Attribute change run problem - infoobject is not listed in the list

Hi folks,
When I load master data for 0customer, the infoobject 0customer doesnt come in the infoobject list for attribute change run. Also, when I try to activate master data manually it says 'Master Data already active'. and the reality is M version of Data is not active.
Can you guide me.

Try running the program RSDMD_CHECKPRG_ALL for this infoobject. You can select all the options when running this program.
Try running this program multiple times, coz my experience showed that initial run may not always fix this issue.
Good luck!

Similar Messages

  • Attribute change run problem

    Hello Gurus,
    I have deleted all the master data tables(P,S,X,T). Deleted the PSA table entries too.  I am loading data frm R/3.
    No data exists in 0VENDOR ,when i click manage master data.
    When the moment I load data in 0VENDOR_ATTR, without doing Attribute change run(ACR), the data is getting displayed in Maintain master data.
    Please let me know why this happens.
    Thanks,
    Sonu

    Hi
    According to my understanding of your issue, there is no master data in 0VENDOR, i.e., all the Dimension tables along with SID's are deleted.
    But SIDs of the 0VENDOR_ATTR(whcih is the attr of 0VENDOR and also acts as characteristic) exists.
    Sow hen you load data the master data is written into 0VENDOR and hence teh SID's of the attr are not deleted do teh master data will exists for 0VENDOR_ATTR.
    Please let me know incase i got your question wrong.
    Regards, Hyma

  • Attribute change run for Customer

    Hi All,
    I did a delta load of the customer data and got some new and changed records. I remember that we need to do an attribute change run after loading any master data. To do that, I went through the menu path Tools Apply hierarchy/Attribute change run...but couldn't find anything there. Do I need to do anything to get the "Customer" here to do the attribute change run.
    Thanks,
    RPK.

    Hi
    Go to
    Tools-->Apply hierarchy/Attribute change run
    Oncle ur there click execute to start change run,It will staart and finishes the Attribute change run.
    If u want to see the list of objects click on the 'InfoObjectlist' on the Tools-->Apply hierarchy/Attribute change run screen
    Assig point if it is helpful

  • Attribute Change Run aborted with an error :Not all data indexed for index

    Hi,
    I have an issue where the master data Attribute Change Run  aborted with an error pointing to the BWA:
    Attribute Change Run aborted with an error :Not all data indexed for index
    we tried to load only 0 data into it,the error still occured.

    Detail message is following:
    not all data was indexed for index 'GBP_BIC:XYCH_098('0' for '114')
    creation of The BIA INDEX for infocube 'YBC_SD015' terminated while filling

  • Attribute change run Failing in Process Chain

    Hi guys,
    Every day my process chains is failing due to Attribute change run and I am maually running attribute change run.
    And one more thing when the attr. change run is triggered automatically,then it is generating 2 change counters in RSATTR tcode instead of 1.
    One is successfully completes and one is still in schedule.After 2days days it is showing like completed change count id.
    Please help me.
    Regards,
    Tiragati.

    Hi,
    As you said Attribute change run step is failing every day.
    can you post the error message. is it failing because of Lock issue or some other issue.
    Mostly attribute change runs fails with lock issues. if its the same problem in your case. make sure that no master data objects runs at the time attribute change run runs.
    Try to put some delay in the process of the Attribute change run so that it will not get failed.
    Check if its the same ACR scheduled or diff objects?
    Regards
    KP

  • Can we apply attribute change run for datatarget (Master data )

    hi,
    can we apply attribute change run for datatarget like masterdata where for example i am loading 0pm_order_attr to 0pm_order data target (master data). after successful loading of data, do i have to apply attribute change run for <i>info object</i> 0pm_order or apply attribute change run for 0pm_order in <i>info providers</i> because after successful loading of pm order data, i am trying to load transactional data and it is showing error "No SID value found for xxx record"
    pls advice how not to make the error repeat even after successful loading of master data.
    Thanks in advance, quick responce is greatly appreciated.

    Hi all,
    i am in production server and cannot activate the master data 0pm_order which is in info providers directly, is there any chance of activating it with any other option.
    coming to attribute change run, i understand that we can apply for master data objects which are there in info providers, am i correct?
    i ran attribute change run yesterday for the info object 0pm_order but even after doing that i tried to load transactional data but it was failure with the same error "No SID value found", why i am getting when i found master data loading successful and ran attribute change run for infoobject.

