Availability check for Sales order

Hi Experts,
I have material say 100199 in which I maintain In house production time as 10 days.
Now I have to create Sales Offer for this material and system check availabity and give delivery date for Offer from Inhouse production time maintained.
Problem is this In house production time is independent of Order quantity so system will give same delivery date irrespective of quantity in sales order.
I want system should propose me delivery shedule from master data maintain
i.e if order is of 120 qty then system should propose and for 30 lot i requires 3 days to manufacture.Order creation date is 09/12/07
30   12/12/07
30   15/12/07
30   18/12/07
How I can achive this in SAP?

Hi Lalit,
You can give Lot size dependent In house Production stimes in Work Scheduling View of Material Master.  You can do it in MM02. Wish this solves your problem.
Regards
Krishna

Similar Messages

  • Availability check for sales order stock

    Hi,
    We use sales order stock in sales order which creates purchase requisition automatically.Movement types for GR 101E, for GI 601E. Material master data has on MRP2 view as GR processing time 2 days for example. I create sales order with requested delivery date today.After saving SO, PR is created and I create PO with delivery date today and post goods receipt document for today. System gives as confirmation date today + 2 days. although the material is in stock.
    We use also project stock in sales order which creates purchase requisition automatically.Movement types for GR 101Q, for GI 601Q.I run the same scenario for the same material. As soon as I create the purchase order system confirms the open quantity in sales order for today. (Scope of availability check is the same for both sales orders and includes PO)
    What can be the reason?
    Thanks

    Hi Murat,
    i guess the problem is with the 'Check without RLT' indicator' in Availability check control. For the MTO (checking rule AE) i guess this indicator is not set but for the Project systems (Checking rule PS) this indicator is set. This makes the difference. Do the changes as desired in transaction OVZ9.
    Please check and revert back if you are still facing the same problem.
    regards,
    Kathir

  • Availibility check for sales orders created simultaneously

    Hi SD experts,
    When a sales order is being created with an item "A", while a second sales order is being created too, at the same time, with the same item "A", the system can't carry out the availibilty check.
    It displays the following message : "The material A (plant M500) in item 000010 which you entered for processing is blocked for another transaction. The system is therefore unable to carry out either the availability check or the transfer of requirements."                           
    This is quite logic... But for example for a call center where the operators create orders simultaneously how can we make it possible??
    Any suggestions please ?
    Thank you,
    Bahia.

    Hi there,
    In SPRO -> SD --> Basic functions --> Availability check & TOR --> Avaliability check --> Avaliability with ATP --> Define material block for other users.
    Here you make the settings for different availability check types 02 for individual requirements etc. If you check the field Block, system will block the material for other remaining sales orders if availability check is being carried for one sales order. It is set at plant level. If same material is available at other plants, it will be available there.
    Regards,
    Sivanand

  • Availability check of sales order in planning strategy 40

    Dear friends,
    Kindly help me this query:
    From online SAP help in Demand Management, it said in planning strategy 40:
    "An accurate availability check is performed according to ATP (available to promise) logic during sales order processing. The system checks whether sufficient planned independent requirements have been planned to cover the sales order....  If there is insufficient coverage of components (the sales order quantities exceed the planned independent requirement quantities), the sales orders cannot be confirmed"
    According to above paragraph, I think that availability check of sales order is carried out against PIR, if PIR quantity cannot cover sales order quantity then order will not be confirmed, it also means stock on-hand will not be included in availability check. However, my testing reveal a different conclusion: sales order is confirmed against stock on-hand, not PIR. My questions are:
    1/ in planning strategy 40, how does system carry out availability check for sales order?
    2/ how to interpret above help from SAP?
    I got that help from this link: http://help.sap.com/saphelp_erp60_sp/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm
    Many thanks for your clear answers.
    Regards,
    Duc.

    Dear duc pb ,
    In 40 its only ATP that works.
    you can do another test ,
    Create PIR 15 quantity.
    Create a stock of 10 quantity.
    and now create a sales order firszt of quantity 30, as both of the above after combining cant fullfill this demand, save order run MRP.
    system will create orders against PIR (15)  and remainibnbg quantity of sales order (5)
    run one more test, by creating PIR 15 quantity , no stock and a sales order of with quantity 10.
    share your findings.
    Thanks
    Ritesh

  • Availability check in sales order for DIEN materials.

    Hello,
    Is it possible to make availability check in sales orders for a service material e.g.: type DIEN? How can i customize it?

