Dear Gurus,
I originally posted this in PP and SD, however, it does now seem to be APO related.
Hence my posting here. Can you help? This is the question:
"How can we prevent that APO immediately creates a planned order when the purchase requisition is put in the system.
(apparently they set up the system as such that a flow then starts and automatically transforms the planned order into a production order).
We want to prevent APO to automatically create a planned order from the purchase req, we only want a planned order at a later stage, i.e. the finalised purchase order.
If a setting like this exists, can we activate this per plant?"
Thanks!

Hello there,
The control that you mentioned can be maintained at a product level, which is more granular than what you have asked for. Refer to the PP/DS tab of the product master and you will find a filed for PP planning procedure, which determines various actions that PP/DS executes for a specifi type of event. There are standard planning procedures (procedures 1-9) and ofcourse you can configure your own procedures as well.
The configurations here define if your dependents requirements have to created immediately or just a planning file entry has to be created or a product heuristic has to be started immediately or no action has to be taken!
Refer to below link for more info:
http://help.sap.com/saphelp_scm70/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm
Cheers,
Kalyan.

Similar Messages

  • Automatic Creation of Planned Order in PPDS Horizon

    Dear Experts,
    Kindly answer my following query.
    I have created PIRs before/inside my PPDS Horizon (its also falling outside horizon as SNP horizon is shorter than PPDS Horizon). If I check the PIRs created by me in /SNPAPO/RRP3, it also shows me planned orders corresponding to them. However, if I create PIR outside PPDS horizon then system is not automatically creating the planned order.
    Kindly let me know which master data/configuration setting is responsible for automatic creation of planned orders within PPDS horizon.
    Best Regards
    Rinju
    Edited by: Rinju Mukherjee on Sep 26, 2010 10:05 AM

    Dear Rinju,
    Check in Product Master PPDS view the Planning procedure maintained? if it is balnk check in the heuristic, the palnning procedure maintained.
    Since automatic planning procedure(3) is maintained, that is the reason it is creating order proposals, it self.
    Sree

  • Automatic creation of Planned order

    Hi,
    Would like to know how to check if a certain material is set up in MRP to automatically create planned orders or should be cretead manually.  I have verified the material type and the value is already PD (Material requirements planning).
    Thanks,
    Lyncel

    Hi,
    Based on the MRP types sytem will creates Planned Order automatically  when u run the MRP Run.
    MRP type can be  PD,VB...etc .  if it is ND  MRP will not create planned order.
    Even though u have selected the MRP type PD, based on the Planning file entry system  will include the Material in Planning Run and creates Planned order.(Md22)
    Letus explain your problem sothat help further.
    Pradeep

  • Automatic creation of production orders via planned orders

    Hello experts!
    is there a way via customizing to trigger an automatic creation of production order from a planned order when the planned order finished date is within the next week?
    thanks

    David,
    Not in customizing.
    Most people create a job step after the RMMRP000 program step in their MRP job, using program PPBICO40.  Dynamic date range is available as a selection criteria against the opening date, which is the standard criteria for selecting and converting planned orders (not finish date).
    Best Regards,
    DB49

  • How do I maintain storage location for Planned Orders in APO

    Dear all,
    Can you help us in maintaining storage location for planned orders in APO. The storage location from material master need to be updated in product master of APO and the same shall be automatically picked from product master during Supply Network Planning run.
    Material master CIF is live.
    We have got the following content error in CIF consistency check. How ever this is nt goging to harm any thing, but we would like to maintain in both R/3 and APO.
    Error:
    Plant and storage location in SAP APO: 2004
    Plant and storage location in SAP R/3: 2004 FGPA
    Thanks in advance
    Ram Mohan Rao Kolanupaka

    Instead of maintaining additional master data, i would rather use CCR user exits to switch off comparison of planned order at storage location level if the APO storage location is blank. This way you would not have to make changes to PPMs everytime a new scale out of the solution happens.
    In SE18 check the user exit /SAPAPO/CIF_DELTA3 (interface RELEVANT_FOR_COMPARE_ORDHEAD)
    If it is not possible to switch off this comparison then I guess changing master data is the next step. Do explore with a developer though about the first option.

