Hi Team,
Can you tell me the setting for Automatic Rework Order creation by the system when the product is rejected while confirming the production order.
Samar

Hi,
Pls follow the below mentioned procedure:
1. Create a Reference op set in tcode CA11.
Enter the plant, Description, usage and status
for the ref op set
2. Create a Standard trigger point in CO31.(Ex
Production)
Enter the Trigger Point usage /Group as FERT.
3.Tick the Trigger Point Functions.
4. Enable the indicator create order with Reference .
5.Enter the system status as PCNF.
6.The system will says standard trigger point exists from which you can
select the created Trigger Point (EXx Production)and save.
7. MD02/MD04.
8. Convert the Planned Order into Production Order and Release the order.
9 .Now confirm th ops.
10. For the last op enter the yield and rework qty
and set the status as PCNF.
11. If the status of last op is PCNF then in the
system a POP UP will appear as Activited by
Trigger Point /Create order with reference/order
number/sequence and op number which trigger point
works and enter.
12. Now a rework order will be created.
13. In c003 enter the number which is next to the actual prodn order no.Rework order will be seen.
Hope this helps.
Regards,
Tejas

Similar Messages

  • Automatic rework order creation

    Hi,
    I have 7 operations in routing . at the time of operation level confirmation when I will put quantity in rework system should generate rework order for the rework Qty.I have two different Order types.
    Regards,
    Manoj Jadhav

    Hi,
    Please fallow the below steps for auto rework order.
      1) Create Reference Grp - CA11
      2) Create Std Trigger Point -  CO31
              Select Create Order With Reference & enter system status as PCNF/CNF. Enter parameterfor the selected function as  reference grp & seperate order Type for rework, if available.
    3) Use this trigger point in the opration where you want trigger & select the indicator for  Trigger point used for trigger point functions.
    4) Create the production order.
    5) Do partial/fully confirmation with rework quantity. Then, system should propose to create the rework order quanitity eq to rework quanity.
    Rgd,
    Chetan

  • AUTOMATIC CREATION OF REWORK ORDER

    Hi
    Could any solve my problem?
    Basically i am working in pipe manufacturing unit where we follow discrete manufacturing.
    I have some pipes that been rejected from certain operation and sent for reworking.Now, i want that "A rework order should be created automatically for the same pipes"
    Is it possible? if yes then, what will be procedure & what setting required for the same ?
    Cheers
    Alok

    Hi,
      Rework order can be created automatically by trigger point through change in operation status only.
    I think not possible to create rework order automatically if the material got scrap.
    Regards,
    Dharma

  • Automatic Trigger of Rework Order

    Hi Gurus,
    As a rework process, I know the following
    1) We have to create rework order through CO07, and settlement to be done for original order after confirmation with ref. to Ref. Opn. set.
    2) We can introduce a rework operation in the production order operation view and carry out further process
    3) We can set trigger point in the routing to carry out Rework Process as std. for all the orders, which uses that particular routing.
    Now my requirement is, how automatically  process the rework quantity, when we enter rework quantity in CO11N.
    Pl. let me know the IMG setting.
    Regards,
    Madhava
    Edited by: Madhava K.N on Jul 15, 2009 5:03 PM

    Hi,
    Thanks for the inf.
    With your help, I can create a rework operation for that particular order. But following are my doubts.
    1) You have mentioned that, change to be set * first and then again + What is the significance of assigning twice.
    2) During confirmation, I entered some quantity in yield and some quantity in rework, but in the order display, it has created one more operation as rework, but required quantity as original order quantity, That means, we have to rework entire quantity of the order not the rework quantity entered during co11N.
    Hence this solution holds good for Insert ref. operation set and rework of all quantity.
    My requirement is automatic creation of rework order for the rework quantity. For this
    I have chagned my earlier setting of trigger point - create order with reference and in active I have put 2 with the clue from your answer.
    Now the rework order is generated for the quantity which i have entered in Co11n rework quantity field. But not able to see the order no. Just blindly I displayed the next order no. It worked out.
    Now, I released the rework order and confirmed through co11n.
    I tried to confirm original orderfor rework quantity, it is giving the information as "Up until now only xx pieces confirmed for predecessor operration. Since it is information, i tried to save it, but the  message " total confirmation quantity is not equal to planned confirmation quantity" is displayed.
    Performace assitant gives following message.
    Total confirmation quantity not equal to planned confirmation quantity
    Message no. RU117
    Diagnosis
    There are the following reasons for this message:
    You create a final confirmation. The confirmed quantity for this operation (yield + rework quantity + scrap quantity) is not equal to the planned quantity to be confirmed.
    You create a partial confirmation. The quantity confirmed until now for this operation (yield + rework quantity + scrap quantity) is greater that the planned quantity to be confirmed.
    My yieldrework qtyscrap qty. does not exceed the planned quantity.
    Then I went to MIGO, and posted GR for original order,  but in CO03, it is not showing the del. quantity, even for the partial accepted quantity also.
    Is there any steps for rework order after confirmation?
    Pl. help me.
    Madhava

