Automatic Clearing (F.13) not possible for two different year GR/IR document

Dear Expats
We are facing one problem.
Through automatic clearing F.13 we are unable to clear the GR and IR document.
GR document posing date in 2013
IR document posting date in 2014
How can we will solve the issue?
Regards
Tarek H Chy

Dear Christian
Thanks for your feedback
As per advice i have remove the year
Clear over the year document.
Regards
Tarek

Similar Messages

  • Automatic time conversion is not possible

    Hi Friends,
    I have a problem in Transformation Level when i am mapping "automatic time conversion is not possible for source field FISCPER to 0FISCYEAR,FISCPER3".can any one help me in this issue.
    Thanks
    Narasimha

    Yes if it was date filed then it would have been possible.If you are trying to derive the fiscal year between datasource and cube then you can get it with the help of simple filed level routine.
    Map your fiscper field from source to fiscal year--Rule type Routine.
    RESULT = SOURCE_FIELDS-(Technical name of source field)+0(4).
    For Posting period
    Map your fiscper field from source to fiscper3 year--Rule type Routine.
    RESULT = SOURCE_FIELDS-(Technical name of source field)+4(3).
    This will give you the required output.
    Regards,
    AL

  • The reporting point backflush is not possible for make-to-stock repetitive

    Hi All,
    we are using the assembly backflush in the MTS REM process. we are need to do the reporting point backflush
    if we tick against the RP backflush. what will be the effect in the process while confirmation.
    i read the sap library . it say like
    The reporting point backflush is not possible for make-to-stock repetitive manufacturing.
    is it correct.
    Thanks
    VRaj

    Hi mangal,
    i did all the setting as you said. but when click on the reporting point.
    system thru error
    Error reading reporting point information
    Message no. RM111
    Diagnosis
    The repetitive manufacturing profile is set for the reporting point procedure. However, either no reporting points exist for the material or they are incorrect. Two common reasons for this are:
    The repetitive manufacturing profile has been changed in the current session.
    You have not defined any milestone operations in the routing.
    When creating the product cost collector, no reporting points were created.
    Procedure
    Two alternative solutions are possible:
    Assign a repetitive manufacturing profile with no reporting point procedure to the material in the material master record.
    Recreate the reporting points by recosting the product cost collector. To do this, the following prerequisites must be met:
    In the material master record, in the production version, you must enter a routing under either detailed planning (first priority) or under rate-based planning (second priority).
    Milestone operations must exist in this routing. The system ususally automatically creates the reporting points from these milestones when creating a product cost collector or when creating a production version.
    how to create the REPORTING POINT

  • Account determination not possible for key 3000

    Hi gurus,
    While generating invoice iam getting the error like
    "Account determination not possible for key 3000" 
    3000 is comapny code.
    it shows the Diagnosis
    "The system could find no entry for the following key combinations in the entries for account determination:"
    "Chart of accounts  
    Posting area Billing Default Values: Repayment Method (R401) 
    Key 3000 
    Field names BUKRS "

    Hi,
    For the error, go to details, and check the main/sub transaction.  From there you can navigate thru error analysis and it will take you to the configuration details in SPRO. Check for the key specified in the error log, if the entry is present or not. If not maintain the entries accordingly.
    Alternatively
    Please check the configuration for Automatic GL account determination.
    Please check if the GL determination is made for the main transaction and sub transaction for which it is giving the error.
    Path -: SPRO -> Financial accounting -> Contract Account receivable and payable -> basic functions -> Postings and documents -> document -> define account assignments for automatic postings -> Automatic GL determination.
    Check for ISU : Define account assigment data related to main transaction and data relevant to transaction.
    Alternatively check tcodes EK01 / EK02.
    Hope this helps!!
    Regards,
    Rajesh Popat

  • Goods receipt not possible for delivery 800015869: error code 1

    Dear friends,
    I am doing MIGO-GR for outbound delivery, but getting error once inputting outbound delivery no.
    Goods receipt not possible for delivery 800015869: error code 1
    Message no. M7865
    Diagnosis
    The goods receipt for the delivery cannot be posted.
    The error according to the error code:
    1. The delivery does not exist.
    2. The delivery type is unknown.
    3. The delivery is not goods issue posted.
    4. There are no delivery items.
    5. The receiving plant could not be determined.
    6. The delivery items have already been goods receipt posted or contain zero quantities.
    7. Goods receipt(effect)movement type to goods issue movement type could not be determined.
    8. It is not currently possible to block the delivery.
    Procedure
    Error code 1      : Check your entry.
    Error code 2,3,4,6: Check the delivery and its document flow.
    Error code 5      : The delivery must be related to a purchase order or
                        the customer must be a retail business.
    Error code 7      : Check the settins for your movement types.
    Any poniters to check the setting in PO or delivery or any setting in SPRO.
    Regards
    Ashutosh