  • Process chain hangs when reaching AND process before Attribute Change Run

    Hi Experts,
    I have the following problem. For some reason my master data attribute process chain hangs when it reaches the AND process variant right before the Attribute Change Run. It does not go anywhere from that point.
    Thank you

    hi AG,
    if this is hanging daily at the same place without proceeding further, and with out giving the instance for the same. then the better way is to replace that AND process in the chain with the new AND process. and then check and activate ur chain. this wil solve ur problem.
    if this is the first time that happend to u, then check the previous load status, if any of the load has failed and u didnt turned the status of the process then also this can happen. So please do check it and act accordingly. If u cannt find the resolution then please run ur changerun manually.
    u can use RSPC_PRCESS_FINISH FM to convert the status of any process. for this u need to give instance and variant details. and then if u execute, then chain will continue further.
    Hope this will help you.
    thanks
    Vishnu

  • Attribute Change Run in Process Chain failed with SQL 942 error

    Hi,
    Attribute change run in th eprocess chain failed with the message " SQL Error 942" and ran succesfully after repeating the step.Searched in Forums for similar error but the solutions were not apt.
    Any pointers would be of great help!!
    Thanks in advance,
    Bhagyarekha.

    Hi Bhagyarekha,
    The reason behind that error could be:
    An attempt is made to activate a characteristic whose compounding was replaced and whose navigation attributes were simultaneously deleted. The replacement of the compounding temporarily deletes the M view of the characteristic during internal activation. The process of deleting navigation attributes involves converting the attribute SID tables. However, the M-view of the characteristic, which has just been deleted, is needed for this conversion.
    Check this SAP Note:
    Note 684405 - Replacing the compounding and deleting navigation attr.
    Hope it helps.
    Veerendra.

  • How to make Attribute Change run alignment & Hierarchy changes in Aggregat

    Hello
    I want to understand that How to make Attribute Change run alignment & Hierarchy changes in Aggregate?
    I posted previously the same question but there were not good answers and i was not able to understand clearly .....
    If there is Process chain XXY which makes Attribute change run for Master Data 0SPELLING ?
    Now there is Aggregate TRT which includes :
    0SPELLING , Fiscal Period , Purchase Product, Purchase Category ?
    Now pls answer following question ?
    1) Does the Process Chain XXY which makes only attribute change run alignment for 0SPELLING , Will this process chain automatically do the Change run alignment for 0SPELLING in Aggregate TRT ? YES or NO
    2) If Yes, then we are just suppose to do Roll up for Aggregate TRT after Process chian XXY completes and finish job ?
    3) If No, then what steps are suppose to be DONE so as to make sure that Aggregate TRT has new values and perfect values for 0SPELLING ?
    Please answer and coorect if i have any wrong question....

    for e.g.
    u have 0spelling whicha has attributes x,y and z on day 1 with 10 records
    so do ur aggregates on day1 with same values
    now on day2 u had new values of attributes y,z,s,d and new hierarchies and so u add new records
    with data load u will load the data with version M of modified and is not available for reporting
    If u do attribute change run then this modified version is activated to A i.e. active version .
    It will also do the change run alignment for Aggregate for new attribute values and new hierarchy values for aggregate.
    now in order for this data to be available for reporting u will need to do the roll up of aggregate.....
    if u roll up aggregate before attribute change run , new data is not avaialable for reporting
    if u roll up aggregate after attribute change run, then data is available for reporting
    if u dont roll up aggregate eventhough new data is in dataprovider, still new data will not be available for reporting.
    this is how it works