  • Deletion of Planned Order in APO PP/DS

    Hi All,
    I have a question on PP/DS ( IS-Auto ). Suppose if we are deleting the planned orders in APO so what will happen to the concerned PDS. I want to preserve the PDS so that we can use them later.
    If we delete the Planned Orders then will the PDS be also deleted ?
    Thanks,
    Prabhat

    Prabhat,
    Think of a PDS the same way you would think of a Production Version in ECC.  It is master data, and one or more of these can be assigned to a Material/Plant combination.
    http://help.sap.com/saphelp_scm70/helpdata/EN/4d/01be3d1abbe913e10000000a114084/frameset.htm
    A Planned order is Transactional data.  Creating/changing/deleting a Planned order has no impact on PDS Master data.  During the creation of a planned order, the system reads the PDS info, and copies selected bits of this master data into the Planned order.  At this point, then, certain parts of the planned order data can be changed.  Such changes generally do not affect the underlying master data.
    http://help.sap.com/saphelp_scm70/helpdata/EN/49/d565caf54535f5e10000000a42189c/frameset.htm
    Best Regards,
    DB49

  • Automatic creation of Transfer Order when a delivery is created

    Hi all ,
    I wanted to have Automatic creation of Transfer Order when a delivery is created ,
    what are the configuration activities that needs to be carried out .
    Thanks ,
    KSR

    Dear Friends,
    I am also facing the same problem; I want the system to create a transfer order at the time of creation of an outbound delivery.
    I have done customization as under:
    Step 001
    Logistics Execution > Shipping > Basic Shipping Functions > Output Control > Output Determination > Maintain Output Determination for Outbound Deliveries > Maintain Output Determination Procedure
    Step 002
    On the screen, u201CProcedureu201D: Overview, choose the following:
    Procedure     Description
    V10000     Header Output
    Step 003
    On the screen, u201CControl datau201D: Overview, enter the following:
    Usage     Application     Procedure     Step number
    B     V2                     V10000     110
    Counter     Condition Type     Requirement     Description
    01     WMTA                     032                     Automatic TA
    The system does not create a transfer order automatically.
    May I request our learned friends to guide me?

  • Read the characteristics of a planned order in APO

    how can we read the characteristics of a planned order in APO.What Function Module can be used for this?
    how can we manually schedule the order activities based on the characteristics. Can we use the function module 
    /SAPAPO/OM_ACT_SCHEDULE by copying and making some changes in it for this purpose?

    Hi,
    if there are any orders in your system with characteristics (in planning version 000) then this report will find them:
    report  get_char.
    data:
       ls_genp     type /sapapo/om_gen_params,
       lt_orderid  type /sapapo/om_orderid_tab,
       lt_char     type /sapapo/om_charact_val_tab.
    ls_genp-simversion = '000'.
    call function '/SAPAPO/OM_ORDER_GET_ALL'
      exporting
        is_gen_params = ls_genp
        iv_simsession = ''
      importing
        et_orders     = lt_orderid.
    call function '/SAPAPO/OM_ORDER_GET_DATA'
      exporting
        is_gen_params       = ls_genp
        iv_simsession       = ''
        it_order            = lt_orderid
      importing
        et_charact_val_acts = lt_char.
    Best regards
    Thomas

  • Issue during automatic Creation of Work Order from Notification

    Hi,
    I have a issue during automatic Creation of Work Order from Notification.
    BADI implemented: NOTIF_EVENT_POST
    BAPI called in BADI: BAPI_ALM_ORDER_MAINTAIN
    I am able to create Work Order successfully but after that i need to update notification header with created work order number.
    But i am unable to update the same (VIQMEL-AUFNR).
    Can anybody provide solution for the same!
    Thanks,
    Kumar.

    Hi,
    Any inputs on above posted issue!
    Thanks in advance.
    Thanks,
    Kumar.

  • Mass creation of planned order

    Hello,
    is there a way to mass creat a planned order for a finished product? having same FG mat, plant and prod version.
    Thanks

    Dear
    1.Goto MD61 with User parameters like Plant , Requirement type , Version and Planning Date .Then Select the Material Radio Buttion with FG item code .
    2.Enter the FG qty as required in each month as demand
    3.GotO MD02-Single Item ,Multi Level with indicator : NETCH , 2,1,3,3,2   and Execute the MRP to create the Planned order  for FG
    4.Check the result in MD04
    There is no SAP Standard Traction to Mass creation of  Planned Order .That is possible in Demand Creation and MRP run .
    Regards
    JH

  • Block the creation of planned order

    Dear experts
    How can I control the creation of planned order? I want to block the creation of planned order if the BOM or routing is not exist.
    BRs

    Hi,
    I think this can be done using 'Material status' try the following and let me know if it works.
    Create a new material status in transaction OMS4 (like R1 - "Created but BOM and Routing not maintained" )and in the details screen select Option "B" for MRP messages.
    You designate a material as a "R1 -Created but BOM and Routing not maintained" In the master record.
        MRP                          "B" = warning
    Please try this and let me know the result.   
    Regards,
    Prakash