  • Some querries related to BOM,Rework order

    Hi FRIENDS,
    Really feeling good to being among SAP intellectuals.This is my first thread in community....
    I am working in SAP QM past 2 yrs,and am trying to get some SAP PP knowledge...
    pLz help me out in getting some knowledge......
    a) Whis is it so that rework order is always created without material,it sounds confusing to me.Cant I prepare a standard order for a component say of 100 pcs and then confirm it by 95 pcs and create rew another order with material(same) for 5 pcs..
        By co07,the user can book other component (apart from BOM component of that header) by going to co07---bom tab.
    Can it be stopped....
    b) Another querry is related with BOM....
           Why By product is maintained in negative qty in BOM,Cant get the theory behind it.....
    Plz answer my querries....

    Dear Snehal,
    1.Normally a rework order will be created in order to address the product which does meet the expected quality parameters.
    2.For a rework order which is created through CO07,no GR will be made and only confirmation will be required because
    already the whole product exists as such and this order helps to capture the extra cost spent for correcting the product and
    for settlement.
    3.So for this reason order without material will be created without referring to any particular material or say product and in
    case if you creating a production order with material GR will be made as an automatic process or manual GR.
    4.A byproduct will be maintained in negative quantity because so much of product will be obtained as an output along with the
    main product.In this the GR will be happening for the main product as well the by-product.So the normal components will be
    maintained in +ve quantity which means consuming so much quantity the fianl product is produced and if any component is
    maintained in negative quantity then it indicates that its a by product.
    Check these links to explore more.
    settings for co-product and by-product
    Re: Co product and By Product
    http://sapfunctional.com/PP/Co&BiProducts.htm
    Regards
    Mangalraj.S

  • Automatic production order creation for remaining sales order quantity

    Hi All,
    My requirement is to create automatic production order for a particular material when the available quantity ( Stock in MD04) is less than the sales order / Delivery quantity.Automatic production order should only be created for deficit quantity.
    For example if i have stock of material A 100. I have recieved a sales order for 120 pieces. Now automatic production order should be created for 20 pieces only.
    Any inputs/ suggestions, please let me know.
    Thanks in advance !!
    regards
    Pawan.

    Hi Pawan
    In Material Master MM01 / MM02, you need to maintain 20 in MRP3 --> Planning --> Strategy Group.
    If you maintain this, items can be produced only against sale order you are creating.
    Dont forget to reward if this helps you.
    Regards
    G. Lakshmipathi

  • Automatic production order creation and confirmation

    Dear all,
    I am in a situation where i have to configure the SAP system in the following ways:
    1. From the planned orders automatically production order should be created today for the next day production and the end user will re-declare the quantity if there are any changes in the production order.
    2. If there are no re declarations to be done SAP should automatically release production order and save it.
    3. After the goods are produced the confirmation of the order should happen automatically from the measuring points.
    4. In the order confirmation, the storage location for goods issue should be automatically captured from the goods issue slip.
    5.After the confirmation of the order the goods receipt should happen automatically.
    Please suggest me whether these are possible in SAP or not.  If yes please tell me the procedure.

