Automatic settlement rules for AUC

Hi.
I want to create the automatic settlement rules for AUC settlement instead of entering the setllement rules manually.
can anyone provide me the configuration steps required for automatic settlement rules.
Regards,
Padmavathi

Hi ,
Path: Spro - controlling - Internal orders - Actual postings - Settlement - Automatic generation of settlement rules
Can anyone please provide me the details how to configure in this path and in which scenario is it useful.
Regards,
Padmavathi

Similar Messages

  • Settlement rule for AUC

    Dear SAP gurus,
    In AIAB, I have assigned the settlement rule for AUC asset id. However I am not able to see the settlement rule assigned in  As03. Is there any report

    Hi,
    you can see the settlement rule only in AIAB.
    regards Bernhard
    Edited by: Bernhard Kirchner on Jun 15, 2010 12:52 PM

  • Settlement rule for AUC not automatically generated

    Hi Experts,
    I am working on a capital project scenario where I have configured the investment profile and assigned this to the project profile.  I have also configured the settlement profile and allocation structure for settlement to FXA.
    On release of the WBS element the AUC is automatically created.
    I have posted costs to the WBS element.
    When I run settlement in test mode, using CJ88 the details show the sender as the WBS element and the reciever as the AUC, and the amount = the cost posted to the WBS element in the posting period, (as expected)
    However, (now my problem)
    When I run settlement in "update" mode the settlement shows 1 settlement however when I drill down to see the sender or reciever details are blank.  There are alno no accouting documents and a settlement rule does not display for the WBS element.  There are no error messages even though the settlement has not taken effect.
    Please can anyone advise on the possible cause of this error.  One further  point the document type on the settlement profile is configured as "SA"  GL Account Document.
    Thanks in advance.
    Ian

    hi,
    Go to Settlement rule (CJ02),where enter the WBS .here go to Extra in the menu bar of that WBS ,under Asset under construction ckeck the box of Historiy....something like that .
    Regards
    Ricky

  • Automatic settlement rule for receiver 'Fixed asset' (with out IM)

    Hi Experts
    I am working with project settlement to a fixed asset.
    I have defined a selttlement profile in which, FXA is the only valid receiver.
    Please note that we do not use Investment managent and hence no automatic AUC.The predefined asset to be used for settlement.
    In this situation i am unable to generate settlement rule automatically as like the case with CTR.
    The below message is experienced.
    "Enter a distribution rule for Asset without a validity limit"
    However i have manually maintained the settlement rule with specification of appropriate asset as receiver and settled.
    In this scenario, how to ensure that the settlement rule is automatically generated, any where can we refer the fixed asset?
    warm regards
    ramSiva

    Hi,
    Settlement rule cannot be automatically maintsined, you have to maintain manually, for example if you want to settle to fixed asset, how the system know to which fixed asset it should settle. You have to maintain settlement parameter manually.
    Regards,
    Sreekanth

  • Error while attaching settlement rule for AuC asset

    Getting error "The share to be settled in rule 001 is not unique"  "Enter a unique number (001) (view: Actual settlement) "  when trying to attach a settlement receiver in transaction AIAB  - where to view the duplication of rules, and where to delete the rules ?

    Hello
    Check the transfer variant / receiving asset / transaction type.
    Check all rules again.
    Reg

  • Maintain settlement rule for AUC

    I am getting following error in T.code AIAB. 'You have chosen a depreciation area, which does not carry the depreciation data from table COEPBR.'
    Anyinputs to resolve would be appreciated.
    Thanks in anticipation.
    Regards,
    Prasad

    HI,
    Assign depreciation key 000 (no dep) for Asset Under Construction - Asset Class.
    Regards,
    satish

  • Settlement rule for Asset Under Construction not automatically generated.

