Assignment of single capacities to a work centre

Dear experts,
I have following problem:
We created capacities which we want to use for capacity planning using CR11.
In the work centre maintenance I want to assign these capacities using CR02. -  Capacity header view --> ' go to individual capacities' . Here I want to fill the table 'capacity assignments - individual capacities' . When I put in the capacity code I get the error message CR100 'the capacity exists already'.
I can only create new capacities (using new capacity codes). that doesn't help since we need to assign pool capacities which means these new capacites can not be assigned to the other work centres later on. For my problem it does not matter whether the capacity to be assigned is a pool capacity or not.
What I want to do is exaclty what I found described in SAP documentations, unfortunately without detailed instruktions .
What do I need to do to be able to assign these individual capacities?
thanks in advance
Kurt

Dear,
In Work center i.e CR02 capacity header, click Goto -> Individual Capacites . This will take you to the "Assignment tot the Individual Capacity" screen. Here you give names of the individual capacities and Click "Choose (F2)" , where you can maintain the header details for this individual capacity.
For example:
when You  give individual capacites as '2' ,youI have to go to GOTO field and select there Individual capacities. It asks for capacity and its short text.In capacity field  you can  give person1, person 2 etc and its short text as Ramesh, Kishan (name of operators).
Regards,
Ram,

Similar Messages

  • How to assign work centre in OM

    Hi,
    In organizational structure how to assign work centre.
    it is necessary to assign cost centre to org structure.how ?
    President has to be given personnel no.?
    if employee is reporting to two superiors of different depts or different regions ,how the employee should be placed i.e dual reporting?
    Urgently reply.
    Thks
    Archana

    Hi Archana,
    1. To assign Work Center the T-code is PO01.
    2. Yes. In SAP HR every employee has to be given Personnel Number irrespective of their designations.
    3. No its not possible according to me (Gurus Pls correct me too if I am wrong)
    Hope above answers are helpful to you.
    Regards
    Pavani
    Remainder: Points to be given on answered.

  • HR posistion updated when person assigned to a work centre.

    Hello
    in SAP Plant Maintenance (PM), we are assigning persons to work centers.
    Some times a strange thing happen when we assign a person to a work center.
    The position for the person is updated with a wrong value in HR master data.
    We are not given any position in PM, and definitely do not want to update HR master data from PM.
    Anyone experienced something like this?
    Best regards
    Tom Saga

    Hello
    I have now tried to do the same in our test system.  And for the particular user I get an error message when doing this.
    The screen for "Copy Organizational Assigment" pop up.
    And SAP try to fill in the Work centre ID as Position.
    ut with error message:
    Entry in outbound table not found
    Message no. E0400
    Diagnosis
    No partner profile (outbound parameter) could be found using the following key:
    PXCCLNT100/LS//HRMD_A///
    This refers to the key fields in table EDP13:
    RCVPRN  Partner number
    RCVPRT  Partner type
    RCVPFC  Partner function
    MESTYP  Logical message
    MESTYP  Message code
    MESCOD  Message function
    TEST    Test indicator
    Procedure
    Please check the EDI partner profiles.
    We do not understand this.  And it only happend with this user, and with all work centres we try to add him to.
    Best regards
    Tom

  • Assignment of shift sequence to work centre

    I have created a new shift sequence. where can I assign it in the work centre?

    Hi,
    you need to define the grouping key /shift definition /shift sequence in SPRO.
    Assign the grouping key work center capacity tab pageunder capacity header.
    Regards,
    nandha

  • What is Work centre

    Can u let me know what is Cost Centre / Work Centre ?
    What is the difference between production order / process order
    Thanks in advance.

