Assign multiple relationships at once

Hi everyone...I am working in Primavera P6 Project Management Release: 7.0 Service Pack 3 (Build #: 00033036)
When trying to assign multiple relationships at once, my computer will not allow me to capture multiple activities that have been assigned as either a predecessor or successor. I can highlight them, but when I click the assign button they all briefly flash as being captured then the assignment only shows the first activity in my complete schedule?
I am able to log into a co-workers machine with my credentials and perform this task, but not on my machine. Do you have any suggestions?
Thanks

Hello,
I assume this is all in the same project? It sounds like your project profile security settings could be different than your co-workers. I would see if there is a conflict between your settings from the admin perspective.
Check these two lines in project security profile.
Edit Project Activity
Relationships
Create, edit, and delete a project’s activity
relationships.
Add/Edit Project
Activities Except
Relationships
Create and edit a project’s activity information, except
activity relationships. To edit activity IDs, a user must
also be granted the Edit Activity ID project privilege.

Similar Messages

  • Can you assign multiple customer masters to one Business Partner in R/3?

    We are trying to configure SAP Business Partners in ECC5.0 but it seems the relationship between a business partner and a customer master is one-to-one so a business partenr cannot have multiple customers (table BD001 only allows for a single entry).  Does anyone know if it's possible to assign multiple customer masters to one business partner?  If so, is there any documentation available?
    Many thanks.

    We are trying to configure SAP Business Partners in ECC5.0 but it seems the relationship between a business partner and a customer master is one-to-one so a business partenr cannot have multiple customers (table BD001 only allows for a single entry).  Does anyone know if it's possible to assign multiple customer masters to one business partner?  If so, is there any documentation available?
    Many thanks.

  • Assign Multiple Sales Org for One Plant in STO process

    Hi Experts,
    Aware that I can assign multiple sales org to 1 plant (relationship: many to many).
    I am trying to create STOs to supplying plant and assigning them to different sales organization but encountered problem.
    Example:
    Supplying Plant 1000 - Sales Org 1000A (food) and 1000B (apparel)
    Receiving Plant 1100
    Plant 1100 wants to issue 2 STOs to Plant 1000 - 1 for each Sales Org (for instance STO1 to food division, and STO2 for apparel division).
    However, when I tried creating STO in the system, noticed that in the shipping tab (item details) the sales org, DC has been assigned to 1 particular assignment and data is locked.
    Tried to get into SPRO to configure and define the shipping data for plants but noticed that it's 1 to 1 relationship (SPRO - IMG - MM - PO - Set up Stock Transport Order - Define Shipping Data).
    How can this be done?

    You can set different sales areas (~sales organisation) for one plant in SAP - based on issuing SLoc provided STO between storage locations is activated.
    SPRO > Materials Management > Purchasing > Purchase Order > Set up Stock Transport Order > Set Up Stock Transfer Between Storage Locations > Define Shipping Data for Stock Transfers Between Storage Locations
    Edited by: Csaba Szommer on Jul 2, 2011 6:14 PM

  • Changing the display profile for multiple users at once.

    Is it possible to change the display profile for multiple users at once? We would like ot be able ot add tabs and channels globally, but right now we can anly do it for once user at a time. Also, is it possible to have certain generic display profiles that all users use? like an admin profile and a tech support profile and a normal suer profile? Any help is appreciated...

    Yes this possible using the dpadmin batch command.
    Please check the dpadmin documentation for the batch command.
    For generic display profile what you can do is create users and assign the user particular roles. The display you would be creating would be for the roles. The users belonging to that role would inherit that display profile.
    HTH ..

  • One position multiples relationships

    Hi Gurus,
      I have a scenario with my client..  There is a position (12345678) now this position is been occupied by 3 employees.. i have done that through percentage basis.. i hope i am correct till here.. now the client req is these three employees have to report to three different managers..
    can any please let me know how to give this kind of relationship when the position is same.
    Regards
    Swathi

    Hi Swari,
    You are right. Employees having same position will have same manager. Thats the reason you assign multiple employees to one position.
    You need to explain this to your client.
    If client wants employees to report to diffrent managers then you should create 3 diffrent positions reporting to 3 diffrent managers.
    This is SAP's best practice. If you implement in this way it will help in OM reporting and MSS implementations.
    If you deviate from SAP best practice your client will be in trouble in future.
    If you want to deviate from SAP best practice, you can create Custom "Z" relationships  between employee P and Manager's Position S and maintain 3 diffrent managers for all 3 employees on same position. This will have a big impact on OM and MSS and needs through investigation.
    Regards,
    Amit.