    Hi Experts,
    I am working on a capital project scenario where in i configured the SAP IM and SAP PS module. i am able to create AUC at the WBS level on project release,but i am not able to generate the settlement rule for AUC automatically.
    Please suggest as to what i am missing to generate settlement rule for AUC automatically.
    Thanks,
    shiv

    i think for automatically AUC to be generated, u need to create investment profile in OITA in that u have to tick mange AUC in investment measure. & select settlement for summary settlement.
    This investment profile u need to specify in Project Profile OPSA.
    do this setting & let me know whts happen?
    ok best of luck.
    Regards,
    ANSAR

  • Automatic Generation of Settlement Rules for PM order

    Hi All,
    I am doing a maintenance orders settlement and I have the fallowing issue:
    My client has 2 types of equipment, namely vehicles and industrial equipment. Both have particular rules.
    For vehicles, we need to control all cost by an internal order
    Industrial equipment costs will be control by cost center.
    So, cost center is maintained for industrial equipment, and Settlement Order for vehicle equipment.
    I have a unique order type for which in Settlement profile I have entered Order and Cost Center as 'Settlement Optional' and default object type as CTR.
    When I create a PM order for vehicle, system cannot generate automatically the settlement rule, because in order type I have entered default object type as CTR and in equipment I just have the Settlement Order.
    But if I create a PM order for industrial equipment system create automatically the settlement rule, because cost center is maintained for industrial equipment and order type has default object type as CTR.
    In the allocation structure I have a receiver category for CTR and ORD.
    So, Could you help me how to generate automatically settlement rule for both cases without 2 order types?
    Thanks & regards,
    Hélder Nunes

    hi
    i think it is not possible to generate settlement rule based on equipment ,if you have specified the default settlement category in IMG ,it will be generated .
    check with your technical team whether user exit IWO10027 can be mapped
    regards
    thyagarajan

  • Automatic Creation of Settlement Rule for Maintenance Order

    Hi,
    While doing TECO for Maintenance Order, its asking for Settlement Rule. IF I click settlement rule, message is coming as Maintain Settlement Profile with options like With Default, Without Default & Cancel.
    I have maintained the Cost center in Equipment Master. Also I maintained Cost Center as Default Settlement receiver.
    Also I have gone through setting in Automatic Creation of Settlement Rule under Controlling Category.
    But I couldnt understand that. Can you please tell what are the steps to be done?
    Regards,
    Maheswaran.

    Hi,
    Please check the indicatorsin Actual cost/cost sales  and Valid recevivers in settlement profile.
    If for cost center : 1 settlement optional is maintained in valid recevivers and also for order
    and in actual cost/ cost sales: indicator to be settled in full is selected.
    Also check Allocation structure too if you have assigned the valid allocation structure.
    **check if you have assigned the valid settlement profile to order types.
    *****Most important after doing all these settings you need to create new order. for same order you will not get the automatic settlement rule
    Hope this helps.
    Regards,
    PMAddi

  • Automatic Settlement rules generation

    PS Experts
    I need to have automatic settlement rule generation for WBS elements.
    I do have all the config (PS & IM) in place and when i release my WBS element then AUC is automatically created and no settlement rules are generated at this point.
    But when i create FINAL ASSET, then the settlement rules are generated automatically with final asset as the receiver. When i run my final settlement (CJ88) then the settlement rule is updated with AUC & Final asset.
    My question is do i need to have Investment profile to have automatic creation of settlement rules.
    What if i don't want to activate IM and still have automatic settlement rule generation?
    Edited by: Raj M on Apr 17, 2008 8:49 PM

    Hi,
    For automtic settlement rule generation folloowing steps need to be followed.
    1. Determine Strategy for Settlement Rule
    In this there will be settings for settlement rule where we define the recevier cost object after project settlement.
    This strategy will be assigned to project profile
    2. Generate Settlement
    CJB2 transaction need to be run for generation settlement for the WBSE.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Automate settlement rule

    How to  configure the settlement rules to be automatically created when a new project is saved such as for the AUC settlement or Requesting Cost Center?

