Assign Source of Supply to External Catalogue Vendors

Hi there,
we're running on EBP 3.5, replicated catalogue Vendors in the structure, assigned the BP and Purch Org in customizing, created contracts with relevant Mat Group, but when the system returns to EBP from the website doesn't assign the cart automatically to the vendor.
Might that be because there's more contracts with diff mat groups per single vendor?
Thanks very much for your help,
Enrico

If the purchasing requisition is assigned to a contract as source of supply, then you can see it in ME5A transaction before and after the PR was converted to a PO.
And you can see it in all purchasing list reports such as ME2N, in the schedule view, here you have even PO number, contract number and requisition number in one view.
Technically  the table for requisition is EBAN which has a contract number field.
however this is only good before the PR got converted to a PO, as it is possible to create several POs from one requisition, you better get the PO-PR reference from EKET table, and the PO-contract reference from the EKPO table

Similar Messages

  • Proposed vs. assigned source of supply

    Hello Experts,
    I have the following scenario:
    We are using SRM 5.0, extended classic scenario and have a requirement in which a material without an SAP number is selected from a catalog (something similar to a 3rd party catalog).
    However, each material in this catalog have all the information needed such as price, vendor, description, etc.
    However, when this is sent to the shopping cart, the vendor is assigned as a proposed source of supply, instead of an assigned source of supply. Because of this, this requirement is sent to the Sourcing Cockpit, which we don't want to to, since all information needed is already there, and is should automatically create a Purchase Order.
    Is it possible to do this?
    If so, which BADI's should we use?
    Regards,
    Gilberto Gallardo

    Hi
    Using BBPDOC_CHANGE_BADI, we have done this several times._
    Also, we can go for BBPCATALOG_TRANSFER BADI..._
    Please go through the links below for more details ->
    Re: Automatic PO with preferred vendor
    Re: Convert preferred vendor to fixed vendor
    Missing Name in BBP_PD_SC_GETDETAIL
    Re: I cannot access "Supplier Catalogue no" in BBP_DOC_CHANGE_BADI
    Re: partner functions  for vendor master in SRM
    Re: Partner functions OA and IP missing for Vendor in Extended classic PO
    How to select Vendor information as per the line item of the shopping cart
    Hope this will defiinitely help. Do let me know.
    Regards
    -Atul

  • Assign Source of Supply for Services

    Hi,
    I understand that Materials has source list and the system can actually suggest possible vendors for the material via t-code ME25.
    However, I am now dealing with services with service master defined and service conditions maintained. I can create PR via ME51 and assign source of supply but I can't do this for PO via ME25 as that is catered for materials only (even if I entered item category D, it shows as a material PO).
    My question is, is there any default SAP transactions that allow me to create a service PO with the Assign source supply function? If no, what kind of enhancements can I look into to achieve this?
    Thanks!

    Hi,
    In a normal PO there is no auto assignment of sources so I am not sure why you think that there might be for a services PO?
    Remember that to create a PO, you have to specify the vendor first, so how can it assign a source automatically if you have to manually enter the source before you can do anything?
    If you are creating a PO with reference to a requisition or contract, again there is no auto source allocation because the source is being taken from the requisition.
    So you need to try to allocate the source to the requistion and not the PO
    Steve B

  • Assign Source of Supply User Exit with Quota Arrangements in ME57 and ME56

    Hi there,
    We are using Quota Arrangements to define Vendor rebate levels and we have enabled User Exit EXIT_SAPLMEQR_001 to provide a more informative popup to replace standard Source of Supply popup as need to display current allocation quantities and % allocation fulfiled.
    This User Exit is invoked during Assign Source of Supply during PReq processing (More precisely during Assign Source of Supply in ME51n and Automatic Source of Supply in ME57 and ME56) which all works fine.
    When used in ME51n and Source of Supply Assigned and PReq saved, the allocated quantity against the valid Quota Arrangement (EQUK-QUMNG) is successfully updated with the relevant amount
    When using ME56 or ME57 to Automatically Assign source of Supply via the PReq list, the User Exit is invoked correctly and on selecting Vendor and saving the PReq is update correctly, however the allocated quantity against the valid Quota Arrangement (EQUK-QUMNG) is NOT updated with the relevant amount
    I have searched SAP Notes and debuged with limited success but cannot find evidence as to why this difference is happening - I assume that it has something to do with User Exit but any advice gratefully received if anyone else has experienced this issue?
    Ben