    Hi Anupam,
    That is the requirement of my scenario
    That is happening in intercompany posting.
    I am explaining to you.
    say total stock for article AR is 1000 ( In DC --A it is 500 and in store B it is 500)
    I have two company codes X and Y
    One DC (A) belongs to X and second store (B) belongs to Y.
    I have stock available for say article ( am working here in IS Retail  instead of material ) in both DC --A and Store --B.
    Now I have created PO thru replenishment planning WRP1 , now in PO supplying plant is DC.
    Now I did delivery thru VL10B and then picking and then PGI.
    Now my stock is reduced in DC by PO quantity created.( let us assume it is 100)
    So now total stock in DC=400
    Now this stock is in transit we can check thru MB5T. so total stock in transit = 100
    Now I have to do GR against delivery , if I will do GR for 100 nos , there will be no stock in transit
    and stock of receivibg store (B) will increase by 100 nos.
    But I am not able to do GR against delivery so I did GR against PO for say 50 nos. In this case stock in store is increase by 50 nos.
    But there is another stock in transit available=50
    Now why GR is not happening against delivery but it is happening against PO???
    Any pointers

  • GR of Delivery completed item not possible for line item of PO/SA ?

    Hi,
    Am unable to Receive Goods in MIGO an Error - "GR of delivery completed item not possible for line item of PO/SA"?
    Regards
    Mohammed Khaja Pasha
    +919550917395.

    Hi Mohammed Khaja Pasha ;
    Delivery Completed checkbox provides a lot of fonctionality like an additional delivery is not expected, but is possible. If you prevent posting of migo , you can benefit from system messages M7 163 and 254.
    You want to ensure that the delivery is made before the planned delivery date : Set message 254.
    You want to ensure last possible delivery date : Set message 163.
    However ;
    The open PO quantity of the PO item equals zero.
    The PO item is no longer relevant for materials planning.
    The PO item is ignored when letters urging delivery of overdue goods are generated.
    The PO item can be deleted and archived.
    You can specify whether the Delivery Completed checkbox is to be selected automatically.
    Regards.
    M.Ozgur Unal

  • Pricing at time of goods receipt not possible for this item

    We're receiving error Message no. 06634 Pricing at time of goods receipt not possible for this item when trying to change the PO Pricing Date Category from No Control to 5 GR Date.
    The error message is clear and reads:
    Pricing at time of goods receipt not possible for this item
    Message no. 06634
    Diagnosis
    For this purchasing document item, you wish to specify that a new price determination process is to be carried out at the time of goods receipt.
    System Response
    Pricing cannot be carried out for the item at the time of goods receipt because the price was either entered manually or copied from the last purchasing document.
    The scenario is that we have a contract reference on a PO and the contract condition records are to be maintained as a new price is valid each day.  The problem without this is that the new pricing will not be reflected in the GR.
    What is the solution to overcome this issue?
    NOTE:  the Info Record conditions are not being read during GR as the PO references a contract.

    For further clarification the PO is referencing a contract and as such not pulling the pricing information from the info record and instead pulling the price from the conditions on the contract. 
    I want to change the pricing date category from " No Control" to "5 GR Date" however I'm receiving the error message stated and unsure of how to make this change.
    The intent is not to create a new PO each day the condition record is created and instead we are utilizing one PO referencing one contract with multiple date delimited condition records containing the daily pricing.

  • Direct Posting is not possible for G/L accounts

    Hi,
    Procurement of Consumables thru Maintenance Order(for Breakdown Maintenance):
    1. Generation of Purchase Requisition thru maintenance order .
    2. Purchase Order from purchase requisition
    3. MIGO
    4. MIRO
    The required consumables are assigned in maintenance order. when converting PR to PO this consumables will automatically flow. According to the valuation class and gl account in material master GL  account  will also flow automatically.
    When converting PR to PO the system throws an error saying that Direct posting is not possible for the G/L account.
    I made this GL account as post automatically to ensure that  there should be no manual postings for such  automatic account determinated GL accounts thru valuation class.
    This error can be resolved by removing the tick mark post automatically but is this correct. If it is so then what is the implication of automatic a/c assignment thru valuation class.
    <removed_by_moderator>
    Thanks in Advance
    Regards,
    Radhika
    When I am trying to use a G/L account for a Consumable (eg: diesel) (that is required for Maintenance) at PO level (through maintenance order) system throws an error sying that Direct posting is not possible for the G/L account.
    Also, teh Same G/L

    Hi,
    Your balance sheet accounts for stock should be defined as for direct postings only. But the P&L accounts should not be marked.
    Regards,
    Eli

  • FBRA-Document includes already cleared items - reversal not possible

    While reset and reversal using FBRA I am getting the following error. Please do let me know if any clue to resolve this issue.
    Document includes already cleared items - reversal not possible
    Message no. F5 308
    Diagnosis
    A reverse posting clears all line items that are managed as open items. This is not possible if one of the items in question has already been cleared by another method.
    System Response
    Error message.
    Procedure
    If you really want to reverse the document with the number you specified, display the cleared items and reset all those items for which you can find clearing document numbers. Then repeat the reverse transaction.