    Automatic settlement rule work for the projects where object class is other than INVESTMENT.
    You have to configure  in SPRO IMG->>>PS->>>Costs->>>Automatic and Periodic Allocations->>> Settlement->>> Settlement Rule for WBSE ->>> Determine Strategy for Settlement Rule.
    Here you can mention your default settlement receiver as requesting cost center / responsible cost center or you can enter a settlement rule for level 1 WBS element and then copy this to all lower levels.
    Assign this to Project profile in OPSA transaction under the controlling area tab Settmt rule strat. field.
    Then you have to execute the transaction CJB1 / CJB2 for generating the settlement rule automatically to all the WBS elements.
    You can search the forum, <link removed>
    you can also refer to the online help. <link removed>
    Incase of INVESTMENT object class projects, the settlement rule is automatically created by the system when you execute the settlement for project first time, the receiver will be the respective AUC.
    Praveen
    Edited by: b praveen savan on Sep 14, 2010 6:27 PM
    Edited by: Virendra Pal on Sep 15, 2010 4:56 PM
    This time I am not deleting the post and do not bank on second chances.

  • Capital Project Settlement Rule for lower WBS

    Hello,
    At my present client, for Investment projects the client want to settle top level WBS to AUC and capitalise it. So ideally the cost from lower level WBS should flow to top WBS. I am using substitution to remove investment profile from lower WBS.My concern is how do I auto populate the settlement rule for lower WBS to top WBS. I am aware about settlement strategy and OSS note 211324 (however dont want to implement this note)
    The appraoch I am looking for is using "WBS_SETTLEMENT_RULE' BAdI . However this BADI calls for strategy and I could not maintain the required strategy (settlement to top WBS). Is there some BADI/Function module available which can be called for updating the settlement rules on lower WBS while saving or Release ? Can I make use of exits in Substitution?
    Please let me know your opinions.
    Thanks
    Sarang

    Thanks Virendra. I agrree the only approach is development. But I need to give inputs to my developer.
    We tried with BADI "WBS_SETTLEMENT_RULE" but it didnt work as it calls strategy in configuration.
    So I am checking for some other options for e.g "WORKBREAKDOWN_UPDATE" which is called during save or Fn modules K_SETTLEMENT_RULE_FILL or K_SETTLEMENT_RULE_SAVE which I can use. This is a client requirement to create AUC only at top level n all cost to be rolled up to superior WBS n then settle to AUC.
    The other option I was thinking is of using exits thru substitution.
    What will be the best approach?
    Thanks
    Sarang

  • Error-M2O-Settlement rule for assembly order for item...could not be genera

    Hi,
    When I am creating Sales Order (VA01) for M2O, I am able to do the costing and copy the EK02 condition type. I have verified the the incompletion log, it indicates that document is complete.
    But while saving the sales order, the below error message is displaed:
    Settlement rule for assembly order for item 000010 could not be generated. Should the order still be saved?
                    Yes/No
    1. If No is choosen the following error message is displayed
           Error when processing Production order
          Error when processing Production order
          Message no. V1380
          Diagnosis
            A technical error has occurred. On calling up the assembly interface, exception 5 was triggered. The exceptions have the  following meanings:
    1 = External block,  2 = General error,  3 = Insufficient data for the interface,  4 = Order was not found, 5 = Update has been rejected, 6 = Final document number for Production order is not issued.  Procedure: Inform your system administrator.
    2. If Yes is choosen, it is creating Production Order without settlement rule. Able to perform GI & Gr. If I try to enter settelement rule (Settlement receiver SDI - Sales document item) in production order (CO02), the belwo error message is displayed
    "Distribution rule for Sales document item can only be created automatically Message no. KD063"
    We are using the requierement class with below details:
    Reqmts class: ZSO- for M2O
    AAC = E, Valuation = A, Settlement profile =SD1, RAKey = 000004, Assembly type = 3.
    Settlement profile contain:
    Allocation structure, PA structure, Default object type = SDI. Valid receivers: Optional -Sales Order / Prof. seg.
    If I make the Valuation field as blank in Reqmts class, there is no error while creating Sales order. And also Settelemnt rule with sales document item as receiver is successfully creating for the production order. Since the Valuation is blank in requirement class, it is Non valuated Sales order stock. All GIs & GR are non valuated
    The business requirement is it should be valuated sales order stock and the production varinaces has to be settled to Sales order. Then Sales order has to be settled to COPA.
    Need your valuable inputs to meet this requirement.
    Let me know if you need any further details.
    Thanks in advance.
    Regards,
    ADI

    Dear SAP PP Consultant ,
    What is the strategy group you are maintained in the material master ?

