Hi, Please advise how to assign mic to the newly inserted operation of the prod order?i mean say 3 operations copied form master data. we added a 4th operation manully. i want to assign new inspection characterstics to the 4th opration. plese advse.

Dear Raju
1) Go to CA02
2) go to header
3) Maintain inspection Point as 150
4) Maintain partial Lot Assign as partial lot assignment according to plant default
5) At Operation level maintain a QM work center ( testing ) with Control key QM04 ( as per your requirement)
6) double click on the control key and go to Quality Management : Inspection points
7) Maintain Inspection point completion : Quantity , Valuation and confirmation ( as per your need , you can select other options also) press F1 and see the impact of each
8) choose time related and keep Tfac 1 and Unit as HR ( As needed)
9) You can select quantity - related also and then maintain the quantity.
10) Select the QM operation and maintain in the MIC
Regards
Gajesh

Similar Messages

  • How to get a list of production orders for a work center?

    Hello SDN Community, 
    I have an requirement to display in a pop-up window a list of production orders for a work center.
    Does anyone know which screens/transactions would show this relationship?
    Or better yet, does anyone know how to demonstrate this from the tables themselves?
    Thank you,
    Dean Atteberry.

    Hello Mangalraj.S
    >>Goto COOIS-->For the field List select PPIOO000 - operations and layout -->standard layout
    >>and execute,by this you will be able to see the operations for each order and to which
    >>work center they are assigned.
    The system I am working on is ECC 6.0.
    For this system the values in the dropdown for the "List" field are "Capacities, Items, Order Headers, Sequences, Trigger Points, etc".  But nothing that says PPIOO000 - operations and layout.
    >>Or else in the in input screen of COOIS,enter the work center for which you want to see which
    >>are the production order's assigned and execute.
    For system I am working in, I do get a grid display when entering a work center.  It has columns like "Order, Material, Icon, Order Type, MRP cntrlr, etc."   But no column with Work Center.
    Any further insight into how to use this transaction to display a list of production orders for a work center would be greatly appreciated.
    Thank you,
    Dean Atteberry.

  • Single production order for many materials

    Dear Experts,
    We can create a single purchase order for many materials. Like wise can we create a single production order  for many materials which is produced from single raw material in same operation?
    Thnaks,
    Chetan

    Chetan,
    You can not create a single production order for multiple materials.
    However, the workaround would be create one material as BOM header and and assign the remaining materials (for which you want to have production order) as BOM components with by-product or co-product. With this you can receive all the materials against one single production order.
    This will have implication in many areas like planning and costing.
    Evaluate the option with your FICO consultant also, before going ahead.
    Regards,
    Himanshu

  • Goods Issue To Each Operation Of Production Order?

    As we know, in SAP ,when we create and realse the production order,we could posts good issue to the production order ,using MB1A. And in SAP , the components can be assigned to the operations of the finished product.
    But in our company, the production order will take long time,and during production,different materials will be used in different phase of the production order,that means different components will be used for different operations.
    And for some reason,we don't want our material to be backflushed during production.
    So I want to ask can we post goods issue to each operation of the production order,not to the whole production order? Can SAP support Post Goods Issue To Each Operation Of Production Order?
    What shall we do if we want do this?By ABAP development ? Or there is third party software
    can do this with SAP? 
    Thanks for any reply!
    Edited by: Fei Liu on Mar 14, 2009 4:56 PM