    Hi
    check info given BY sap to clear ur doubt
    Definition
    Operations are carried out at a work center. In the R/3 System work centers are business objects that can represent the following real work centers, for example:
    Machines, machine groups
    Production lines
    Assembly work centers
    Employees, groups of employees
    Use
    Together with bills of material and routings, work centers belong to the most important master data in the R/3 production planning and control system. Work centers are used in task list operations and work orders. Task lists are for example routings, maintenance task lists, inspection plans and standard networks. Work orders are created for production, quality assurance, plant maintenance and for the Project System as networks.
    Data in work centers is used for
    Scheduling
    Operating times and formulas are entered in the work center, so that the duration of an operation can be calculated.
    Costing
    Formulas are entered in the work center, so that the costs of an operation can be calculated. A work center is also assigned to a cost center.
    Capacity planning
    The available capacity and formulas for calculating capacity requirements are entered in the work center.
    Simplifying operation maintenance
    Various default values for operations can be entered in the work center.
    The following graphic illustrates the use of work center data.
    Use of work center data
    Structure
    A work center is created for a plant and is identified by a key. The work center category, which you define in Customizing the work center, determines which data can be maintained in the work center.
    The data is grouped thematically together in screens and screen groups. Examples of such screen or screen groups are:
    Basic Data
    Assignments (to cost centers, Human Resource Management System (HR))
    Capacities
    Scheduling
    Default values
    Hierarchy
    Technical data
    Integration
    Task Lists
    Work centers are assigned to operations in task lists. If you change default values in a work center, the changes are effective in the task list if a reference indicator has been set for the default value.
    Work Center Hierarchies
    Work centers can be arranged in hierarchies. These are important in capacity planning. You use hierarchies to cumulate available capacities and capacity requirements in a hierarchy work center.
    Assignments to Objects in the Human Resource Management System
    A Logistics work center can be assigned to either an organizational unit or a work center in the Human Resource Management System (HRMS). Assignments to other HR-objects, for example employees or qualifications, can be maintained via the HR work center.
    Vishal...

  • Work centre capacity utilization

    Dear guru ,
    i have a work centre that always work in the same moment for 3 different production order.
    If my total daily available capacity is 11 hours for my 1 individual capacity is right that I assign to the work centre a capacity utilization of 300 percent in order to have a daily available capacity of 33 hours and I can use capacity levelling in the best way ?
    Or there is other better solution for solving this problem ?
    Thanks for your help.

    you can also put no. of individual capacity as 3.

  • WORK CENTRE IN EQUIPMENT MASTER DATA

    Hello All,
    In IE01 tcode > creation of equipment , pls tell me what is the relevance of work centre in location tab ??
    Thanks,
    Sunny

    Hi
    Work Center
    Definition:Operations are carried out at a work center. In the R/3 System work centers are business objects that can represent the following real work centers, for example:
    Machines, machine groups
    Production lines
    Assembly work centers
    Employees, groups of employees
    Use
    Together with bills of material and routings, work centers belong to the most important master data in the R/3 production planning and control system. Work centers are used in task list operations and work orders. Task lists are for example routings, maintenance task lists, inspection plans and standard networks. Work orders are created for production, quality assurance, plant maintenance and for the Project System as networks.
    Data in work centers is used for
    Scheduling
    Operating times and formulas are entered in the work center, so that the duration of an operation can be calculated.
    Costing
    Formulas are entered in the work center, so that the costs of an operation can be calculated. A work center is also assigned to a cost center.
    Capacity planning
    The available capacity and formulas for calculating capacity requirements are entered in the work center.
    Simplifying operation maintenance
    Various default values for operations can be entered in the work center.
    Look at CR01 ,CR02,CR03 Transaction
    table : CRHD Table
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • Creating/Copying a Work Centre,also a Production Scheduler and Cost Centre.