    Hello Jerry,
    source will be determine based on the following points:
    Outline Agreement
    Info record
    Quota Arrangement
    Source List
    For more information, <a href="http://help.sap.com/saphelp_47x200/helpdata/en/75/ee11b255c811d189900000e8322d00/content.htm">Click here</a>
    Hope this helps.
    Regards
    Arif Mansuri

  • Assign source of supply in PR from SO

    I have a PR that automatically created from SO.
    I have already created outline agreement for each material in PO and created source list (with fix indicator) too.
    But when I click "Assign source of supply" button in PR, system ask me to choose between outline agreement and info record.
    If I create PR manually with the same materials, the outline agreement will be assigned immediately after I click "Assign source of supply" button.
    Is there any master data or config that make these PRs act differently?
    Thanks for your help.
    Duangsamorn.

    Hi Duang,
    When you create the PR manually , guess that you are not selcting the source list check box ( tick
    in the ME51N screen ),hope this should be the reason for the difference in behavior.
    Please select the tick box when you create PR in ME51N, then the manual PR also will not auto select
    the Vendor. Please test & confirm the behavior after check box selected.

  • Assign source of supply

    dears
    i have made PR in a client and when i click "assign source of supply" it gives me 3 vendors where only one of them in the source list while the 2 other vendor is not in the source list but have info record
    when i make PR with the same material in the other client which have the same source list with the same material i found that i give me only the vendor in the source list although it have info record with other vendor

    Hi,
    Please check have you created PO against these vendors in that client
    If no those will not be proposed
    BR
    Diwakar
    reward if useful

  • Assign Source of Supply at Header Level of SC for single Supplier

    Hi Team,
    We are in SRM7.0 and EHP4.
    The requirement is : User is creating a SC for 50 line items to a single supplier. In SRM7.0 User not able to find the Button Assign Source of supply at Header Level. I know it is at item level and it is very painful from user point of you going to individual line item details and assiging the same Source of Supply 50 Times.
    The design is Once Source of supply assigned. It leads to Auto PO after SC status changes to approved.
    Please tell is there is a standard SRM7.0 Functionality to handle this requirement with out any BADI / Enahancement.
    If not above, please tell how to enhace the same.
    Thanks
    Giri

    Hi Masa,
    As I Mentioned in my Initial thread. We are using Auto PO. Once the Shopping cart under go 2 step Approval Process. Once the status is completly approved, Auto PO is created.
    Pre negotiated vendors for product commedities are available for the SC requestor to select and the list of supplier to Product commedities is available to requestor.
    Request Process (SC) is mainly used from approval point and from analytics (reports) point.
    1 st step approval - Finacial Approvers approve the SC.
    2ns Step Approval - Buyer check the Price in SC as per Vendor Negotiated rate and Approves and Approved staus SC result in Auto PO to Vendor.
    Business do not want change the above process and it is configured as per business and delivered. Only difficulty they are faceing is when creating SC for Same vendor with multiple line items. They need to go Individual Item details and assign the source of supply. It is pain full for them. If the SC is created for multiple line items to same vendor. They want to assign the vendor at header level of SC, Instead of going to Individual item and assign the vendor in SRM 7.0
    Thanks
    Giri
    Thanks
    Giri

  • Assign Source of Supply - Inforecord

    Hello guys!
    Do you know if can be possible to assign a source of supply at a Purchase Requisition but where the inforecord isn´t brought too?
    Is there any IMG activity where i can customize this?
    Now, if an inforecord exists for a certain vendor-material and i press "Assign Source of Supply" button, this inforecord is always showed.
    Thank you very much for your help.
    Regards,
    cecil