    Hi Fei,
    As explained above, i think the concept of releasing the individual operations instead of releasing the order at header level would work fine for your requirement.
    Steps:
    1. Go to operation page in co02.
    2. Select the first operation, at the bottom of the screen you would find a Green Flag, click on the same.
    3. You will now find that the status of the first operation has changed to REL, while the others are still not.
    4. At header level you will find a status PREL, indicating partial release.
    5. After completion of the first operation, confirm the same & select the second operation & click release, & the process follows in this manner
    6. Please do not click the green flag at the header level as this will release the entire order.
    Pre-requisite:
    1. You have assigned components to the respective operations.
    You might also want to consider the usage of trigger points. This you can assign to each operation, where-in if the status changes to CNF, you trigger the release of the following operation. But before opting for this flow, first do it manually to ensure it meets your need.
    Also if the components assigned to the same operation, needs to be issued at different date, then you can use the lead time offset in BOM. In cs02, go to item details, here you can specify the same. Eg: If your operation stats on 15th March & you want this component to be issue only on 17th March, then specify the offset as 2. But if you want the components to be issued 2 days in advance of 15th march, then specify as 2-.
    Hope the above helps.
    Regards,
    Vivek

  • Production order for a multiple materials codes...

    Dear...
    Could you please suggest me the SAP solution for the below production strategy.
    This production process is of heat treatment. Actually I am doing heat treatment of Cast and Forge items. These items weights are in the range of 150 kgs to 40000kgs. For example I am having a 40 tons heat treatment furnace. So at a time I can load the materials upto 40 tons. I am having different materials of different sizes and chemical compositions.  But heat treatment cycle(Routing) is same. So I can load different types of materials i.e. upto 40tons for the heat treatment for which same type of heat treatment is required. Sometimes this may be a single item .. if the weight of the items is 40 tons. If it is single item...then there is no problem. If I am loading different items...and if execution process is same for all the items, then how can I map this in the SAP. So that I can create a single order for different Items of different materials and quantity. I need to do the confirmation of these items with respect to the same item. Please suggest me...how can we map this scenario into the SAP.
    Thanks in advance.
    Regards,
    Surya.

    Hi surya,
    As per the heat treatment process concern, total cycle time is constant, and load is also constant (if we havenot changed).
    i hope u have defined workcenter formula and routing accordingly.
    i think creating single production order for multiple material is not possible, instead of thsi, i would suggest one way,
    > Since u have to maintain stock for Heatreated items, create sepearte Material code for each item to be heatreated.
    > Create BOM ,Routing  for New Material code.
    > Acitvate Batch management for New Material Code has been created.
    >Now create Production order for each material to be processed in one cycle, Assign the Batch Number manually.Batch number repersents your Heat treatment cycle number and same can de used for traceability.
    >Confirm the each order seperately, Now the Heatrement process cost will be updated and stock will be posted to heatreated storage loaction.
    But i am worrying about capacity planning and scheduling, For my knowlegde purpose i would like to know your existing scenoria, like workcenter formula and  routing operation values has been assigned , if u wish plz share with us.
    Please come back with your ideas..
    regards
    Pradeep

  • Production Order for a material without BOM and Routing

    Is it possible to create a production order for a given material without routing and BOM, I know we can
    create a production order for a material without a BOM (with a default routing) just wanted to check with
    the above criteria
    Thanks in Advance!!

    Members:
    Thank you for your valuable replies and time
    Santosh:
    Tried what you have mentioned, but system still picks up a default routing
    Kaushik:
    Maintained Default values in OPJG for the given order type, but system still picks up
    default routing
    Mangalraj:
    have no issue in creating a production order without a BOM, but I am trying to see
    is there a way where I can create a production order without a BOM and routing (not
    even default operation )
    Any suggestions on how to create a production order for a material without a BOM
    and routing (not even default one )

  • Error while converting planned order to production order for config materia

    Hi experts,
    While converting a planned order to production order for a configurable material.I am getting the following error meassage. Message No.CO684,
    "You cannot make an assignment to make-to-order stock"
    ( DiagnosisThe component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
    A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant.
    System ResponseThe following responses are possible:
    Order processing is cancelled.
    The system resets the special stock indicator back to the original value.
    Procedure
    Choose another order type).
    I have checked some of the threads related to this error. But no where there is any solution.Please tell me if there is any settings to make so as to work on this scenario.
    Thanks,
    Sham