  • Automatic settlement rule creation

    Hello Guru's,
    I have a scenario of capital proejcts. Were I create Assets with the help of Investment profile at the top(1st level) WBS element. Now my requirment is the cost of the second level WBS should be rolled upto top level WBS element. To do this I have to manually create settlement rule for all second level WBS to settle at top level. I have to create this rule automatically throught CBJ2 tcode.
    As per SAP Note 211324 I have  Implemented the modification. Now I have Insert value '5' with short text 'Superior WBS element'. Also have assign the strategy to Acct. Assign element. This strategy is also assigned to settlement profile. Also have assigned this settleemnt profile to project profile.
    Now, when i run CJB2 tcode for my project the system issues me an error :-
    Error(s) during creation of settlement rule
    Message no. ORB509
    Diagnosis
    Errors occurred during the check on settlement receivers.
    System Response
    Processing stopped.
    Procedure
    Check whether the:
    Specific receiver Account assignment e actually exists
    Settlement profile ZPI03 permits account assignment to the specified receiver
    Please throw some light on this error
    Regards,
    Tushar

    Thanks Virendra,
    Thanks for your reply but tell me after the implementation of note do I need to implement BADI also as in past for some forums you have mentioned???
    Regards,
    Tushar

  • Creation of settlement rules for WBS element

    Hi,
    Iam having problem when creating the settlement rules for WBS elements. The business goes like this.
    We have XI interface which creates the Idocs and an inbound program(customized) to process the Idocs. When the Inbound program is run the WBS elements are created and settlement rules are created for the WBS elements. The inbound program is run automatically thru batch job.
    First time when the Idocs are processed about 95% of the WBS elements have settlement rules created and for other 5% settlement rules are not created. The Idoc is in status 64. I tried reprocessing the Idoc and then the settlement rules are getting created succussfully. The problem is Iam not able to find why the Inbound program is not processing succusfully when its run first time but works when reprocessed.
    I appreciate if anyone can send their views.
    Best Regards
    SK

    Hi!
    You might set the processing to check not only once the relevant IDocs, but more times...
    Check out these programs, and set them into a batch job periodically...
    RBDMANI2
    RBDAPP01
    Regards
    Tamá

Maybe you are looking for

  • Please tell me there is a way to remove the slide that cuts up the pictures

    Ok, your slideshow, photo album template in iphoto is THE BOMB.. so cool! But, someone thought, hey lets put one that cuts all the photos up and almost surely cuts the important part of whatever the original photo was.. grr? It wouldn't be so bad, if

  • Access iphoto 08 file on shared storage device from multiple machines

    I recently installed ilife 08 on both an imac and macbook. Previously (iphoto 06), both devices accessed the iphoto library on a shared storage device without any problems. After the upgrade, my imac is able to view thelibrary but my macbook (the sec

  • Can Absorption costing transfer in COPA?

    Hi All I would appreciate your help. Please provide me details explanation over. 1) Can we transfer Absorption Costing in COPA? 2) What is the procedure? ( It is my request please use full form rather than short words).

  • Adobe Form Server 5.1 Memory Problems

    FSService.exe increases memory when serving forms but never releases it. The forms are of the Form Server type and they have several calls to an InHouse COM Component. The COM Component was developed to encapsulate the calls to our Legacy systems via

  • Dynamic portal Themes

    Hello All, I just wanted to know if it is possible to changes the portal themes based on roles during runtime. Thanks