    Hello,
    Please maintain source list .
    You define source list requirements at plant level. If a source list requirement exists, you must maintain the source list for each material before you can order it.
    The source list serves:
    To define a source of supply as "fixed". Such sources count as preferred sources over a certain period of time. For example, the fixed vendor XXXX for material 100XX is ASA Company for the first quarter and BSB Co. for the second quarter of the year.
    Select the plants for which you wish to specify a source list requirement
    You use the source list to determine the valid source of supply at a certain point in time.
    The source list contains all the sources of supply defined for a material and the periods during which procurement from these sources is possible
    Following T/Code activities in Material Management module.
    Maintain source list  -  ME01
    Display source list  -  ME03
    Display changes to source list -  ME04
    Analyze source list  -  ME06
    Reorganize source list  -  ME07
    Generate source list  -  ME05
    Display source list for material-  ME0M
    you make the system settings that are necessary for purchasing operations carried out using source lists.
    Source list requirement for materials, It may be necessary to include possible vendors of a material in the source list before the material can be ordered.
    The Source list requirement field in the purchasing data of the material master record indicates whether a source list requirement exists for a material.
    You can define the Source list requirement at plant level in IMG.  Logistics -->Materials management --> Purchasing --> Source list.
    Here you can see the plants for which a source list requirement exists.
    Reward if useful
    Kedar Kulkarni

  • Validate (check) after PReq assign source of supply with ME57

    Hi,
      I want to know if it is possible to control or check the PReq after assign source of supply with ME57. My explanation, I have a release strategy on the u201CSource of supplyu201D if it is null. When I create a PReq with the MRP by default the release strategy appear because there is no Source of supply. If I go with ME52N and put a Source of supply my release strategy disappear but if I use ME57 to assign the release stay there until I use the transaction ME52N to control(check) it. Do you know if it possible to force the control(check) with ME57?
    Regards.

    Hi Duang,
    When you create the PR manually , guess that you are not selcting the source list check box ( tick
    in the ME51N screen ),hope this should be the reason for the difference in behavior.
    Please select the tick box when you create PR in ME51N, then the manual PR also will not auto select
    the Vendor. Please test & confirm the behavior after check box selected.

  • Requisition  - Assigned Source of Supply field

    Hello,
    Please could someone advise how the Requisition Assigned Source of Supply field (EBAN-ZUGBA) gets populated. I am particularly interested in how it would get populated in a MRP created requisition.
    Thank you,
    Kind Regards,
    Jackie Jones

    Hi,
    I have just tried this in our system and found some that did not have the flag set (I checked for MRP generated requisitions where the Assigned was equal to spaces and the fixed vendor flag was NOT equal to spaces)
    There were not many but I was suprised to find even one.
    It might be better to change the code used in the workflow to check for the presence of a fixed vendor or agreement instead of relying on this flag.
    I will have a look to see if I can see why it is not set sometimes and I will let you know if I find anything.
    Steve B

  • Assign Source of supply is not working for contract with material group

    Dear Experts,
    I have searched all the threads and gone through before posting my query. So i would ask moderators to go through the thread properly before rejecting this.
    We have value contracts with respect to a particular material group without material and with item category W in the contract item, Please note that for the materials with this material group, the source determination is not set and source list is also not maintained.
    When we create PR for the material with this contract, and when we click on assign source of supply contracts used to get popped up, but recently from few days, when we click on assign source of supply we are getting an error " no source found for this item ".
    Can anybody help on this.
    Regards

    @ Biju,
    As mentioned earlier, we are not creating PR with reference to contract.
    first we are creating contract with item category W (material group), without material and plant details.
    we create PR with or without material with account assignment K and with the material group in the transaction ME51N, and after inputting all the fields, we click on assign source of supply, it was proposing the existing contracts with respect to material group earlier, but it is not happening for particular material group(it is working for all other material groups)
    Hope it is clear.
    @ Dev Patra,
    we are using DIEN-Service material types and we assign that particular material group to only service material type.
    we have not ticked, source list in the material master, we donot have any source list for the materials under that material group.( please check the note 457110- question number 14.)
    Regards

  • No Requisition Found in Assign sources of Supply,  under central function

    Steps followed:
    1) PR is created in ECC prod 1000000262
    2) Through SRM after selecting the PR we selected Collective Processing
    and then transfered to sourcing cockpit. We got the green message
    transfered to sourcing.
    3) We tried to access the same PR in Assign Source of supply in central
    function. But we could not access the the PR. The message is "No
    requisition found; verify your entries ".
    Any clue or solution to this Issue. ??
    Thanks in advance
    SK

    Hi Manjunath,
    In BBP_PD SC is created
    In SXMB_MONI in SRM, ECC and PI/XI system everything looks ok
    I am a SRM Tech Consultant Did not understand from NOTE  1263876.
    When I go for "Assign Sources of Supply" under Central function
    I do not get any result...I get message
    "No requisition found; verify your entries "
    Thanks
    SK

