Dear Experts,
I am buying asset by PO. As far as I know, when we check goods receipt field in PO, system must use MIGO ( goods receipt ) date as capitalization date of asset. but when I try to do MIGO for such an asset, system shows me following error:
- Asset 1111 111000010-0 is incomplete, check the asset Message no. AAPO184
Diagnosis
The 'incomplete' indicator was set for asset 1001 111000010-0 because required entries were not made.
After investigating I see in asset master data, that asset does not have capitalization date and system consider that asset incomplete. ( I created asset at the time of creating PO ). please tell me why this happens and system needs capitalization date while capitalization date for that asset must be MIGO date. and system must not stop me and show error.
Regards,

Hi rakesh
Capitalization date were system will calculate the actual depreciation and how it can be GRN date ??
When you create assets in master data system you have to give capitalization date not as GRN  date

Similar Messages

  • How to change Asset Capitalization date ?

    Hello
    All Experts,
    I want to chnage asset capitilizatio date so how can I ?
    Experts guidance is needed.
    Regards,
    Pankaj.

    Hi,
    You can change the asset cap date at any point of time using AS02.
    But the date in the First acquisition on cannot be changed, since it is a display field.
    At the time of changing the cap date, system will shows an warning message like below.....
    You should no longer change the capitalization date
    Message no. AA225
    Diagnosis
    You have changed the asset capitalization date.
    You can make this change, however this warning should make you aware of the consequences of such a change.}
    And what is the business requirement to change the cap date?, since if you have already posted the dep posting, it doesnot make any adjustment to it.
    Thanks,
    Srinu

  • Asset Capitalization Date change

    Dear SAP Gurus,
    We uploaded the opening assets in 2006  and the cpitalization date updated as 31.03.2006. Now our asset accounts team
    wants to update the actual capitalization date .
    Shall we change the capitalization date now? what is the impat ?
    Is there any SAP notes available is this regard?
    urg please...
    Tamilselvan

    Hi Tamilselvan,                                                                               
    it can have impact on the derpeciation calculation.
    Perhaps it have impact on reporting (for example RAGITT_ALV01  if some transactions are posted bevore the  capitalization date.                                                                               
    perhaps the following notes will help you.                          
    50970   When and with which date is an asset capitalized?           
    548899  FAQ depreciation asset accounting                           
    Generally this should not be really critically.
    Regards Bernhard
    Edited by: Bernhard Kirchner on Apr 21, 2010 2:31 PM

  • Asset capitalization date not appropriate

    Hi,,
    Please tell me while I run Asset settlement through KO88 in period 7 ie, 22October 2010 asset capitalization and first acquisition date become 31.10.2010 instead of 22.10.2010. Because I executed asset settlement through KO88 on 22.10.2010 which is appearing 31.10.2010. What is the actual logic of taking advance value date instead of taking current date? Is it taking entire month and value is stamped on asset master as last day of month.....
    Regards,
    Samrat

    Dear Samrat,
    when you enter the capitalization date manually the system uses this date as the default asset value                    
    date when you post the first acquisition to the asset. If you do not  enter a capitalization date in the asset master record, the system   automatically adopts the asset value date of the first acquisition   posting as the capitalization date. The system inserts the asset value    date of the first acquisition posting in the capitalization date field   (Capitalized on...) in the asset master record, when a capitalizing   transaction type is used.                                                              
    Please check your customizing in IMG: Asset Accounting > Transactions  > Specify How Default Asset Value Date is Determined                                                                               
    The System logic with Asset capitilisation date is as follows:                                                                               
    When no capitalization date is entered in the asset master record  the posting date of the first posting will be taken  as the      capitalization date not the asset value date.                                                                               
    Documentation:                                                                               
    R/3 Library:                                                                
    Asser Accounting > Basic functions for transactions > Dates in Asset accounting                                                                               
    Default Values for Asset Value Date:                                                                               
    - Initial acquisition > Capitalization date from master record (if in      
       same FY, otherwise posting date)                                         
    - Settlement of AuC > Posting date                                                                               
    Set 'Prime Rule' and 'Alt.Rule' for each transaction (in your case it is    
    for transaction 'Settlement of AuC')                                        
    Regards Bernhard

  • Where to down load assets with Asset Capitalization date and Book value..