    Hi All,
    I am trying to create a new work centre based on the settings of a previous one? First of all,how I can do this?
    Secondly,after I have created the new work centre (having copied being copied from another),I need to create a new production Scheduler and Cost Centre? How I will be able to do so,also?Will the Production Scheduller and Cost Centre assignments fom the old work centre be copied,too,or I will need to create/copy these from scratch?
    All help greatly appreciated,will award points to all useful answers.
    PAPJ1.
    Edited by: PAPJ1 on May 20, 2011 11:01 AM

    Hello,
    You can create a new work center by copying an existing work center. in the cr01 screen in the copy from column put the plant name and Ref. work center name and put enter. all the existing data will be copied to the newly created work center. no need to create new assignment to  Production Scheduller and Cost Center.
    Hope it helps.
    Regards
    Alok

  • How to Create New Activity Type  for Assiged to work centre Costing in Acti

    Dear Sir,
    We have four activity type to assigned in workcentre Costing Activity. Details are as under
    AIRJET     2010     AIRJET
    DONIER     2010     DORNIER
    SULTEX     2010     SULTEX
    SULZER     2010     SULZER
    in addition one more loom is comming in our unit and require new activity type.
    How can i create new.
    Please guide.
    Thanks in advance
    Regards
    Ajit

    Dear ,
    To create new Activity Type  , you need to follow the below steps :
    KA01 - Create Primary Cost Element for the new activities type.
    KL01 - Create Activity Type tied to the primary cost element. 
    KP26 - Change Activity Type/Activity Price Planning - maintain the Variable price
    Assign the activity type to cost center using T code KP26.
    In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the Fiscal Year as 20xx.
    Click on Overview tab on top and key in costing details in this screen.
    After performing this ,while creating the work center ,this combination of activity type & cost center should be assigned.
    At work centre level , you should have
    1.Create Standrad Value Key -OP19 and Formula Key in OP49.
    2.Create Formula Parameters in OP7B or u can use existing one to assing in the Standard Value Key
    3.In CR02-Assing the Standard value key in Basic Data  and select the Formula Key in Costing tab with cost centre assingement .Save
    Try and check
    Regards
    JH

  • Activity type in work centre

    Hi,all,
    I have a requirement as mentioned below-
    I have certain pm work center like engineer,fitters.But under engineer i have 3 different activity type like Sr.engineer time,Asst.engineer time,Jr.engineer time.I have assigned all these 3 activity type in my work centre in cost tab page along with standard formula SAP008.Now , my requirement is when I assign this work center in my equipment or maintenance order ,in operation tab pages of maintenance order ,only these three activity type should flow from where I want to select my relevant activity type.But instead of this,all the activity type around 10 nos whatever defined by CO consultant , is flowing to my order from where i need to select.I want only those 3 activity type which I had defined in my work center.can anybody please explain how to fulfill my requirement.thanks in advance.
    rgds
    rajib

    hi
    you can make the default cost element by creating the external profile in IMG and assigning to the order type ,also in easy access screen during order creation you can mention as default values in the menu Extras>settings>default values
    As per what cost element has to be specified kindly consult with the CO team,regarding the mandatory field may be you have specified the fields as mandatory in IMG settings,kindly check
    regards
    thyagarajan

  • Work Centre in Org Management

    Hi Gurus,
    How to view work centre object A wither in organization & staffing or simple maintenance
    I assigned workcentre to the position through PP01 but couldn't view in either above.
    Sunny

    Hi,
    to view the Workcenter with the orgunit create the evaluation path (OOAW tcode)accordingly.
    then execute the report RHSTRU00 with the eveluation path.
    then you can see the work center..
    Try the std Evaluation path
    A_TASKS

  • Difference in Main work centre and Operation workcentre

    Hello PM Gurus,
    In CS order, we have two work centres. One at header level called as Main work centre and another at operation level.
    Why do we have two work centres. The one at operation level itself should have been enough.
    There is a main work centre at functional location too ( Organisation tab). So what is the connection if we use this functional location as the reference while creating a CS order.
    Please reply soon.
    Cheers
    Sunny