    HI,
    I hope this will give you the clear picture
    actually my scenario is:
    Finished good= x
    work centers involved = WC1, WC2.
    HERE BOTH THE WORK CENTERS ARE IDENTICAL, INPUTS ARE SAME AND OUTPUT IS THE FINISHED GOOD "X"  FOR BOTH THE WORK CENTERS.
    I HAVE A ROUTING FOR THE FINISHED GOOD "X" WITH TWO GROUP COUNTERS AS (1)WC1 AND (2) WC2
    When i create plan in md61 for 1 month and when i do mrp run in md02 it will create the planned orders and we can see the stock requirements in md04 and when we double click on the planned order we can convert them into production orders.
    But my users requirement is, he want to run the mrp in md01 and after that automatically each day the production order should be created.
    example with the above work centers and materials:-
    i have done the mrp run for "x" for November and December months
    i want to produce "x" of 200 kg on 30.11.2011.
    so SAP should generate production order for WC1 AS 100KG AND WC2 AS 100KG on 29.11.2011 at 5 pm automatically  and the user will release the order.
    similar example:-
    i have done the mrp run for "x" for November and December months
    i want to produce "x" of 400 kg on 03.12.2011.
    so SAP should generate production order FOR WC1 AS 200KG AND WC2 AS 200KG on 02.12.2011 at 5 pm automatically and the user will release the order.
    Please suggest me how to do the configure settings for my users requirement.
    Thanks,
    Aravind.C

  • Error message when releasing a rework order

    Dear Experts
    I try to create a Rework production order  using co07 but I am unable becase when I click on the Release button, I get this error message " order type pp07, no checking rule maintained for operation. Release of order not possible". what steps do I take to solve thisproblem?

    Dear Vincent,
    1) Go to OPJK, here for ur plant & Order type do settings for Business function 1 & 2
    2) or else Copy any Std Rework order in OPJK & Give ur plant & order type & save
    Then check the result
    Regards
    Madhu Kumar

  • Automatic Purchase Order upon Goods Receipt 101/161

    Hi Guys,
    Hope everyone is well. I would like to know in as simple terms as possible, what is the use of Automatic Purchase Order upon Goods Receipt mvt 101 or 161. Can someone explain to me the purpose of this? or applicable in which type of business scenario?
    Because i think, if it is upon Goods Issue, then it is understandable, you would want to top up the stocks, but upon GR? Why?
    This is a non configuration question, just a business process question..

    >
    Nazrin84 wrote:
    > Hi Guys,
    >
    > Hope everyone is well. I would like to know in as simple terms as possible, what is the use of Automatic Purchase Order upon Goods Receipt mvt 101 or 161. Can someone explain to me the purpose of this? or applicable in which type of business scenario?
    >
    > Because i think, if it is upon Goods Issue, then it is understandable, you would want to top up the stocks, but upon GR? Why?
    > This is a non configuration question, just a business process question..
    This process is used in case of emergency when stock is required in the plant and we dont have time to first create PO and then get its approval and follow the normal process. In the case of emergency, we tell the vendor to deliver the material and on receipt of this material we take it into the system through GR and the corresponding PO is automatically generated.
    Usually this is option available in system, but it depends on the clients requirement whether they want this option available to end users or not. Mostly our clients prefer not to have this option enabled, as this way can lead to irregularities by the users.
    So they prefer to follow the normal process, but this process for above scenario is followed on war footings that way the GR takes place immediately when Goods are received.

  • Automatic Transfer Order Creation

    Hi All,
    Scenario: When there is GR from Production order into WM Storage Location I have all settings so that Inbound Delivery HU Mvt is created also Material is getting packed into HU in Backend automatically as soon as Delivery is created.
    My Requirement is
    that I want to create Automatic transfer Order for this Inbound Delivery created. I have gone thru STD SAP Docuemnts which tells auto TO creatoin for TRs. But I need to create Auto TO for Inbound Delivery not for TR (of course in backend)
    So that in the next step the TO can Be confirmed manually.
    Can anyone plz help me << Moderator message - Everyone's problem is important >>.
    Thanks in Advance
    Edited by: Rob Burbank on Nov 10, 2010 3:57 PM

    Hi,
    To create automatic TO in the back grond w.r.t to inbound document is not possible in WM , i belive.
    if you dont want to use TR ,then do the following setting in customisation
    SPRO- LE-WM-interfaces-activate automatic to creation -movement type assign- keep TR column blank and in create TO immediatly column use x ( Call up transaction "Create TO for material document")
    Thanks & Regards
    Om

  • What are the settings for  rework order  quality inspection

    HI,
    Iam doing production order confirmation at the GR time some oprations are rejected.that operations i want too rework order CO07 process without GR ,i want to Quality inspection in REWork order.
    What are the settings for rework order Quality inspection?

