Asset value date at the asset posting when using F-90

Hi,
I have an asset and the first acquisition date was 10.30.2009.
I'm using the transaction F-90 (external aquisition with vendor) with posting key 50 for credit entry, 70 for debit asset and the transaction type is 100.
Why the asset value date at the asset posting is equal first acquisition date (10.30.2009)? If I'm posting 12.17.2009 the asse value date woudn't be 12.17.2009?
Regards.

Hi
The first Acquisition Date will be the Asset Value date.
When ever you going to do more Acquisitions they will be added on to that Acquisition Amount but on the Particular Dates of Acquisitions and Asset Value Date will remain the same as First Acquisition date.
Whether you do Acquisitions using F-90 or through Settlements, the Asset Value Date will be the 1st Acquisition Date.
regards
Venkat

Similar Messages

  • Different Asset Value Dates for each Asset

    Hi,
    A very interesting and unique requirement.
    We are attaching multiple assets in the settlement rule of wbs elements and run CJ88, but as per standard SAP, all assets under each WBS Element are capitalized on the same Asset Value Date.
    My client wants to capitalize assets at different asset value dates for each of these assets without needing to run CJ88 multiple times.In CJ88, however, we have only one asset Vale date option.
    Is this possible to have different asset value dates asset wise when we run CJ88 ? I did not find any option to define an asset value date in CJIC either.In Settlement rule neither.
    Thanks for any help.
    Regards,
    Manis

    Try and explore the option of using Asset Value date on the sender WBS, you can find this under settlement parameters.
    This option depends on your project (WBS) strcture and the number of assets being capitalised on back on one WBS element.
    Refer note OSS 98496 for more information
    Regards
    Sreenivas

  • Asset Acquisition with Asset Value Date earlier than GI post.date

    Dear all,
    I am curently using SAP ECC 6.0. We are not creating AuC assets but directly capitalizing assets from investment accounts.
    If a material is issued with a date in March and i try to acquire it with asset value date from a previous period, for example in February, the system doesnt issue any message and lets me post the transaction. The accountants claim that this hadnt been possible in the earlier version of SAP 4.6 that we had been using and that the system had issued an error message - "Posting not possible (Value date earlier than capitalization date)"
    The accounting logic is that you cant capitalize an asset with a date earlier than the date when it has been in use, i.e. in our case it`s the date the material has been issued from the warehouse.
    Does someone know what logic does SAP follow in this case - and if i can set a validation control that will check and compare the two dates?
    Any opinion would be appreciated
    KR
    Severina Koleva

    We are on ECC 5.0 and we do get that message, but it is a warning.
    AA348...
    that said, you can setup a validation using GGB0 and asset accounting

  • Setting the Asset Value date as the dep start date

    Hi,
    I need to pick depreciation from the asset value date and NOT the dep start date in the asset master record. Is this possible? IF it is, then what config changes needs to be done.
    Thanks

    Hi
    You can define that in the multi level method assigned to your depreciation key.
    Assign points if the information is  useful to you
    Regards
    Sanil Bhandari

  • Asset Value Date determination during settlement from Orders or WBS!

    Hi,
    I have a scenario on the asset value date and I am not sure what went wrong, asset side or CO side.
    The scenario is as following:
    1. Asset was converted into the system by 7/31/2008 with $10000.
    2. The capitalized on date is 2/29/2008 on the asset master data.
    3. On 8/31/ 2008, I charged $300 to an internal order and settled the $300 to this asset. The Asset Value Date on the Asset Explorer is 8/15/2008.
    4. On 9/30/2008, I charged #500 to the same internal order and settled the $500 to this asset, the Asset value date on the asset explorer for this charge is still 8/15/2008.
    This messed up the depreciation of this asset. Does anyone know how to control the asset value date from the settlement? Do we need to config in Asset side or in Order side? I want the $300 charge's value date is on 8/15/2008 and $500 value date on 9/15/2008. Is this possible?
    Thanks,
    Ting

    In the settlement you can fill in the asset values date.
    The first posting is the basis for capitalization date(when you don't fill it in manual), when you fill it in for the second time the Asset Value Date it is no longer relefant.
    This is only important when you have say in your depreciation key that the depreciation is based on days( see the help on this field)

  • Different Asset value dates for different depreciation areas

    Hi All
    I have a requirement for different capitalization dates in different depreciation areas for some LATAM countries .How can this be achieved?