  • How to make Attribute Change run alignment & Hierarchy changes in Aggregate

    Hello
    I want to understand that How to make Attribute Change run alignment & Hierarchy changes in Aggregate?
    I posted previously the same question but there were not good answers and i was not able to understand clearly .....
    If there is Process chain XXY which makes Attribute change run for Master Data   0SPELLING ?
    Now there is Aggregate TRT which includes :
    0SPELLING , Fiscal Period , Purchase Product, Purchase Category ?
    Now pls answer following question ?
    1) Does the Process Chain XXY which makes only attribute change run alignment for 0SPELLING ,   Will this process chain automatically do the Change run alignment for 0SPELLING in Aggregate TRT ?         YES or NO
    2)  If Yes, then we are just suppose to do Roll up for Aggregate TRT after Process chian XXY  completes and finish job ?
    3) If No, then what steps are suppose to be DONE so as to make sure that  Aggregate TRT has new values and perfect values for  0SPELLING ?
    Please answer and coorect if i have any wrong question....

    for e.g.
    u have 0spelling whicha has attributes x,y and z on day 1 with 10 records
    so do ur aggregates on day1 with same values
    now on day2 u had new values of attributes y,z,s,d and new hierarchies and so u add new records
    with data load u will load the data with version M of modified and is not available for reporting
    If u do attribute change run then this modified version is activated to A i.e. active version .
    It will also do the change run alignment for Aggregate for new attribute values and new hierarchy values for aggregate.
    now in order for this data to be available for reporting u will need to do the roll up of aggregate.....
    if u roll up aggregate before attribute change run , new data is not avaialable for reporting
    if u roll up aggregate after attribute change run, then data is available for reporting
    if u dont roll up aggregate eventhough new data is in dataprovider, still new data will not be available for reporting.
    this is how it works

  • How does attribute change run works for Aggregates and Master data?

    Hi
    Can anybody xplain how does the attribute change run works for Master data ?
    For e.g.
    There is 0spelling and it has master data
    On Day 1 there are 10 records
    day 2 it has 12 records
    so with attribute change run this 2 new records will get added....
    The values for this  12 records will added seperately in Data load
    Is this how it workss
    So how about Aggregates which has Master data.????

    for e.g.
    u have 0spelling whicha has attributes x,y and z on day 1 with 10 records
    so do ur aggregates on day1 with same values
    now on day2 u had new values of attributes y,z,s,d and new hierarchies and so u add new records
    with data load u will load the data with version M of modified and is not available for reporting
    If u do attribute change run then this modified version is activated to A i.e. active version .
    It will also do the change run alignment for Aggregate for new attribute values and new hierarchy values for aggregate.
    now in order for this data to be available for reporting u will need to do the roll up of aggregate.....
    if u roll up aggregate before attribute change run , new data is not avaialable for reporting
    if u roll up aggregate after attribute change run, then data is available for reporting
    if u dont roll up aggregate eventhough new data is in dataprovider, still new data will not be available for reporting.
    this is how it works

  • Attribute change run and aggregates

    Hi Gurus,
    After loading to master data, we do the Attribute change run via RSA!->Tools and select the particular infoobject (which was loaded).
    After this do we need to activate the aggregates or are they taken care by the change run which was done for the infoobject.
    Also do we need to activate the master data via its context menu or is the attribute change run sufficient.
    Thanks,

    Whenever you load new datas into your master data table it wil be in M version(Modified version). you are running an attribute change run to change the M version to A version(Active version). so you dont have to activate the master data separately via its context menu.
    The attribute change run will aslo take care of your aggregates. You dont have to activate your aggregates separately.

  • Error in process chain with attribute change runs

    We have one warning is coming in one process chain :A type "Attribute Change Run" process cannot precede process "Execute InfoPackage"
    We checked the Process View , we found that there are number of attribute change run after each scheduling of Info package with different datasource but for same data target.
    How to remove this warning .
    Some onsite person has added this extra Attribute Change Run recently.

    Hi Surendra,
    If it is the same Info-object that is getting loaded through different Info-packages then have only 1 "Attribute Change Run" process at the end. You can ignore the warning.
    Bye
    Dinesh