    The DIEN material type is not stock managed, so it does not make sense to check the availability. If you need to do something similar you could use material type UNBW, this material is quantity managed but not valuated, so maybe this can help you !
    Regards
    Roberto Mazzali

  • Availability check at Sales Order Create

    Dear Experts,
    I want to do availability check at sales order creation stage (VA01). My requirement is, the system should check the sales order line qty against the unrestricted stock. And if sufficient stocks not available it should prompt an error message.
    In more detail; unrestricted stock of material X is 100 PCs. I put a sales order for the same material for 101 PCs. Then systems should block me from saving the order.
    Can some please provide me detailed step-by-step action for configuration of above scenario. Thanks in advance for your support
    Regards,
    Ramindu

    HI,
    User exits in program FV45VFZZ
    USEREXIT_ADD_FIELD_TO_HEADER
    USEREXIT_ADD_FIELD_TO_LINE
    User exits in program FV45VFZY
    USEREXIT_DELIVERY_GROUPS
    USEREXIT_MVERF_INIT
    USEREXIT_QUOTA_KEY_VALUE
    User exits in program RV03VFZZ
    USEREXIT_AVAILABILITY_IN
    USEREXIT_AVAILABILITY_OUT
    USEREXIT_DARA_REFRESH
    USEREXIT_PLANT_SELECTION
    Check these user exits also very helpful to you.
    Regards,
    kishore.

  • Changing Availability Checks in Sales orders

    hi there,
    Can i easily change the Availability Check in a sales order?
    i have 5 sales orde rtypes, and I sometimes want to change the Availability Check, how can i manage this?
    thanks

    There are three types of availability checks
    1. Availability Check with ATP Logic or Against Planning
    2. Availability Check Against Product Allocation
    3. Rule-based Availability Check
    For ATP logic, the Checking group and Checking rule combination determines the availability check parameters. The checking group is maintained in the material master, and not to Sales order type. Hence you can control by having different groups attached to different materials.
    If you have Advanced Planner Optimiser (APO) then you can use the Rule based availability check. You can attach a Business transaction to a Sales document type and thus control the availability check in sales order level also.
    Refer the below extracts:
    <b>Define business transaction</b>
    Path : spro -- img -- sd -- BF -- Av chk and TOR --- Rule based availabilty check
    In this step you can define the business transactions. These transactions must also be available in the APO planning system. Here the availability check control is carried out for the transactions.You can find the business transactions in the APO planning system (Field BPROC) under:
    Global ATP -> Settings -> Rule-based ATP -> Conditions -> Assign rule strategy.
    <b>Assign business transaction to sales order type</b> t code VOV8
    In this IMG activity, you assign the actions you defined previously to the order types. This activates the availability check settings for this order type, that were maintained in the APO planning system.
    Regards,

  • Disable Availability Check on Sales Order  But Activate on Outbound Delv

    Greetings all experts !
    Currently, there's a new request to create a new processes whereby during the sales order creation, no availability check will be in place but material will still be posted to production planning ( TOR ).
    Availability check instead should be activated  during the creation of outbound delivery.
    I have already configured in such a way that the relevant sch line item ( VOV6 ) - availability check is unchecked and TOR is checked.
    But during creation of sales order, availability check is still in place for material specified.
    I have check on the necessary requirement class and requirement type settings. Fyi, requirement class used - availability check is ticked. Could this be the reason even though i have disabled availability check on sch line ?
    I have tried to untick the availability check setting in requirement class  ( OVZG ), and while this can disable the availability check in Sales order, but that configuration will also disable availability check in outbound delivery.
    My queries :
    1 ) What are the configurations that I need to look into to cater to the above request. To disable availabilty in sales order but instead, run availability in outbound delivery ?
    2 ) Is there any way I can disable the availability check on based on sales order type using userexit or function module ?
    3 ) Is there any additional function module/bapi/userexit that i can implement to force outbound delivery to run availability check ?
    My apologies for such lenghty message here but really really need some valuable feedback here as I'm totally at lost with the new requirement for now.
    Many thanks in advance.
    Warmest Regards,
    Edie O

    In SPRO
    goto SD>Schedule line>Define schedule line categories
    here check if the schedule line category associated with your mentioned order has a flag ticked for Availability.
    Availability check for sales
    You must carry out an availability check for the following transaction.
    The indicator is determined as a proposal in conjunction with the respective requirements type. It can be changed in individual shipping transactions. However, only one restriction is effective.
    Example
    You do not set an indicator for maintaining the requirements type. In this case, no availability check is carried out. This is independent of the selection in the respective transaction.
    You set an indicator for maintaining the requirements type. In this case you can decide whether or not you require an availability check for the relevant transaction.
    reward points if it helps
    regards
    Biju