    Hi,
    This will be a MTO scenario. Please check your requirement type,Requirement class and strategy type config along with your Item category and schedule line category from SD.
    Also check your Production order type config and settlement profiles.
    I mean to say that you need new production order type to be configured for specific above mentioned combination.
    Are you working on a production system..?? is it the first time you are creating the order for this config material..??
    Regards,

  • Creation of Production order for FInished Product through Project

    Hi,
    Pls clear me on how we can create a Production Order for finished product.  
    If we confirm the production orders in PP, cant the same be confirmed in PS.. Should we consider the same activity types in both PS and PP
    Pls clarify

    hi srikanth,
    your answer has been very helpful... but could u clarify  why MRP is run in MD51 for WBS element and in MD02 for network..
    Pls clarify...  My scenario is like this ...                                                                               
    A
                            B                                                                                C
                    D  E F G H I                                                                                J K L M N O
    I have  a Assemblies B and C which are always delivered in sets.. under assemblies B and C,  we have 6 sub assemblies which has its own components.  I am assigning sub assemblies to differenet WBS elements 01 and 02. so, initially these sub-assemblies are produced to stock. this should happen in PP i.e., through production orders generated in MRP run ( MD51 ). In the next phase i will assign Assemblies B and C to another WBS element.  Again system should generate two Production orders thru MRP for this. Here the 6 sub-assemblies produced earlier will be consumed in confirmation of the production order...
    What i am doing is this correct...
    and the procurement for the components is happening thru the purchase requisition generated via MRP. the components themselves are not directly assigned to the project..
    Pls advise and clarify?

  • How do we Prevent Creation of Production Orders for Phantom materials.

    Dear Experts;
    We have some materials which are Phantoms.
    We have set "special procurement type" as 50 in MRP2 and "Strategy Group" as 59 in MRP3
    These are non stchable items, but have BOMS.
    We dont create orders for them, however at the mement the system allows order creation. How do we prevent creation of production orders for these items in the system.
    Thanks in Advance
    Richard.

    Dear Richard,
    Check using this BADI - WORKORDER_UPDATE using method IN_UPDATE or Release by including a check if MATNR and for
    WERKS combination if SOBSL = 50 from table MARC,then do not allow to save.
    Check whether this works or else you have to set a plant specific status using OMS4  for not allowing production order
    creation and assign this value in the material master of the phantom assemblies.
    Check and revert
    Regards
    Mangalraj.S

  • Error in GR for a Production Order for a particular material....Unique case

    Hi Dear Gurus,
    I am facing the following problem:
    There is a production order for a material (say X, matrl type FERT) of order qty 21EA. First we did GR of qty 9EA. but when we are going to do GR for the rest of the qty i.e.12EA it is not happening system showing Error message " Account XXXXX requires an assignment to a CO object".
    But while we are going to do GR for the rest 12Ea qty in two parts i.e. first by doing GR of 11EA then 1EA system is accepting.
    Interestingly if do the GR for the same order as first by 8EA and then the rest 13EA that is also accepting.
    Eventhough, for any other material (of same type and group) if we make a production order of the same 21EA and then doing GR firstly by 9Ea and then 12EA that is also getting posted properly.
    What would be the reason for the error message for that particular case?
    Here the system is SAP4.5B version, material MRP type is M0, lot size  FX & fixed lot size 10Ea, safety stock 8EA, Reorder point 15.
    Thanks in advance for your inputs.
    Regards,
    Arghya

    REfer this link..
    [https://forums.sdn.sap.com/click.jspa?searchID=25161817&messageID=7040673]
    [https://forums.sdn.sap.com/click.jspa?searchID=25161817&messageID=7159723]
    hope the above helps..
    karthick

  • Operation on production order - what is the object (BOR) to manage it ?

    Hello,
    I have to call a workflow when an operation on production order is confirmed, or partially confirmed, or deleted.
    What is the business object to use to manage it ??
    Tks,
    Roberto.