    Hi All,
    What is table/Transaction code  to down load Asset with below details:
    1) Capitalization
    2)  Acquisition value
    3) Book Value
    4) Book Dep Value
    5) Cost center
    Thx In advance..
    Regards,
    Shirisha

    You can try the Asset History Sheet report S_ALR_87011990 (which has all fields except for cost center) and if you want additional fields you can choose to add new fields through the link [Include own fields in FI-AA standard ALV |https://wiki.sdn.sap.com/wiki/display/ERPFI/IncludeownfieldsinFI-AAstandardALV] the relevant report for Asset History Sheet should be Asset History Sheet -> FIAA_SALVTAB_RAGITT includes CI_REPRAGITT (out of RAGITT_ALV01). Else a quicker option would be to perform a vlookup process from another report that has cost centers like S_ALR_87011979.

  • Asset Capitalization on date...!

    Hi,
    I got one requirement where .... while creating the Asset the asset capitalization date should be defaulted with the date of the AUC settlement date or with today's date. Can any please let me know.. any Exits/BAdi which will help to this requirement.
    Thanking You.
    Regards,
    Anjan...

    Hi..
    Thanks for your reply... but the captalization date is Under "General" cna u please let me kow whe this-(Badi given by u) one will get trigger..
    Cheers...
    Anjan...

  • Asset Capitalization on date...!-require Exits or Badis

    Hi,
    I got one requirement where .... while creating the Asset the asset capitalization date should be defaulted with the date of the AUC settlement date or with today's date. Can any please let me know.. any Exits/BAdi which will help to this requirement.
    Thanking You.
    Regards,
    Anjan...

    Hi,
    Good evening and greetings,
    In the following path you can customize your requirement
    SPRO > Financial Accounting > Asset Accounting > Transactions > Enhancements > Develop Enhancements for Asset Value Date
    Please reward points if found useful
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Asset value date in case of multiple GRs

    Hello All,
    Could you please advise on the below issue.
    I have created PO with one line item for quantity of 5 for acquiring 5 Fixed assets. Created 5 GRs with different dates as mentioned below
    S.No. GR posting date Asset No.
    1 18.08.2009 190698
    2 28.08.2009 190699
    3 10.08.2009 190700
    4 06.08.2009 190701
    5 03.08.2009 190702
    In 1st asset capitalization taking 18.08.2009 which is Ok, for 2nd Asset also capitalization date taking as 18.08.2009 ( i.e. 1st GR date), for 3rd Asset capitalization date taking as 10.08.2009, for 4th Asset capitalization date taking as 06.08.2009 & for 5th Asset capitalization date taking as 03.08.2009. That means capitalization date it is taking as Oldest GR date. But essentially capitalization should pick from GR posting date (i.e.for 2nd asset it should take capilization date as 28.08.2009 instead of 18.08.2009).
    Could anybody has clue why system is picking 1st GRN date when I have posted 2nd Asset.
    Thanks a lot for your help in advance.
    Regards
    Srinivas

    Hello
    Please check the Document Date for the same
    Thanks
    Pramod

  • Asset acquisition date (How to change?)

    Hi all,
    As per http://www.jt77.com/financials/finan-15236.html
    Asset capitalization date = 1day of depreciation calculation
    Asset acquisition date = day of first cost allocation to the asset
    Asset value date = date of effect in asset account of a posting
    From the above dates, I would like to have a try to give my understanding on them.
    Let say I have acquire an asset through a PO -> GR -> IR on 15 Oct 2007.
    If I set the Cap Date as on 01 Nov 2007, and Asset Value date as on 01 Dec 2007, does this mean that ...
    <u><i>Question 1:</i></u>
    <b>My Asset depreciation will starts on Dec, with 2 months depreciation, which is Nov and Dec (because my Asset Cap Date is on 01 Nov 2007)?</b>
    <u><i>Question 2:</i></u>
    What if I want to <b>change the Asset acquisition date</b> to, say 01 Nov 2007?
    I tried AB08 to reverse the asset, and change the GR posting date (through MIGO), and these date affect asset value date only.
    I tried also to reverse the IR (using MR8M) and re-post the IR using Miro, with different Invoice and Posting date, these date only affect the FI documents.
    I tried AS02, and I can only change Cap date, and NOT the acquisition date.
    Please help on this, and clarify the usage / importance of the acquisition date.
    As per AS03 (wrong first acquisition date)
    Andreas Mann said that crucial is the "asset value date" (field BZDAT)it should be 31.05.2007, than first acquisition date is not important