  • Assigning multiple values from a List of Values at detail (table) level

    Hi,
    I have a master detail entry screen. I want to assign multiple values when end user selects an item from the list. The field is at detail level (Table type). I can do it using the "Select one choice" type component (ADF Faces Core) but it doesnt retain the value when I go to the next record. This type of component works fine with the screen with only one record to show (form type). This component has binding with list type.
    If I use simple list with Table binding, I can not assign values to multiple items. This type of list retains value when record is changed.
    Can anyone help me resolving this issue?
    Thanks,
    CAH

    Post on Jdev forum JDeveloper and OC4J 11g Technology Preview
    --Shiv                                                                                                                                                                               

  • How do I delete multiple items at once instead of one at a time?

    How do I delete multiple items at once instead of one at a time? I have several duplicate items in my library and would like to delete the duplicates. Thanks!

    You can select multiple items using shift to select a range and control to add or remove items from it.
    Regarding duplciates, Apple's official advice is here... HT2905 - How to find and remove duplicate items in your iTunes library. It is a manual process and the article fails to explain some of the potential pitfalls.
    Use Shift > View > Show Exact Duplicate Items to display duplicates as this is normally a more useful selection. You need to manually select all but one of each group of identical tracks to remove. Sorting the list by Date Added may make it easier to select the appropriate tracks, however this works best when performed immediately after the dupes have been created.  If you have multiple entries in iTunes connected to the same file on the hard drive then don't send to the recycle bin. This can happen, for example, if you start iTunes with a disconnected external drive, then connect it, reimport from your media folder, then restart iTunes.
    Use my DeDuper script if you're not sure, don't want to do it by hand, or want to preserve ratings, play counts and playlist membership. See this thread for background. Please take note of the warning to backup your library before deduping, whether you do so by hand or using my script, in case something goes wrong.
    (If you don't see the menu bar press ALT to show it temporarily or CTRL+B to keep it displayed)
    tt2

  • How can I delete multiple photos at once from the official Photos app?

    Dear fellow Apple users,
    I have many pictures on my Camera Roll in Apple's Photos app. What's the quickest way to delete multiple photos at once?
    Thus far, I know how to delete photos one by one, but that's time-consuming.
    Thank you.

    No not box with arrow, that is share button.  Edit is where it shows in the pic I posted

  • From my music how do i move multiple songs at once to a playlist

    From( My Music) how do I move multiple songs at once to a playlist.
                                        Thanks

    Your issue has nothing to do with Apple networking. You may get better results in getting a solution if your post your issue to the iTunes area of the Apple Support Communities.

  • How to assign multiple categories to a webapp item that is populated from a frontend form?

    We have a webpage with a form that allow users to populate a webapp, but we also need that the user can assign multiple categories to the webapp item that is going to insert.
    The support forum told us that it is not possible to assign categories from the frontend, but only from the admin area.
    Is there any workaround to this issue? We do not want the users to access to the admin area because we need them to populate the webapp only from the web form.
    Thanks for any help on this.
    Franco

    Dont know if this will help:
    http://bcgurus.com/tutorials/dynamic-categories-for-business-catalyst-introduction

  • Assign multiple users to a single role?

    I have a process where I need to assign multiple users to a given role.  In this case, I want one of the users to 'win', and take ownership of the process step.  (Imagine the situation where one user is the primary processor, the other is a backup; if the primary is out of the office, i want the secondary to have the ability to pick up the request).
    I've tried to assign multiple users to the same process role as follows:
    rtm.addRuntimeDefinedUserToRole(prInstance,  roleName, user, userContext );
    but the process is only assigned to a single user - from my testing, it seems to be assigned to the first user specified using the above api call.
    Is there a way to do this programatically?

    Hi,
    Can you please advice how you did this?
    I am using Visual composer as my UI. But with looks like i am not able to pass a structure from VC so i can map it to "Assign Users to Process role" CO.
    Per my understanding I need to write a program using GPI API which populates the User_List structure of the above CO. But after that i am not sure how to use this CO. Can anyone give me detailed instructions on how to use the "Assign Users to Process role" CO to assign multiple users to the role dynamicallly?
    Regards,
    Kumar.

  • Is there a way to format multiple images at once? Change colour mode or resolution?

    Is there a way to format multiple images at once? Change colour mode or resolution?