    Hi Sunny,
    The work center at haeder i.e., Main Work Center is the reponsible work center(say a department). It means it takes the reponsibility of the whole job mentioned in that work order(or job given by production dept.). Now, assume , it further distributes the whole work to its own sub-dept or different work centers as per nature of job. Say, electrical related work to elec work centers etc., by ,means of assigning to different operations.
    The Main work center's cost center will be copied as responsible cost center in Additional data TAB of the order.Now thus you see commercially the responsibility of doing the job lies with the responsible cost center (or say Main work center).
    Hope it is clear.
    Regards,
    Rajesh

  • 2 machines in 1 work centre

    Hi Experts,
    In my scenario there are 2 machines in 1 work centre. So when I go to capacity tab then where can I maintain that I have 2 machine capacity? Please answer me ASAP....

    Hi,
    You can maintain two machine as one work center in the Capacities tab enter 001 (Machine capactiy) and enter the system will take to another screen, where you can enter the time ofthe workcenter and capacity utilization and number of individual capacity, there you can enter 2. So the the capacity available will be multiplied by the number of capacity.
    for Ex: you have enter time 08:00:00 to 17:00:00 then for one machine the available capacity is 9 hrs for 2 machines, it will be 18 hrs, the system will calcutate andit will show the capacity as 18 hrs.
    Thanks,
    JK

  • How to measure work centre performance in the pp point and pm pinot of view

    Dear Guru`s,
    how to evaluate the work centre performance in the pp,pm point?
    how to evaluate the OEE (overall equipment efficieny)?
    can anybody suggest that, if there is any transactions are avialable to get the reports or any process is to be followed to evaluate these?.
    regards,

    hi
    you can evaluate the PM work center using t-codes
    CR05 - Work Center List
    CR06 - Cost Center Assignment
    CR07 - Work Center Capacity
    CR08 - Work Center Hierarchy
    with this you can get the requirment,available and overlaod of the capacity
    OEE cannot be directly calculated you can develop the custom based program to calulate the one with available input,( available hrs,down time hrs)
    regards
    thyagarajan

  • Querry regarding work centres

    hi guys
    1. anybody plz explain the concept of standard values that are maintained in workcentres and how they are calculated when work centre is assigned to operations in order.
    2 any doc regarding costing of orders ?
    regards
    pushpa

    hi pushpa
    satandar values are used for calcualtion of time spend for partcular workcenter ,for example if it is machine category you will create standard value which contains setup,machine and labour which contains the formula for calculating the execution times for that particular activity.
    setup-15min
    machine-30
    labour-15min
    then the system will calculat the price based on the planning in KP26
    for PM point it is basically NO STANDARD VALUES,hence you have to specify only the activity type in the costing tab page ,cost center and the formula for calculating the times
    regards
    thyagarajan

Maybe you are looking for

  • SAP Netweaver 7.2 CE Installation

    Hello, I'm trying to install SAP Netweaver 7.2 CE on a Windows 2008 Data Center X64 machine but I'm stuck at "Solution Manager Key" screen. I followed all necessary steps described in notes 805390 and 811923 but I was not able to generate a key. When

  • How to register External table into Oracle APPS?

    hi can we register the External table in Oracle apps like SQL Loader? So if yes, please share the steps. Thx

  • How to change backgournd image with 7941 phones

    Hello, I followed the steps indicated to change the background image on my 7941 phones, but the only image I see when I try to change it on the phone, is the default one. I dont know where to look for answers. I join my list.xml file and the two back

  • LAF and Java Plugin not opening in some machines

    Hi all, I have strange problem in my forms 10g application. We have implemented LAF in our Forms 10g application that requires to use Sun Java Plugin. In formsweb.cfg, the sun java plugin version that would be downloaded is - 1.4.2. For most of my us

  • Creating pop-up bubbles

    I have a word document that is to be filled out as an application by users. I can convert it to a PDF and also have FormsCentral. Basically, there are long strings of acronyms in consecutive order within the document, and I need to create a function