    Refer beautiful document
    http://wiki.sdn.sap.com/wiki/display/HOME/ReworkInProduction

  • Problem in settlement of rework order

    Hi
      I have raised a production order and settled all the products in the order. But in quality inspection i have cleared only some quantity and made some quantity rework. I have raised a rework order for the same and settled the rework order.But the quantity is not settled to the main production order.Where is the problem in the rework order
    Regards,
    PradeepM.

    Hi Pradeep,
    Are you expecting
    1. the rework cost in the rework order to be settled to the parent order or
    2. the confirmed quantity in the rework order to be added to the parent order.
    Up to my knowIedge I dont think the 2nd point will happen.
    Let us confirm with other Experts opinion.
    BR,
    UK

  • Error while Goods receipt for rework order.

    Dear all,
    I have created one Rework order through TC CO07.
    While doing Goods Receipt it gives Error Msg as following.
    "No valid order items exist for order 200000203"
    Message no. C6008
    Regards
    Atul

    Dear,
    There is only confirmation CO11N for the rework order. And good reciept MB31 for main order.
    There is no GR for rework order. Once you confirm rework order,you need to do the GR for the balance qty of  main order or parent order.
    And you need to priliminary settlement of rework order first in CO8B, hence the cost will be moved to parent order, then you settle parent order in KO88.
    Hope clear to you.
    Regards,
    R.brahmankar

  • Automatic Sales Order Creation from PO in B1

    Hi,
    I have this scenario. Purchase order is created in SAP B1 (Business One) which triggers automatic Sales Order creation in SAP ECC 6.0.
    The requirement:
    For the combination of PO number and Sold to party there should be only one sales order created.
    The problem:
    Sometimes for the same PO duplicate Sales orders(sometimes 3,4) are getting created in ECC.
    Possible causes:
    Probably no validations in the interface.
    Question:
    1. First of all, is it an SD issue or PI (process integration) issue.
    2. If it is an SD issue, as a functional consultant what / where can we do to prevent this.
    Thanks.
    Edited by: SAP SD_Newbie on Oct 20, 2011 6:59 PM
    Edited by: SAP SD_Newbie on Oct 20, 2011 6:59 PM
    How do I move this to "ERP - Sales and Distribution (SD) General", because this question is not just related to "ERP SD Sales" but SD in general. Isn't there an option for the users to a question from one forum to another.

    1. First of all, is it an SD issue or PI (process integration) issue.
    - May be PI, or SD or both. I am not sure about the integration mechanism/program so I am not able to pinpoint.
    2. If it is an SD issue, as a functional consultant what / where can we do to prevent this.
    In t.code VOV8, go to the sales document type. Select value A in the field, check Purchase order Number. Then go to t.code OVAH, there make the message number V4 115 as error message. This will not allow the creation of the sales order, if the Purchase order number duplicates. I assume in your process, the purchase order number is populated in the PO number field of the sales order overview screen.
    Regards,

  • Automatic Purchase Order Creation

    Dear All,
    I would like to test the scenario of automatic creation of PO. I have already checked the Auto PO indicator in material master and vendor master record. Info Record and Source list also exist. In MRP view i have maintained manual reorder point planning.
    When I run the MD02, system creates the Pur. Req.  but automatic PO generation doesn't exist. Please let me know what else I need to check or there is any more setting, which I have to do.
    Thanks and Regards,
    Vineet

    Dear Vineet,
    In SAP, the automatic Purchase Order(PO) creation is possible via ME59- which via Purchase Requisitions. I would like to remind you, the automatic PO creation is possible only if Purchase requisition exists with required pre-requisites.
    Not possible to create the PO from Requirements. I mean to say not possible thru MRP. Where MRP is a requirement planning, order proposal. Order placement is an another process, which can be automated thru ME59- when PR exists.
    Hope this helps.
    Njoy SAP
    -Saravanaganesh

Maybe you are looking for