  • Automatic creation of Transfer order for Picking and putaway

    Hello All .
    I would appreciate if someone can explain the process of configuring Automatic creation of Transfer order for Picking ( outbound delivery)and putaway( inbound delivery)  .
    thanks
    Rahul

    Hi
    To have transfer orders created automatically in the background, you must first set the indicator Automatic transfer order creation for each respective movement type in the Customizing application for Warehouse Management under the path <b>Activities - Transfers - Define Movement Types</b>. The system automatically copies this indicator into the header item of the source document.
    For more information on how to set up automatic transfer order creation for transfer requirements and posting change notices, refer to the IMG for Warehouse Management under the path <b>Activities - Transfers- Set up Autom</b>. TO Creation for TR/Posting Change Notices.
    You can find more details on this link
    http://help.sap.com/saphelp_47x200/helpdata/en/c6/f85c504afa11d182b90000e829fbfe/frameset.htm
    Thanks & Regards
    Kishore

  • Unable to see planned order in APO

    Dear Experts,
    I'm creating a Project manufacturing order in ERP. After that I do MRP run in SCM7.0. When I check in Product View (transaction /SAPAPO/RRP3), I do not see any planned order, though I can see orders in ERP (Tcode-md04).
    I guess transfer of network to APO is not happening.
    Same problem arises when I schedule a dummy project in ERP and after I do MRP run in SCM7.0, I do not see any planned order in planning board.
    The MRP run in SCM7.0 shows no error and no warnings and everything appear in green.
    I was able to see planned orders in APO before there was system upgrade from SCM 4.2 to SCM 7.0.
    Please provide some clue to solve this problem.
    Regards,
    Jyoti

    Hi Jyoti,
    There will be an "Iterate" button on the left hand corner in the result display of CCR.  Please click on this button so that these errors will get iterated and goes to the respective distinations.  After this, you go to smq1 and smq2 trasnaction codes of R/3 and clear all the queues.  Similarly you clear the queues in smq1 and smq2 transaction codes of APO.  Afterwards, check whether you are able to see the planned order.
    Please confirm
    Regards
    R. Senthil mareeswaran.

  • How could I re-explode planned order in APO?

    Please adivse me how could I re-explode planned order in APO?

    Hi,
    Go to the planned order in the change mode, again adopt the source of supply and save.
    or you can use the PPDS heuristics "SAP_PP_021" New explosion to explode the orders.
    Thanks,
    nandha

  • Correlation of reservation with Planned order in APO.

    Hi,
    In R/3 in COGI we see reservations. my issue is I want to know for which planned orders in APO these reservations are.
    In the product view in APO we can see some reservations (PRDRES(W) - correct me if I am wrong). How to correlate these reservations with planned orders. I am looking in PP/DS module of APO.
    Thanks a lot in advance,
    Prabhat

    Hi Prashant,
                      You are correct and if product is showing the reservation then it is mean for all order in product view.
    You can check the Production Planning Table inside PPDS for wider view of reservation and orders.
    /n/sapapo/ppt1
    Check the SAP Note: SAP note 439596
    SAP Link is also useful:
    http://help.sap.com/saphelp_scm50/helpdata/en/64/dca63be2bc331be10000000a114084/content.htm
    http://help.sap.com/saphelp_scm50/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm
    Let me know if it is sufficient.
    Regards,
    Vishal

Maybe you are looking for

  • PrE Can't Find My DVD/BD Burner - Why?

    You have a multi-drive (DVD, or BD drive and Burner) installed on you computer, and it appears fine in the Control Panel>System>Hardware profile. Other programs can use it, but PrE, or Encore cannot find the burner, and reports such. What is going on

  • User Exit - adding defualt WBS Element in addi.tab for IW31 - Servi.Order

    I am facing a problem with adding WBS Element in Addit.Data tab for Service Order creation using IW31. At the time of creating service order using TCODE IW31, I have to maintian default values like WBS ELEMENT, for this I am using a USER EXIT "IWO100

  • How can I delete a file in AL11? Or rename it?

    Hi experts! I need to rename or to delete a file sites in Al11, can anybody guide me how can I delete or rename that file? The name is incorrect and there's a job how search for this file and is always running because the name doesn't fix with the go

  • Not able to connect to Oracle Data source in Oracle Essbase Studio 11.1.2.2

    Hi, When i tried to connect to Oracle data source, i get this error "Unable to establigh connection. Ensure that the server is running, the user name and password are correct, and the ohter data fields match the server's configuration" when i tried t

  • User not found in SharePoint application

    Dear Friends, We have a Sharepoint 2007 application hosted on port 443 for LDAP users. One of my team memeber has been  facing "user not found" error for the last 1 week while uploading images on one of the subsite. He has full control to the complet