Auto PR by MRP

Hi All,
Am using MRP for Auto PR based on reorder point specified in material master.
I did all the configuration check. Its running perfectly for one plant. Now for the same material user want to use MRP process for another plant. So I extended all those materials to another plant and blocked in first plant for MRP in Purchasing view. But when job is running (RMMRP000) no PR are created. But when I created new material, for that material PR are generated. What may be the reason. Pls guide.
Regards...
Edited by: sapsarang on Apr 11, 2011 12:50 PM
Edited by: sapsarang on Apr 11, 2011 2:10 PM

Thanks Jurgen for the reply.
Its not having planning file entry. But when m trying to create by MD20, its showing following msg. I ticked the box " Net Change Planning"
The material X has been marked for the MRP run
   Message no. 61078
Pls guide.

Similar Messages

  • Auto PO through MRP

    I want to create PR & PO both automatically through MRP by the explosion of BOM.
    how can I do this?
    Pl detail in steps.
    Regards
    VS

    Hi VS,
    Auto PR creation through MRP is possible. While running the MRP system will generate planned order or Purchase requistion based on creation indicator. If u have a material type of both internal and external procurement type then u must select the creation indicator accordingly for PR generation.
    For Auto PO u need to maintain Auto PO both in Material master and Vendor master. The PR must have a unique source assigned to it. You need to maintain a source list for this. By running ME59 u can create PO from PR.
    Hope this helps.
    regards
    Anand.C

  • Automatic schedule lines not creating after MD03

    HI Gurus,
    When I am running MD03 system is creating Pur. Requisitions instead of Schedule lines
    I am running with
    NETCH
    2
    3
    1
    1
    1
    29102011
    Data maintained
    1.Material master /vendor master Auto po ticked (MRP type VB ROP 500 ,Safety stock 600, current stock 200)
    2.Sch. Agreement created with LP (validity period, Qty ok)
    3.Pur. Info rec maintained for vendor material for the plant.
    4.Source list maintained with Vendor,scheduling agreement no ,item no, MRP indicator 2 Fixed vendor ticked
    Now after Running MD03
    Pur. Req created for 400 qty
    but when I click on Procurement proposal manually I can select Del. Schedule and create
    but system is asking Agreement no. item,qty etc (I already maintained Source list system is asking again )
    Then why not system creating automatically..
    Please help..
    Thanks in advance

    Thanks  Jürgen,
    It was a problem of Date ,validity period of the SA.
    which I sort out any way thank you. for your input

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Update Fund & Fund center data in auto generated PR during MRP RUN

    Problem in the MRP auto generated PRs.
    The normal PRs created manually have all relevant fields of fund center viz CO area ,commitment item,Funds center, fund.
    But the problem is with respect to the Purchase Requisitions generated automatically during the MRP RUN.
    How to include the fund centers in MRP generated PRs automatically in the creation stage itself instead of going into change mode using ME52n Transaction code and change it to include fund centers one by one for each line item.
    We require this as we have hundreds of PRs generated every day.

    Hi,
    In order to fulfill this requirement, transaction FM_MRP_PR should be used.
    Please also take a look to FM_MRP_PR on-line documentation :
    The PRs generated from the MRP run are considered as planning documents
    and do not have any impact on the budget. To encumber these PRs in the
    corresponding settlement receivers, you have to execute this program for
    the relevant PRs.
    Best Regards,
    Arminda Jack

  • MM:We produce a MRP run each week. If auto PO is set up does all of the

    Dear Gurus,
    We produce a MRP run each week. If auto PO is set up does all of the
    pr's allocated to one vendor get adopted into the one PO?
    Please let me Know ASAP
    Regards
    Raj

    Hi,
    Use Tcode-ME59 ,and create single PO w.r.t Mulitple PRs ,if you want to do again advance automatic then make a Job and schedule the same as per your requirement.
    Hope this will resolve your query.
    Thanks & Regards,
    Sandesh Sawant

  • Does the profile "MSC: Auto-Release Compression Days Tolerance" work with MRP or just ASCP?

    Does the profile "MSC: Auto-Release Compression Days Tolerance" work with MRP or just ASCP?

    All the objects starting with MSC are owned by ASCP and will only be supported in ASCP and no where else.
    Same goes for this profile.
    Thanks,
    Abhishek Sharma
    Please mark the post correct or helpful, if answered

  • MRP auto creating and batching releases

    Using standard functionality it's possible for standard Oracle processes to automatically create PO Releases within the Release_Time_Fence_Days. We want to use this functionality, but, the answer it provided was inappropriate.
    The main issue is that if there are two MRP Planned Orders for different days and the Delivery Calendar indicates that they will both be delivered on the same day, the result is that two PO Releases are generated rather than one?
    This makes it difficult for the Receiving staff who would have to book material in against different releases; doubly awkward if the material was delivered all at the same time.
    Does anyone know of a way to sum/group the releases at all (by vendor/part/dock date)?
    Regards,
    Bren

    Dear
    Are you dealing with Single vendor  where you want Multiple Schedule Line item through single PR  which should be generated through MRP run ??
    What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.
    Or you can use Qouta arrabgement in that case for different vendor .Please refer : Multiple Requisition  line itme for Quota arrangement
    Just check and revert
    regards
    JH
    Edited by: Jiaul Haque on Dec 25, 2010 1:52 PM

  • Auto PO creation from MRP PR

    All,
    what settings do I need to do in order to have automatically PO's created from MRP PR's?
    1 besides the Automatic PO in Material Master and Vendor master and the fix Source list, what else do i need to set up?
    2. What are the next steps?
    THANKS