    Hi Dewang,
    Thanks for your quick responce.
    step 01- Posted Customer Invoice on 01-Jan-2011with RV doc with Rs-1200: Doc 111111
    Step 02- Posted Customer downpayment on 01-Jan-2011 with DZ doc with Rs-1200: Doc No 2222222
    Step 03- Clear Customer line items on 10-Jan-2011 with AB doc with Doc no- 3333333
    Trying to reverse Cleared Item (i.e. Doc No 3333333) with T-Code FBRA. While doing Reset and reversal we are getting the above problem.
    Please let me know if you need any information.
    Regards
    Raj

  • Document is alrady contains cleared items-reversal not possible

    Hi All,
    At the time of MIRO reversal we are getting error massage Document is already contains cleared items-reversal not possible
    actually one MIRO document using TDS line item and we make a payment for that TDS line item after that we try to reserve MIRO document that time we are getting error massage.
    Please help me to resolve this issue.
    Regards,
    juhi

    Hi Spradip & Minesh,
    Thanks
    But as per my client they do the same in system but this document only not getting reveres why they don't know.
    but what we do because they want to reverse the document.
    Please help me
    Thanks & Regards,
    Juhi

  • MR8M-Document already contains cleared items - reversal not possible

    Hi Gurus,
    I am getting error message Document XXXXX 1000 2014 already contains cleared items - reversal not possible while cancelling IR via Tcode MR8M.
    Invoice was already paid twice by mistake hence we are trying to cancel via MR8M.
    I know we can do via FBRA by resetting the cleared item but is there any other options or workaround?
    Thanks,
    Kumar

    Hi Jurgen,
    Thanks for your reply;
    Invoice posted twice and 1 needs to be reversed. Please refer the attached screenshot.
    Thanks,

  • Is it possible to use the same Switch for two different clusters.

    I have 10g Rac setup on windows.
    Now I am planning to install 11gR2 on different servers.
    Is it possible to use the same Switch for two different clusters.

    user9198027 wrote:
    I have 10g Rac setup on windows.
    Now I am planning to install 11gR2 on different servers.
    Is it possible to use the same Switch for two different clusters.
    Yes.  Technically there will not be any conflict as long as the private addresses used by the 2 clusters do not collide, and provided that the switch's port capacity and bandwidth will not be exceeded.
    Your NA (netadmin) can also configure the switch to separate the 2 Interconnects from one another (called partitioning when using Infiniband) - if the switch supports such features.
    A major consideration is not to make the switch, public. That typically cause a range of problems and can have a serious impact on an Interconnect. But using 2 private networks on the same infrastructure should not have the same problems - if configured and implemented correctly.

  • Error M8-688 - Creation of several vendor line items is not possible for document type RN.

    Hello All,
    We are using the Net Invoice Posting with document type RN(Invoice- Net). We are generating different vendor line items in the accounting document based on the withholding tax codes involved in the invoice posting. When it comes to net invoice posting system is giving an error message M8-688 - Creation of vendor line items is not possible for document type RN. Is there is any way to create multiple vendor items with net invoice posting? Please suggest.
    Thanks,
    Chandu.

    I dont think that there is any way because it is a hardcoded error message.
          IF NOT t003-xnetb IS INITIAL.
            MESSAGE e688 WITH pi_rbkpv-blart.
          ENDIF.
    SAP is checking the customizing for net/gross posting per document type in table T003
    And if it is set up as net, then it is a hard error.

  • HT4314 I have two ipods in my house that were set up under the same email.  I have since assigned two different emails.  How can I change the game center account so that is not shared by both ipods because it is for two different users and they are not ha

    I have two ipods in my house that were set up under the same email.  I have since assigned two different emails.  How can I change the game center account so that is not shared by both ipods because it is for two different users and they are not happy?

    By "game center account", do you mean Apple ID?
    If so, you can change it.
    1. Tap settings and navigate to iTunes and App Stores
    2. Tap "Apple ID" and then tap "Sign Out"
    3. Log in with a different ID.

  • Posting is not possible for the specified company code.

    Hi SRM Gurus,
      We have a four company codes in our org.structure and if we try to post manual invoice for a particular company code with its currency, we are getting this error :
    "Posting is not possible for the specified company code "
    We have all company codes defined and inherited for the particular user in BUK and we get all the company codes in the F4 help of this user in BBPIV02 -->Basic data.
    Any suggestions pl.
    I doubt this particular Cocode is deactivated for invoice posting in backend. Is it possible ?
    Kindly suggest.
    Reg.,
    Sridhar.

    Hi
    Which SRM version are you using ?
    Are you getting this error for a praticular company code only or for all the comapny codes ?
    <b>Please read this -></b>
    Since you are trying to create Invoice with PO did you check the Vendor Root there is a attribute for company code. Please maintain the same, if not maintained.
    Refer the link below for details.
    Re: Company code for system missing in user attributes
    <u>Other related links -></u>
    Try to change the chart of acct info in OBY6 for a company code that was copied from SAP template, there is no Financial posting or any other posting in this company code.
    Re: Posting Period Error in Confirmation
    Hope this will help.
    Regards
    - Atul