    Capitalization Date= Date on which the asset will be capitalized
    Acqusition Date= Date on which first transaction is done on the asset after creation.  It cannot be changed once a value is posted to the asset
    Asset Value Date is important to determine the Depreciation
    Asset value Date determines the postings to the asset.  You can set the configuration for default asset value date. It is the date with which user wants to post to the asset, i.e it can be Document Date, Posting Date, Capitalization Date, Goods Receipt date. Check the list in
    <b>Asset Accounting> Transactions> Specify How Default Asset Value Date is Determined</b>
    Ordinary Depreciation Start Date Date on which the system starts calculates and posts depreciation
    Ordinary Depreciation Start Date can be determined by the system through Priod controls defined or entered manually by the user.  If entered manually it surpass the system calculated date.

  • Changing capitalization date

    hi there
    My effort is to add tax (area 10) values to existing assets.
    As of now I have  an asset.
    capitalization date 1/1/2003
    book deprn start date as 05/30/2003.
    but we want , for tax purposes, in area 10, we need the deprn start date as 1/1/2002.
    The system is only calculating accum deprn in as92 (for area 10) ONLY if i put the capitalization date as
    1/1/2002.
    PLease let me know what would be the implications if I change this to 1/1/2002 on the book deprn values.we are in 2009 and change the fiscal year.
    Thanks
    MSJ

    Hello
    I don't think there is any major impact.
    Ensure that this tax depreciation area does not post any real time entries.
    Make statistical entry as check point.
    Reg
    suresh

  • Invalid Asset Capitialization Date

    We have an asset that was accidentally entered with an Asset Capitalization Date of 10/01/0988.  Because of the bad date, SAP will not allow the asset date to be changed or allow the asset record to be deleted on-line.  How can we fix the asset?

    You can changed the Asset Capitalized date thru AS02 in master data tab.
    Check if the field is greyed. If it is then you will need to goto SPRO and into the field variant status.
    I am not sure how you capitalized. If you have settled it thru AIAB then simply reverse the document thru AIST.
    Check the above two solutions and if not then email me more details please.
    Thanks

  • How to delete an asset with a capitalization date inefaceable and no value?

    Hi all,
    An asset was created on the wrong asset class. I would like to erase it but this is impossible because of the capitalization date.
    Indeed, I cannot change the fields status variant of the capitalization date, it is compulsory.
    Furthermore, as this asset was an error, there are no values on it.
    I tried to enter a deactivation date, but this is not possible because of no acquisition performed.
    Therefore, I would like to know if it is possible to erase an asset even if a capitalization date has been entered in the master data?
    If it is possible, how can I do?
    Thanks for help

    Hi,
    This is the drawback in asset master, when you make cap date as mandatory for AS01 transaction.
    As a standard practice, cap date gets updated automatically when posting MIGO / F-90 only along with the qty.
    In your case, first ask your ABAP member to delete the values from cap date field from table ANLA. (Field Name: AKTIV) for your questioned asset.
    Then you can delete that asset with AS06 by choosing Physically delete the asset.
    This will resolve your issue.
    But if you make your field status as optional to cap date, then you must not got these kind of issues in the future.
    Regards,
    Srinu

  • Asset incorrect capitalization date

    An asset is created with an incorrect capitalization date with date feb 2007. now they found out the cap date should be 12/01/2007, so the asset is posted with addl depreciation for 10 months . how to credit depreciation
    What is the ideal way to correct it.
    Fyi..2007 is already closed.
    Any clarification is appreciated.
    Thank you

    Thanks for your response..I realize I just have to write up depreciation using ABZU, but do I need to make any changes to the asset master  to the depreciation start date
    Also when I use ABZU/ ttype 700 to writeup does it recalculate depreciation.
    Thank you

  • Regarding the Reguralization of  Asset capitalization.