  • Attribute change Run and Infocube Problem

    Hi SAP BW Experts ,
       I am getting the following problem
    2 days back our production system was down when Attribute change run is running in a process chain . After the system is up I triggered the Attribute change run manually for that specific master data Object. But the jobs was cancled automatically. When I checked the Job log I found the following messages
        <b>“InfoCube XXX is locked by a terminated change Run”</b>
      System error: <b>RSDU_TABLE_COPY_INI/DDIF_TABL_ACTIVATE /BIC/E200073 /BIC/E100073 0</b>
    Message no. DBMAN100
    When I verified manage screen in the Infocube XXX , one request is not rolled up . when I tried to rollup that particular request manually again I am getting the same message <b>“InfoCube XXX is locked by a terminated change Run”</b>
    When I tried to create Indexes on that Infocunbe XXX , Again I am getting the same message <b>“InfoCube XXX is locked by a terminated change Run”</b>
    When I tried to load data in to that Infocube I am getting the same message <b>“InfoCube XXX is locked by a terminated change Run”</b>
    The Steps Taken By Me:
      1. In SM12 , there are no lock entries for the Infocube XXX
      2. According to A.H.P reply I verified the Support package . We are having Import Support package 18 for 3.10( BW 3.10 patch 18 or SAPKW31018 )
      so I think there is no problem from patch side.
    So please let me know by doing which task , I can eliminate the error message “InfoCube XXX is locked by a terminated change Run”

    I got this reference from one of other site. Hope this solves issues of most of our ques on this topic.
    We faced this problem and reported to OSS. They solved our problem.Here is
    the answer from OSS
    I connected to your BWQ system. I checked the table RSDDAGGRMODSTATEand
    found an entrie for a change run "not yet" finished.
    CNSID CLOSEDFL TIMESTMP_START TIMESTMP_END TSTPNM
    207,851,300 20,030,910,141,500 0 SIDTLHG
    As you can see, the field CLOSEDFL is blank (should be 'X' for an ended
    change run) and the field TIMESTMP_END is also zero.
    You can also check with the function module RSDDS_CHANGERUN_MONITOR as
    in note 388069 that both objects you reported are the ones involved
    with thi change run error (Infocube ZINV and Infoobject ZELEM_PEP):
    E_CR_STATE C
    E_T_CHANM 1 Entry (IOBJNM = ZELEM_PEP)
    E_T_HIEID 0 Entries
    E_T_AGGRSTATE 1 Entry (AGGRID = 3QR79ZYB6VGSDS3C42HPXMA8S
    ICUBE = ZINV)
    E_T_MSG 1 Entry (IOBJNM = ZELEM_PEP)
    You have two choices to solve this problem. You cn either:
    1.- Restart the change run and let it finish with ok.
    The change run usually fails due to database errors, tablespace
    problems, and when some user manually cancel it (NEVER should be
    done!!)
    2.- Change manually the entry from table RSDDAGGRMODSTATE that isdescribed
    above. Set the field CLOSEDFL with a 'X' and also fill the field
    TIMESTMP_END with a value with the following format
    yy,yym,mdd,hhm,mss. Use, for example, '20,030,910,181,500'
    IMPORTANT!!!
    After this change on table RSDDAGGRMODSTATE, you have todeactivate
    all aggregates, activate again and refill them!!
    Hope this solves your error. If the issue is solved, please close this
    message with the [confirm] button.
    Best regards,
    David =C1lvarez
    SAP Active Global Support
    The answer refers to our problem.We chosed option 2. Here is the AbAPcode:
    REPORT ZLOCKED .
    tables: RSDDAGGRMODSTATE.
    select * from RSDDAGGRMODSTATE where CLOSEDFL = ' '.
    RSDDAGGRMODSTATE-CLOSEDFL = 'X'.
    RSDDAGGRMODSTATE-TIMESTMP_END = 20020912195015.
    MODIFY RSDDAGGRMODSTATE.
    ENDSELECT.

  • Hi i have 50 infoobjects as part of my aggregates and in that 10 infoobjects have received changes in masterdata.so in my process chain the Attribute change run in running for a long time.can i kill the job and repeat the same.

    Hi i have 50 infoobjects as part of my aggregates and in that 10 infoobjects have received changes in masterdata.so in my process chain the Attribute change run in running for a long time.can i kill the job and repeat the same.

    Hi,
    I believe this would be your Prod system, so don't just cancel it but look at the job log. If it is still processing then don't kill it and wait for the change run to complete but if you can see that nothing is happening and it is stuck for a long time then you can go ahead and cancel it.
    But please be sure, as these kind of jobs can create problems if you cancel them in the middle of a job.
    Regards,
    Arminder Singh

Maybe you are looking for