In the template a partner determination procedure is maintained => partner tab in the WBS element is displayed (CJ20N) but the partners maintained in the sales order are not populated.
    Is something missing in the customizing?
    Is it possible to do it in standard?
    Kind regards
    Chris

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • COPA and service orders and contracts

    We have service order billings using orders created by customer service.  When the service order is billed, the order numberAUFNR) is included on the billing document and thus GL entry.  These do not post to CO-PA until the service order is settled.  Some of the characteristic data is lost in this posting.  How can I make these go to CO-PA as the actual postings and the service order as statistical.

    Vinay,
    I dont think you need any Middleware adaptor objects for CRM Request download .
    You need to create a request in CRM using R3AR2 . Here you need to provide the R/3 table name and field name to download the service document along with Document ID
    You can monitor your request download in txn R3AR4.
    But as MCG rightly told , you should have done all requried customized settigns before downloading service documents .
    Regards
    Dinesh

  • Issue in settlement of sub orders to WBS Element

    Hi Team,
    Request your help in getting the below issue resolved:
    Our client would like to have the sub order cost details to be settled to the superior order settlement reciever (In our case it is WBS). So we have changed the configuration in the Distribution rule in SPRO to "DIstribution Rule from Main Order". With this change the WBS Settlement receiver is getting populated automatically during release of the sub order. But when we are trying to do the settlement in KO88 we get a message that "Either the order is settled or there is nothing to settle". Please let us know incase of any setting being missed out.
    Thanks for your help in advance
    Regards.
    Priya

    by moving thread to  forum http://scn.sap.com/community/erp/project-systems or http://scn.sap.com/community/eam may generate favourable replies.
    Thanks
    Ritesh

  • Settlement of wbs element

    Good morning all ps guies
    I need help from u
    I m doing customer project. My top WBS element is account assignment and billing element.
    This wbs is assigned to scales order .I m getting cost and revenues on this wbs element.
    Now i want to settle this wbs element. One way is to settle to co-pa, as this wbs is carring both cost and revenues.
    But co team decided not to implement co-pa.
    so where can i settle this wbs element? and how?
    can i settle to cost center?   scales order?
    Please give ur suggessions
    regards
    shashankl

    Hi Gurus,
    I am loading the REAl ESTATE data through LSMW-BAPI.
    I need to load the settlement reciever as WBS elements.
    While loading the data i am getting  the error
    WBS element does not exist even though it is existing in the client and master table as well.
    KIndly let me know what can be done regarding this??

Maybe you are looking for

  • Conversion of Characteristic Values to SIDs is taking long time

    Hi Experts,     Cube load is taking more than 7 hrs to complete for 6 million records. Max time is at Conversion of Characteristic Values to SIDs. Cube consists of 500 fields. Load is from DSO to Cube. DSO has 10 fileds with no SID flag check for act

  • White backgrounds need to be white!

    Hi I'm new here, excuse the basic query.  I have a background to an image which is off-white.  I need it white.  I have tried using the Image>Adjustments>Replace Colour tool but the white remains off-white.  What am I doing wrong? Jason

  • Adobe flash player won re-install

    A few days ago i started experiencing problems with video players and adobe flash . For some reason in the middle of a video the screen turned green and started making static noise. I also couldnt use some websites and their features because they sai

  • Making two more mysql_query on one page

    I wrote a function that will return an xml string from a record set from mysql, then feed it into another function that transform it with an xsl file to html. The function works great for one query to the database per a page. Problem: The first query

  • How can I type colon when I configure my e-mail on an iPhone??

    Look at this link: It shows how to configure Google Mail with multiple POP clients when you want the mail to remain on the mail server after being downloaded. http://mail.google.com/support/bin/answer.py?hl=en&answer=47948 It states that "recent:" ne