    Dear Alice,
    Please check the PR status (release procedure),info record, also check the source in PR.
    Please also check to below link for similiar link,hope it can helps you.
    Steps for creating Automatic PO ???
    Re: Automatic P.O
    Regards,
    w1n

  • Auto MRP run in SAP R/3

    Hi all,
    My query is that , how can I run MRP automatically on a daily basis in SAP R/3. Is there definite settings for it?
    Thanks

    Hi,
    Automatic MRP can be schedule at plant level only and from MDBT (MRP in background) and MD01 (MRP in foreground..this is not advisable) transactions.
    You can schedule this either from MDBT transaction or from SM36. You first have to create variant for MRP program RMMRP000 for your plant with MRP controlling parameters from SE38 transaction if you want to schedule from SM36 and schedule as per your requirement like daywise, weekly or monthly.
    rewards for all useful answers.
    Regards
    TAJUDDIN

  • ASN POACK needs to be MRP relevant and InboundDelivery auto set to COMPLETE

    Dear Experts,
    We have the following requirement not sure how to implement this.
    Need ASN's and POACK to be MRP relevant for accurate planning.Business
    needs to receive against PO,not the inbound delivery for efficiency
    purposes.
    Set confirmation control key to have MRP relevant and GR relevant but
    without invoking the use of an inbound delivery.
    When inbound delivery is created from inbound ASN,need ability to
    automatically set Inbound delivery to COMPLETE.This supports delivery &
    shipping requirement to receive using PO,not Inbound Delivery, and NOT
    have inventory supply duplicated,e.g. by Inbound Delivery created by
    ASN, and again by any Inbound Delivery that may be created as part of
    the PO receipt process.
    Secure creation/change POACK and ASN now MRP relevant documents to
    avoid overpass the PO line item QTY+tolerance,by providing'error'
    message and blocking the saving of the document if happens.
    Does it exist an user exit to implement this.
    Look forward to get your reply.
    Thank you and regards

    Worked with DBA and though source tables were not huge, we extended manually and proccess completed once we re-ran.
    Thanks all.

  • Auto Email Throgh SAP After Creating Schedule Line Through MRP Run

    Hello experts,
    is it possible to have email generation when scheduling lines are created through MRP run ? if yes kindly let me know the procedure.
    Regards,
    Durgesh

    Hello Raghavendra,
    For same requirement i did what you suggested but Can you please guide us what Business object needs to be used as start event for WF3100020 which we are activating. Because We are not able to activate the standard workflow.
    It will be better if you help us with steps.
    Thanks in advance.
    Regards,
    Yuvraj

  • Auto MRP run

    I have done to schedule MRP automatically. I have done this by using transaction MDBT.
    My question is:
    But how will I come to know if the Background job is being scheduled? I mean I have done a trial in FR1 server , and in MRP lists i am not able to see any difference. New MRP lists are not generated. Can you tell exactly where can I see that the scheduled job is done successfully.

    Hi,
    In MDBT only you can get the clour green if job is scheduled or running "in the sow scheduling tab"...you can see there status of the job like running, schedule OR finished.
    after finishing you can check the MRP results from MD04/MD05 list for individual parts and MD06/MD07 at plant level MRP results evaluation.
    Rewards your points and request you to do not post repeated queries.
    Regards
    TAJUDDIN

  • Auto cancellation of schedule lines

    Hi,
    We have a requirement fo auto cancellation of schedule line such that after some time of schedule line delivery date system should cancel the schedule line if the GR has not been posted so that new schedule line needs to be generated by MRP .
    In standard scenario if the GR has not been done system will keep open the schedule line and will not generate new schedule line.
    Is there any config setting is there??
    Thanks
    Prasad

    Hi Bhavin,
      Two report program are there to cancel error msgs automatically..
    1) RSQIWKEX
    2) RSXMB_CANCEL_MESSAGES
    Regds,
    Pinangshuk.

  • Delivery date calculation in auto scheduling

    Dear All,
    We have maintained planned delivery time , gr processing time in mm master as well infor records.
    We are running MRP and auto scheduling and updating schedule lines through MRP.
    System updating schedule lines and the delivery date also. what is calculation of delivery date in this case ?
    also system updating 3 lines with different delivery date ..why ? why not one line ?
    vijay

    no solution.

Maybe you are looking for

  • Need help about method close() in BufferedWriter Class

    Hi All, I'm a newbie in Java programming and I have problem regarding BufferedWriter class. I put the code snippet below. Sometimes I found wr.close() need a long time to be executed, around 9 seconds. For the normal case, it only needs 1 second. The

  • AirPort Express Slowing Connection

    I am experiencing a significant slow down using AirPort as my WiFi Router. I have Time Warner Cable Ultimate 100 as my internet package, running through a Motorola SB6141 and speed tests clock my connection between 85 and 97 Mbps when I'm hardwired.

  • Monitor on timeline goes black...

    Using the latest version of Premiere Pro, what causes the monitor to go black on the timeline? 

  • Chatzum search engine has installed on Firefox. How can I remove it

    Chatzum has installed itself on Firefox.and appears as default search engine each time I open a new tab. It does not appear in the search enhines list or as an add-on. Can you suggest how to remove it

  • How to change the maximum number of process per user in BW ?

    Hi, Do you know how to change the maximum number of process allowed per user ? With RSRT we can customize the number of process per query but I don't know where we can customize the maximum number of process per user. In fact, my production environme