  • PR - unable to assign source of supply

    Hi,
    I have created purchase requisition and tried to assign source at "Source of supply" tab at item detailed section. But it's already graded (display only) out.
    I have checked the "Screen Layout at Document Level" also. It was in optional mode only.
    How can i make it as optional entry.
    Could you pls guide me.
    Thanks
    Anilkumar Dalai

    Hi,
    What i can understand is that you have created a purchase requisition and now you want to assign a source for the item through auto source determination in PR change transaction(ME52n) by clicking on the assign source of supply tab in the item details in source of supply tab page.
    If its so Pl. check in the check box " source Determination" at the top next to the PR No. and then try.
    Regards,
    Prithviraj

  • SRM 7 automatically assign source of supply in SOCO

    Hi guru,
    I'm working with SRM 7.0 extended classic scenario and i have to transfer external requirements from backend SAP into SRM Sourcing Cockpit. In the SOCO I have to determine automatically the source of supply and the price.
    I read that in the SOCo the sources relevant are:
    1. contract
    2. interlinkage
    3. vendor list ( there isn't information of price)
    Could you please explain me how it works this functionality, and the priority in the determination of supply and price?
    Have you documentation about ?
    Thank in advance
    L.

    Hello,
    If there is only one source of supply available (it does not matter if it is contract or info record), system will assign it automatically.
    If there is more than one, you can press "proposed sources of supply" button and SRM will show all available sources of supply.
    Price will be taken from sources of supply in any case.
    Regards,
    Ricardo

  • Assign source of supply - NOT WORKING

    Hi all,
    I am trying to create a purchase requistion and the source is not coming automaticaly in source of supply tab. I have a info record, contract and vendor master. In me01, i maintained the vendor and material number (without info record) in one line and in other line, i had given the the contract.
    Now when icreate the req, i am not getting the inforecord details or anything in source of supply. please advice.
    Sylvia

    Chid,
    Thanks for your reply.
    1) In SPRO check whether source list is activated for Plant
    *yes its been maintained properly.
    2) In Material master check in Purchasing view have have selected the check box Source of list for the Material.
    yes its been maintained properly.
    3) Have you maintained the Source of supply(Vendors) in ME01 for Material number, Plant & Vendor combination
    I have a question here. I have an info record and also i have a contract. Do i need to have both in sourcelist. Which one can i make fixed.
    4) Check whether the validity period for the vendor in the source list in ME03/ME02
    *yes its valid.
    5) Check whether have you created the Info record for Plant,Material, & Vendor with Purchase organization.
    *yes its been maintained properly.
    Now the question is
    a) I want the source list to populate automatically, when i hit the check button in purchase requistion.. But I am not getting the inforecord details and also nothing in source of supply. Any suggestions of how to populate the source automatically?
    Am i missing something?
    Sylvia
    rgds
    Chidanand
    Edited by: Sylvia Hernandez on May 9, 2008 3:24 AM

Maybe you are looking for

  • Server Threw Exception when Exporting the report as PDF

    Hi , I am developing a .Net application , In my application referring to the .rep file which is created using the Business Objects Desktop Intelligence as below   objBO = new busobj.Application();                     objBO.Logon(strUserName, strPassw

  • Why does my new PSE12 crash after about 1 minute?

    I used PSE8 for several years successfully, on a desktop running WinXP. Always reliable, if a little slow backing up etc with my huge (75K images) catalog. My brand new desktop now runs Win7, 64 bit. It is a high-spec machine. I bought PSE12 and conv

  • SSO for Enterprise Portal 6 with different Portal and R/3 userIDs

    Hi there, We are using SNC library for SAP GUI logon to R/3 and SPNEGO for Web access to EP. What works for us currently is: SSO from Windows logon to Portal using SPNego (LDAP as our datasource with AD) However once we are inside the portal, the SSO

  • How to display group data only when the particular group is clicked

    Hi frnds, I want to design my report as follows: Data is grouped by country, and for each country it is showing details for that country. I need to find out a way to display all group names first.  E.g. Argentina Aruba Australia And on click of parti

  • How to set this filters with 'or' relationship

    Hi Pros,       I have a query as follows, rows and columns are all in structures.                                                    regular_employees              active_employees              lay_off_employees      I want to set up filter as ' empl