    Hi
    Hope you can achive this requirement by entering Depreciation calculation start date in depreciation area tab of asset master against each depreciation area
    Depreciation calculation start date
    'As a general rule, the system determines the depreciation start date from the asset value date of the first acquisition posting. However, you can also manually enter a calendar date in the asset master record for the start of depreciation. In that case, the system ignores the asset value date of the acquisition posting.'
    Please check different scenarios in development system and then do it
    Regards
    Praveen PC

  • Asset value date must be in fiscal year of posting date

    Hi,
    When i try to post settlement of AuC in transaction AIBU with parameters:
    document date: previous fiscal year
    asset value date: previous fiscal year
    posting date: new fiscal year
    I know that:
    The asset value date is the value date for Asset Accounting. It can deviate from the posting and document date and be in posting periods already closed for Financial Accounting. <b>However, the posting year and asset value date year must be the same.</b> (SAP documentation).
    But maybe someone knows the way, how to post such a document??
    Regards
    Gosia

    Thanks for Your replay,
    But the pravious year is opened in FI-AA and closed in FI. We can't open previous year in FI.
    Do You know another way to solve it??
    regards
    gosia

  • What is setting for the depreciation calculate on the basis of assets value date

    Hi ,
    My client requirement to calculate the assets depreciation on the basis of assets value date,
    every assets transaction will have take base assets value date
    Acquision   1  Assets value date 1.4.2014
    transfer Assets value date 15.3.2014
    Wbs settlement  Assets value date 20 .3.2014
    second acquisition Assets value date 28.03.2014
    if anybody know about the setting ,Please provide me important setting ,

    Any setting related to assets posting variant ? to calculate if anybody know the setting please inform.

  • Asset Value Date - Wrong posting

    Dear All,
    Company code is on live, Assets legacy data taken as on 31st-March-09.
    Later we find that some of the assets [new purchases, in previous fiscal year (2008)] was not posted.
    For that recently we posted that transactions F-90 using posting date is current date and document date is Actual acquisition date.
    Due to document date in previous fiscal year system taten posting date as asset value date.   So, depreciation posting missing for previous year.
    I need your help.  How can I rectify this???
    Other than reversing the existing posting, what is the scenario????????
    Thanx
    Regards
    partha

    Hi,
    In order to post ,post capitalization please closed the previous asset accounting year.In ABNAN T.Code screen please update the original val date field with the date  of the previous year from where you need to start calculating the dep. Doc date and posting date should be of the current FY.Also check T.Code Ao90 for updating the field Revenue from post capitalization with proper GL Account.
    If your statutory audit for 2008-09 is not yet completed then you can think about T.Code AS91.While  using T.Code ABNAN the following line items are generated.
    Asset        dr
    Acc Dep         cr
    Rev form post capitalization cr
    The system will only calculate dep of previous year.For the current year dep which are yet to be posted will be posted in the next schedule dep posting run.
    Thanks
    Monoj

  • FA-retirement-Asset value date and posting date are not in same fisc year

    Hello,
    I would like to post retirement in the new fiscal year but with asset value date in the previous year so that NBV is calculated correctly. It is not possible neither in ABAON nor in ABAVN with any transaction type.
    I always get message 'Asset value date and posting date are not in same fiscal year'.
    Is there any way how to handle this?
    Thank you,
    Jan

    Hi,
    I have tried this but the settings of our Depr keys works in the way. That if you use asset value date in the new month it will calculate depreciation for the whole month.
    This means if I retire with asset value date 31.12.2008 - NBV will be calculated as at 31.12.2008.
    If I retire with asset value date 1.1.2008 - NBV will be calculated as at 31.1.2009.
    Thank you anyway!

