Automatic change of Work Center during Confirmation.

Happy New Year to all!
Just want to ask if anyone of you encountered the scenario during confirmation in which the backflushed work center was changed. The user claims that they did not do any changes during confirmation nor did they change manually the order itself. The confirmation happened last December and they only noticed it this month when they were checking the reports.
I did not configure their system so that they can change the Work Center during confirmation. By default, the work center is grayed out during confirmation.
Hope to hear from some of you soon!
Thanks and regards,
jLmendoza
Edited by: John Luis Mendoza on Jan 4, 2011 3:15 AM

Dear
If your production order operations are re-scheuled and dispatched after Capacity Avalaiblity check in cm21/cm22/cm31 etc  , then during the dispatch of operation ,  you have option to change Work Cnetre , time , date based on the selection option in Startgy profile (CM31/CM21-Enter the WORK CENTRE /Order )  and check wether work centre is changed.
One more option may be in Order Change in CO02-Operation Overview -Operation -Work centre -Here user may change the Work Centre .
If you have Order Change management active then you can trace the same .
Refer : Production order change history
Otherwise , there is not such confirguration in SPRO where work centre can be changed automatrically during confirmaiton because it will grade out based on the ste of confirmaiton default screen in OP00.
Hope it clarifies
Regards
JH

Similar Messages

  • Changing operations work center during creation of  PM order

    Hi all,
    I am looking for BADI or EXIT in order to change operationS work center which created from maintenance calls.
    Does anyone know such possibility?
    Assaf

    Assaf,
    Have a look at BADI IWO1_TL_INTEGRATION2.
    Also see [OSS Note 925072|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=925072]
    Which system are you running?
    PeteA

  • Changing default Work Center during CATS time entry

    Hi Folks,
    I am hoping someone here can throw some expert advice.
    Currently during time entry in CATS, we have Work Center coming in from the Work Order. Its getting defaulted without any option to change it. Business here has a need to change it. I have llooked into the CATS profile to see if there is a place that enable the WC to be defaulted.
    In Transaction CAC1, there is a section that shows what fields are being defaulted during CAT2 time entry. However I do not see the Work Center as one of the option there.
    Can any one help?
    In short, where do we disable the defaulting of the WC from the Word Order during time entry?
    Thanks in advance.

    Hi,
    Adding to what Kapil said; if the work centre is a grayed out in time shet screen then you can go to CAC2 transaction and make it editable. By this way users will be able to change the work centre on screen.
    Regards
    Sreekanth

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • All default routing value has to be changed, while changed the work center in production order

    Dear friends,
    our client they want to change the work center in production order.according to production version work center also they are changed.so while change the WC,all the default value has be changed as per routing what we maintained in routing.At present we have to enter the manually change the W.C as well as set up time and operation time enter manually.Any other option to do the automatically capture value from routing while change in Work center in production order.pl help me on this.
    Thanks&Regards
    Sabhapathy R

    Hi Rahul,
    Thanks for reply. I am maintained in diff value  maintained routing , Ex :First routing i have  work center 'X' value maintained as a setup time in 15 Min's and operation time 10 Min's
    second work center 'Y' I have maintained as set up time 10 Min's and operation time 30 Min's,
    Now I want to change the work center in production order as a 'Y' so whatever value maintained in routing , it has to be changed automatically (10 min's and 30 Min's), but system will not change only old value only picked (15Min's AND 10 Min's).
    Now I think you get to know what the client requirement, kindly do the need full.
    Regards,
    Sabhapathy R

  • Change in Work center

    Hi SAP Friends,
    I want to do some tick marks in capacity field of work center in one work center as well similar tick mark at other work center also.
    Please Tell how to do in one time?
    Plaese Reply.
    Chandra.

    Hi,
    First in T. Code : OP36, you need to define the Default Capacity.
    Enter your plant and Capacity catgort for e.g : "001".
    Define the default values carefully.
    Then Secondly, in T. Code : OP42, you need to define the Default Work center.
    With thses two settings every time you will get the work center with filled in fields and you can modify at any point in time.
    But, to change the Work center Capcity details, I guess there is no Mass Maintenance Transaction..
    Regards,
    Siva

  • IW41: automatic update of activity type when changing the work center?

    Hello colleagues,
    when doing a time confirmation with IW41, we have following problem:
    In the PM order the operations are assigned to a neutral executing work center, as it not known which individual technician is completing the operation later on.
    Now when the individual technician is entering the time confirmation with IW41, system is proposing the work center indicated in the operation from the PM order, then technician is overwriting the work center proposal with his own individual work center ID (and pressing Enter), but the activity type is not getting updated automatically. So the technician must jump to field "activity type" and choose the correct activity type.
    Is there any solution (hopefully with user exits!) to have the field "activity type" automatically updated with the one indicated in the work center, which was entered manually?
    Thanks for your ideas!
    Regards,
    Patrick

    Hi Maheswaran,
    yes, as usual all PM work centers have only 1 activity type assigned in the costing tab.
    We also checked the settings of the activity type (KL03), but we just found one difference: the price indicator was set on 3 "Determined manually" - we've changed to 1 "Plan price, automatically based on activity" (..same setting as for the act. type of the work center with working update of act.type).
    We tested already all possible constellations and scenarios, but we have not found any good reason for the behaviour.
    Thanks for your efforts so far!
    Patrick

  • Activity Type Changes in Work Center

    Hi Experts,
    We now want to change the activity type in a work center, and hope all the routings that have the work center being changed automatically. Currently, the existing routings can not be changed automatically. Is there a way to have all the routings changed as well? 
    Best Regards,
    Helen