    Dear Team,
    On regularization of Provisional Capitalization Entries in  System especially in the case of provisional capitalization considered in previous Fiscal Year and regularization of the same is done in the Current Fiscal Year we are encountering following issues.
    u2022     Creation Asset Master Record with capitalization date of Previous Fiscal Year
    u2022     Posting of correct depreciation in  System
    The scenario is explained with an example below.
    Provisional Capitalization Value Rs.120000/=
    Date of Capitalization u2013 01.11.2008
    Rate of Depreciation 10%
    Depreciation on Provisional Capitalization Rs.2000/=
    On regularization of provisional capitalization in Fiscal Year 2009 on 31.01.2009 in  System we are encountering the following issues.
    System is not permitting us to create Asset Master Record with Capitalization Date as 01.11.2008.
    If we create Asset Master Record with the First Date of the Current Fiscal Year ie., 01.01.2009 then the depreciation of Rs.2000/= provided in the last fiscal year is not updated in the System.
    Please note that while regularizing the provisional capitalization we used to reverse the provisional entries considered in the Financials of the previous fiscal year.
    Manual Adjustment of Depreciation will be a audit point.
    Hence please provide us a suitable solution to over come this peculiar issue.
    Regards,
    Suma.

    Dear sir,
    I am having one moreissue related to decapitalization.I am giving you theclear senario o the below.
    Initially we used to capitalize an asset on a particular date and after say a month or two we were forced to de capitalize the asset when we avail duty credit on those assets.  In other words Capitalization takes place on gross value in the first instance and de capitalization takes place when we avail duty credit in the second instance.  The de capitalization entry is posted in  System through F-02 Transaction Code.  In this scenario the system is calculating depreciation as per example given below. 
    Example:
    Asset Value   -   Rs.2,00,000/=
    Date of Capitalization - 1.12.2007
    Rate of Depreciation u2013 10%
    Duty Credit availed/De cap on u2013 1.02.2008 say value Rs.20000/=
    System Calculates Depreciation on Rs.2,00,000/= from 1.12.2007 to 31.01.2008  and on Rs.180000/= from 1.02.2008 onwards.
    If we look at this case in a practical way then there is an excess charge of depreciation on Rs.20000/= for 2 months i.e.,(from 1.12.2007 to 31.01.2008).
    Kindly guide us how to post the de capitalization entry in  System so that system itself automatically reverse the depreciation already posted in System on Rs.20000/= for 2 months earlier.
    Regards,
    Suma.

  • Asset Capitalization error

    I have created an asset Master by AS01.capitalization date is 2.5.2009, first acquisition date 2.5.2009. I already posted a entry to the above asset. In the fiscal year asset balance it is showing asset APC value and depriciation value. now I want to do change the capitalisation date to show in the fiscal year 2011 (1.4.2011).Is it possible to change the above fiscal year in the asset master data (Capitalization date/ first acquisition date). because i want to calculate the depriciation in the fiscal year 2011.
    please tell me the solution,
    Thanks in Advance

    Hi
    If your capitalisation date is 02.05.2009, depreciation should have already been posted from 02.05.2009 till 2011 Fiscal year right?
    You can go and tamper the original depreciation start date in AS02 - Depreciation area tab. System will reverse all the depreciation posted till date and calculate depreciation from the date you specify now.
    The problem you will have is, you have to take the hit of depreciation reversal for all the past periods pertaining to this asset in your current month ie the period you specify as depreciation start date.
    Change the dates and check the planned depreciation values in AW01N
    Malathi

Maybe you are looking for

  • How to get Portal user from a standalone Java application

    Hi, I have a standalone Java application from where I need to fetch the Portal User Information like userid and email id. I am using the below line of code iUser = UMFactory.getUserFactory().getUserByLogonID("e017939"); I have included the jar file c

  • I did Archive &amp;amp;amp;amp; Install with "preserve users", why do I now have NO users?

    After a hard crash on my mom's PowerBook G4 (running 10.4.11) I eventually did an OS 10.4 Archive & Install with "preserve users". I now have NO users, not even an administrator, what should I do?  The only indication I see that anything was remember

  • Need help with a manifest file

    I'm trying to make a jar file executable, and I've seen numerous questions and answers regarding this particular issue, and none of them helped me with my problem. I have a batch file that runs the application without any problem, but when I try to c

  • Flash 10.1 not working in Firefox 3.6.6

    I have been trying to get video to play in Firefox after downloading and installing 10.1 last weekend.  Sites like ESPN3, Hulu, CBS, USA, Daily Show, etc. no longer work.  Everything will load any commercials play then the player sits there and does

  • How to check whether a Document in KM is classified or not using JAVA API

    Hello Everyone,   Can anyone tell me, How to check whether a Document in KM is classified or not, using JAVA API's?? Thanks & Regards, Adren D'Souza