    It's very easy to make an action.
    Go to window > actions
    In the actions panel, simply click the 'create a new action' button, it starts recording as soon as you've created it (when you've given it a name).
    Now you can apply the changes you want to make to the images on the file you have opened.
    After you've done all you need to do. You click the 'stop' button. The action is now ready to use. And you can apply the changes you made on all the other files.
    Then you can continue how gener7 explained.
    I usually include a save and close command, so that the whole batch doesn't end up opened after running the script.
    But if you do that you have to create a new file, and save it to your computer before you start recording the action, otherwise the save command will be replaced by each file. And you'll end up with one edited file in the end. At least for as far as I know!

  • ICloud keeps duplicating my contacts, any of which I need to delete anyways.  Is there a way to delete multiple contacts at once? I  have been deleting them one at a time, but they keep reappearing.

    ICloud keeps duplicating my contacts, any of which I need to delete anyways.  Is there a way to delete multiple contacts at once? I  have been deleting them one at a time, but they keep reappearing.

    I have exactly the same problem!  I have Outlook 2010 and it does the same thing with my contacts, and calender enteries!! Really frustrating

  • Insert data into multiple entities at once using a view object

    Hi,
    I'm trying to insert data into multiple entities at once using a view object, but unfortunately it doesn't seem to work. The two entities have a 1:1 association. I created a view object which contains both entities and I made sure they aren't read-only. But like I said it doesn't work, I can't insert data in both entities at once... :(
    Is this possible? And how (if it is)?

    Hi,
    I'm trying to insert data into multiple entities at once using a view object, but unfortunately it doesn't seem to work. The two entities have a 1:1 association. I created a view object which contains both entities and I made sure they aren't read-only. But like I said it doesn't work, I can't insert data in both entities at once... :(
    Is this possible? And how (if it is)? Peter:
    This is definitely supported and tested. Please send us the exception stack trace. You must running into other problems. A few things to note:
    A) You have to mark the entities as both updateable (not read-only) and not reference-only.
    B) If you're not seeing an exception stack, turn on diagnostic. Here is how:
    To turn on diagnostic, go to the IDE,
    1. Select the project.
    2. Do right mouse click and select "Project Settings..."
    3. On the Settings dialog, select Configurations/Runner.
    4. In the righthand side pane, you should see a textbox for "Java
    Options". Please add the following JVM switch:
    -Djbo.debugoutput=console
    Then, rerun. The run command should include
    -Djbo.debugoutput=console as in
    "D:\JDev9i\jdk\bin\javaw.exe" -Djbo.debugoutput=console -classpath ...
    You should now see a lot more output on the IDE's message window. Here you should see the exception stack trace.
    If you invoking your app directly from command prompt, just add "-Djbo.debugoutput=console" after your "java.exe".
    Thanks.
    Sung

  • How to assigne multiple value in key of read table

    Hi gurus,
    I want read table xxxx with key field1 = ' xxx' or field1 = 'yyy'.
    how to assign multiple value as key for the same field while reading internal table.
    Regards
    sagar

    Hi ,
    You can loop the internal table like
    loop at  <table xxxx> where field1 = ' xxx' or field1 = 'yyy'
    or you can write two read statements to read the internal table in wrk area.
    read table   <table xxxx> with key field1 = ' xxx'.
    if sy-subrc <>0
    read table   <table xxxx> with key field1 = 'yyy'.
    if sy-subrc = 0
    endif.
    else.
    do your data processing.
    endif.
    Thans.

Maybe you are looking for

  • How to determine Which Database I am Connected to?

    hi everyone, 10g I'm going to drop a database via SQL Plus. I forgot the command that will show which db I'm connected to. Dont want to delete the wrong database! Thanks, John

  • Can't connect to Configuration Manager Service manager

    So after a failed upgrade to R2, I've had to restore the database as the R2 upgrade corrupted the DB. I am now working though the minefield of component errors. However I can't connect to the configuration manager service manager, I get this error: E

  • Add vendor number and vendor name to the SAP Standard CO/PS Line item repor

    Hi how i can post PS commitment line items and cost center and orders commitment line items The SAP standard reports are: CJI5 PS Commitment Line items KSB2 Cost Centre Commitment Line Items KOB1 Orders Actual Line Items KOB2 Orders Commitment Line I

  • Delivery Confirmation date calculation

    Dear All, In the sales order the delivery confirmation date is achieved after running the Availability check. In our case lead time calculation for TAB item category is from Planned delivery time in Material master or Purchase info record+GR processi

  • Solaris does not see second cpu

    I have put together the following system: Asus A7M266-D mobo 2 - Athlon MP 1.6+ cpus 2 - 512 MB DDR PC2100 Maxtor 60 gb hd Matrox G450 agp video mpstat shows only cpu 0. Any thoughts on how to get both cpus running? Allen