  • Asset Value Date in Settlement

    Hello!
    We would like to settle investment measure to a completed asset, so the settlement rules have been updated with the completed asset, status of the order has been changed to TECO (technically complete).
    When we settled the order (not via u201Cko88u201D but via automated program which uses our client) it turned that out asset value date is different than posting date, so the system takes the date when investment measureu2019s status has been changed to TECO instead of posting date, as asset value date.
    Would anybody know where and how to change config, so asset value date is the same as the posting date?
    Thanks in advance for any hints.
    Regards,

    Hi,
    Are you looking for below mentioned settings...
    Financial Accounting (New)->Asset Accounting->Transactions->Specify How Default Asset Value Date is Determined
    Best Regards,
    Madhu

  • Asset Value Date Exit and Enhancement

    Hi,
    We have a requirement from customer, that the asset value date in ANY asset posting transaction cannot be less than or equal to 30.06.2014 it should always be 01.07.2014 or higher.
    So, please let me know if there is any User Exit which can be used to restrict the Asset Value Date. If yes, then will this User Exit work for all transaction codes, or we need to write different logic for every transaction code.
    Please advise.
    Regards,
    Devdatth

    Hi,
    To transfer one asset to another asset within a company code can be done through ABUMN only.
    While doing this transfer you have enter the document date, posting date, and value date for the transaction, but all these dates should be in same fiscal year only.
    In your case you must have been entered the dates for asset value date and posting date , and these two dates are in diff financial years.
    Please make sure that both the dates are in same FY.
    Hope this will fix your issue.
    Thanks,
    Srinu

  • F-90. asset value date field is not displayed

    Dear all
    In asset acquisition posting through F-90. asset value date field is not displayed at the time of entering acquisition. It is in supress mode. so system is capturing the capitalisation date. But we can see this capitalisation date as asset value date in fb03 display. Now i want to display this field as optional field while creating the entry and also i want to change the field in display mode to change mode. kindly tell me the menu path to access the settings.
    Thanks With  Regards
    RSS.

    Hi,
    You can enter a diff asset value date for your acq posting, only thru transaction ABSO using TType 100.
    This will resolve your issue.
    Thanks,
    Srinu

  • Asset Value Date & Posting Date as defaulte date

    Dear All,
    In CJ88,the posting date & value date is 31.10.2009 by default. The asset value date provided by us is 28.10.2009. The posting date & value date should be the actual date of entry (28.10.2009 in this case) by default.
    How can we do this.
    Do revert
    Regards,

    Regrettably to inform you that in R/3 standard, posting date is always 
    the last day of the period to settle as settlement is a period end     
    operation. The document date is the day when the operation is performed.
    Considering AuC is involved in this case, please check transaction CJ88,
    where you will find the field 'asset value date', where you can manually enter the asset value date you want to have.
    Blaz

  • Asset value date and posting date are not in same fiscal year

    Hi,
    Our business user has created an asset under an incorrect asset class, which he is trying to transfer to a new asset whcih was created under correct asset class. However system is restricting user with the error message "Asset value date and posting date are not in same fiscal year". Can you please advise me how we can proceed further with this error.
    Regards,
    Asam.

    Hi,
    To transfer one asset to another asset within a company code can be done through ABUMN only.
    While doing this transfer you have enter the document date, posting date, and value date for the transaction, but all these dates should be in same fiscal year only.
    In your case you must have been entered the dates for asset value date and posting date , and these two dates are in diff financial years.
    Please make sure that both the dates are in same FY.
    Hope this will fix your issue.
    Thanks,
    Srinu

Maybe you are looking for

  • Safari and Google Maps are useless

    Safari and Google Maps invariably quit and return to the home screen. They are essentially useless. I tried to empty the cache and history...no luck. I then tried a reset and when it restarted got a message to please connect to iTunes. iTunes told me

  • Is it possible to change the first page of a web application that was built using the UI?

    Hello Community     Using Sharepoint 2010 Server and the UI I built and application and would like to continue building the web application using the UI.     The application's first page was built using a Blank Site template and the subsequent subsit

  • How to download a transport package in terms of abap code

    Hi, Is there any sample code or particular FM or anyway that could download a transport package which is then used to import to another server? I've looked at a few thread regarding downloading transport package but there's no specific tables or code

  • Multiple Parameter requests for same parameter - BW-datasource

    Hi I created a Crystal report (CR1) with another Crystal report (CR2) embedded. The datasources are SAP BW queries. Both BW-queries have 0CALYEAR as input variable. If I view report CR1 I have to enter 0CALYEAR twice, once for CR1 and once for CR2. H