    Hi,
    In Costing tab next to the activity you should find a check box for Reference Indicator. If this is ticked, then the changes done in work center will be automatically read into routings.
    If it is not, then you will have to manually change in routings. For individual, you can use CA02, for mass work with CEWB, working area as SAP_OPERATION
    Regards,
    Vivek

  • Urgent : Automatic Selection of  work center

    Dear All,
    Good Morning,
    please provide me valuable input to accomplish the business scenario,
    the scenario is
    1.There are 16 NC T-Bending Machine with different capacity.
    2. The Client wants to select the workcenter automatically if the 1st workcenter is overloaded i.e 2nd workcenter should be selected by the system
    Again,if 2nd workcenter is overloaded then system should select 3rd workcenter and so on..
    How I can make it possible.
    I am trying the Alternative sequence ,will it works to achive the requirement .
    please give ur valuable inputs.
    Thank in advance,
    Vijay Mankar

    In capacity leveling transaction, enable "date entry when dispatching".  Then, every time you dispatch operations, you will get a pop-up for date entry.  Luckily, this pop-up also has a field for work center - so you can change work center also (with or without date changing).
    We are using this method extensively.  Start transaction with all the work centers that you want to be considered.  Then, just select all the orders and dispatch.  In pop-up, change work center to the next in list.  So, some orders will get dispatched to that work center, and after its capacity is fully booked, the balance orders will fail to dispatch.  Once again, select all orders (left in the order pool) and dispatch, and change work center in pop-up.  You will have to do this as many times as the list of work centers OR till all orders are dispatched (whichever occurs first).  Takes just about a minute per work center and works perfectly.
    - Chetan

  • Mass change of work center in production order

    Dear All,
    Is it possible to mass change work center in production order, i.e. i have around 100 production order of which i have to change the work ceter assigned in particular operation .
    Thanks and regards
    Manish

    Hi Manish,
    If you have not posted any activity or goods to the production order, then in header click on Functions -> Read PP Master Data.
    The order will now read the routing with the new work centers, provided the same has been changed.
    If you have posted some activities or goods movement done, then its a manual process.
    Hope the above answers your query.
    Regards,
    Vivek
    Added
    If in case you have posted some goods or confirmed some activity, check if you can reverse the same, re-read the routing & then post back the goods.
    Edited by: Vivek on Feb 24, 2009 12:22 PM

  • Work Center Group Confirmation

    I have the following Work Centers:
    FOUNDRY
    WC1
    WC2
    WC3
    I made a hierarchy where all the work centers are under FOUNDRY.
    Now I use WC1/2/3 in my routing. My question is, is there anything that can be done where I could confirm just FOUNDRY and all of the operations in the work centers beneath it would be automatically confirmed?
    Also, when I follow up I dont want to follow up on each individual work center, I want to follow up on the FOUNDRY level, possible?

    but that would mean in my routing I have to put
    WC 1 / 2 / 3 and ALSO FOUNDRY (which is not logical, foundry is just created to group the WCs)
    Also that would also leave the problem of following up on the Foundry level, I need a report that wouldn't show the WC1/2/3 just show the progress on the FOUNDRY (group) level.
    Thank you

  • User exit/Badi for changing operation work center based on service product

    Hi,
    I have an requirement to change the operation work center based on the service product in IW31/IW32 transaction. I am using the BAdi 'IM_SM_BADI_READT399A' for changing the main work center. It changes all the operation work centers except the first one. But I need to change it all the operations.
    Thanks in Advance.

    I am using the enhancement spot 'IWO1_TL_INTEGRATION2' for changing the first operation work center

  • Automatic creation of work center per new employee

    Dear gurus,
    Is it possible to instantly create Work Centers every time an employee is hired and created via HR module? We consider an employee as "created" when infotypes 0000-0002 are accomplished.
    Work centers in PS are manually done in CNR1.
    The reason for this integration is that the Work Center needs data from HR's personnel master data such as: name and cost center. And it will be tedious to manually create work centers every time a new employee is hired.
    We are thinking this will be done via an ABAP batch input program which just automates the two transactions (PA40 and CNR1). However is there a simpler way to do this? For example, a SAP standard method that we're not seeing?
    Thank you!
    Regards,
    Mozart

    HI,
    I think it can be handled in the following manner
    Use Dynamic Action to call a Cutsom Routine which will inturn do all the actions required. Take Abaper help ..

  • Update Routing data after change in Work Center

    Hello All,
    I have just modified the Costing Data for 100 Work Centers CR02, setting a new "Activity Type" and "Activity Unit".  But the Routing Data CA02 does not get updated correspondingly.  I would like to ask is there any standard program which can help me to do the mass processing as to update the data to the corresponding routing?
    Thanks.

    1) You can change as per Mr Anupam sharma Said
    or
    2) YOU can also Update the data IN CA85N
    In selection criteria enter the respective work center and Plant
    and In new Value Give
    Same work center, Plant,  activity value , Unit  and activity type
    execute
    select the all the work center  and then click mass change
    Edited by: Sundaresan . E. V on Nov 12, 2010 10:25 AM

  • Mass update/change of Work center

    Hi
    I need to change the 'Factory calendar' to 'FO' and 'Set up Formula' to blank for about 500 work centers.
    Is there any transaction avaliable to update new values for work centers, in mass change ?
    Please help me.

    Dear,
    Please try with  CA85 or go with BDC.
    Please refer this links as reference ,
    [Mass Replace Work Center |http://www.sap-img.com/production/guide-to-mass-replace-work-center.htm]
    Regards,
    R.Brahmankar

Maybe you are looking for