    Hello Uma,
    yes, right...
    yesterday, I was not able to see the trace when I deleting a production order becuase the object BUS2005 was not
    active on customizing:
    after I found it
    No business object triggered for production order creation
    end now is showed...
    SO, we have to use BSVW ... and so the consequences is : How to know what is the object BOR to activate !??!?!
    tks

  • Release a production  order for partial quantity

    Hi gurus,
    Can you please tell me how can i release a production  order for partial quantity without splitting the order?
    Regards
    Rajib Pathak

    Dear,
    Best way you can conver the planned order to production oreder in partial in CO40.
    Or from MD04 screen click the planned order, choose pratial release and enter the quantity you want to release and press Generate button. the order gets converted to production orders of yr specified quantity and rest planned order remains for further processing.
    Or,
    Create order
    Goto operation overview
    Select the operation and click on release button...which will release the opration alone instead of releasing the order. If you release the order, then all the eperatios are released onec for all.
    If you go for operation release...you can release operation by operation, which will be partial release of order at header level.
    at operation level - partial release
    Hope it will help you.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Nov 12, 2008 9:44 AM

  • Creating a Production Order for a MRP area

    Hi All
    I have activated MRP area and has created 2 MRP area's.  When I create a production order, always the first MRP area is assigned in the production Order.
    Please help me to understand how do we create a Production order for a particular MRP area.
    Thanks
    Tom

    Sorry guys, the question was not correct.

  • Costing the production order for the configured material

    We are trying to cost the production order for a configurable item.  But the system is not calculating any cost in the production order.  Sales order related to this configurable material is costed.  What additional setting I need to cost the production order for the configured material ?

    Hi Niki
    If your SO is costed, thats enough from a System's perspective... Planned cost will be the sales order cost estimate because SO saves the Chars required for the Configurable material
    Planned cost in Prod order depends on the Costing variant you have assigned in the order type... Check the error log if there is any error in cost calculation in prod order
    br, Ajay M

  • Cannot release production order for a plant

    Hi:
    When I try to release a process order , I get this error message:
    "CAnnot release production order for plant".
    I get this message  for a particular material in the plant. For other materials, it's working fine.
    Please give your suggestions!
    Gautham

    Hi,
    Check the Tasklist usage for your routing for that material.
    For this usage ,check in op45 against the task list type whether until release indicator has been enabled.If so remove
    and do the release.
    or
    check whether workcenter which is used for producing the   material has been locked in work center itself.
    Indicator: Usage only until release in orderIndicator used to specify for a task list usage and a task list type that an operation in the order cannot be released.  This occurs when a work center group that is not intended for production is allocated to this operation.
    When this type of operation in the order is released you must enter the work center where production should take place.
    Regards,
    nandha

Maybe you are looking for

  • Movement Type 161error in STO return (Plant to Plant) at the time of goods issue .

    Hi all... Am getting the following error while posting goods issue through VL02N Update control of movement type is incorrect (entry 161 X X _ L) Message no. M7226 Diagnosis The system could not find entry 161 X X _ L in any of the movement type cont

  • Dynamic FLV StreamName using MySQL

    Hi there, I am trying to display a *.flv movie which has its filepath drawn from a php MySQL dataset The recordset works ok and is tested with just a text output of the filename but i cant get the flv player code right.  <param name="FlashVars" value

  • Port Programming Using Netbeans

    Hello everybody, I am working on Serial port communication, and I have used Netbeans for GUI designing. I am able access the port, but failed to set Event for the same. I am getting error like............ D:\NetBeansProjects\MySerialPort\src\readseri

  • Populate Combobox in Excel from SQL Table

    I have a requirement to populate a combobox in excel from a table in SQL when the user opens the excel workbook. Can you help me on how I can do that. I have a supplier column in the table which I like to appear in the combobox and has around 1500 re

  • Components now showing in parsys design

    Hi, I have created a component, allowedParents set to */parsys, set the componentGroup to 'mytest',  In the generated jsp just simply put some texts, then created a dialog structure. But when I get to my page and swtich to the 'design' view, my compo