  • User exit in ATP Check for sales Order to trigger notification

    Hi All
    please let me  know is there any user exit after ATP check or in ATP check for sales order to trigger a notication mail.
    Regards
    Kishore

    Hi,
    User Exits For Availability Check are given below:-
    The user exits named here are planned for projects that are to be carried out in agreement with SAP development as they may only be used in consultation with SAP.
    USEREXIT_PLANT_SELECTION in program RV03VFZZ is an exception to this rule (see below).
    User exits in program FV45VFZZ
    USEREXIT_ADD_FIELD_TO_HEADER
    USEREXIT_ADD_FIELD_TO_LINE
    User exits in program FV45VFZY
    USEREXIT_DELIVERY_GROUPS
    USEREXIT_MVERF_INIT
    USEREXIT_QUOTA_KEY_VALUE
    User exits in program RV03VFZZ
    USEREXIT_AVAILABILITY_IN
    USEREXIT_AVAILABILITY_OUT
    USEREXIT_DARA_REFRESH
    USEREXIT_PLANT_SELECTION
    This user exit is used to adjust the flow during plant transfer. A list of permitted plants, where this material is created, is determined and checked in the standard R/3 delivery. A dialog box appears where you can select the plants. The user exits allow you to modify the plant table so that plant selection takes place in advance for every flagged selection and a dialog box becomes unnecessary.
    regards
    Vivek.

  • Material availability  check for production order

    Hello,
    Is there any functional module to check the material availability of production order. So that it can be used in developments.
    Regards,
    Ganesh

    Hi,
    Following are the available Function Modules for avaibility checks in Production orders,
    BAPI_PRODORD_CHECK_MAT_AVAIL -  BAPI: Execute Material Availability Check for Production Orders
    And for Process Orders,
    BAPI_PROCORD_CHECK_MAT_AVAIL - BAPI: Execute Material Availability Check for Process Orders
    Regards,
    Dhaval

  • Bapi or Function Module to do the availability check for Planned Orders

    Hi all,
    I need a Bapi or a Function Module to do the availability check for a Planned Orders. Anyone knows how?
    I will use it in an Exit.
    Thanks in advance
    Points will be given

    I think I found it.
    If anyone is searching for it too, we will use these one:
    CO_ZA_AVAIL_CHK_ORDER_MULTI

  • Availability check on Sales order creation

    Dear Gurus,
    I'm trying to set the availablity check on Sales order creation VA01. I need to do this on saving the order. it there an SPRO for this. please help me out on this occation.
    many thanks..

    Hi
    If there is a stock of 1000 in unrestricted and if you have included sales requirements in OVZ9 (made a tick sales requirements in inward and outward movement) then if you create a order customer X with 100 quantities of that same material stock will be reserved for that customer X with 100 quantities
    But if you check in MMBE there wont be any reduction still it will be 1000 only
    If that order is delivered and pgi done then only In MMBE stocks will become 900
    To have a very proper reservation for that customer it is better to go to  t code MB1B movement type 412 E and that will reserve stocks for him with proper material document(reserving for sales order)
    If you do that unrestricted becomes 900 and sales order stocks become 100 in MMBE
    In case 1 there is chance of your 100 quantities can be reallocated to another customer thro back order processing
    In case 2 it is not possible it will be for that order only
    Or if you create delivery and dont do PGI then stocks will be reserved for that delivery
    But to have stocks reduced from MMBE you have to do PGI
    Regards
    Raja

  • ATP Check for Sales Order

    Hi Friends,
    I have a requirement in which I want to have ATP on material X, but if the quantity is not in stock for X, system should check for ATP on Y, which can be similar to material X.
    How to achieve this and further make relationship between X & Y ?
    Please advise.
    Regards,
    Harsh

    Hi Harsha,
    we can fullfill this requirment by using Material determination
    In Material determination Record
    normally we are maintaining for A give B instead of putting like this maintain record like this For A give A after that in additional data maintain more material like B,C etc..
    And maintain availability check for every material...
    then u r problem will solve..
    in this item category determination is
    OR NORM PREL        TAX     CX
    OR NORM PSHP TAX TAPS  PP
    like this u need to maintain determination then u will get..
    i hope ur problem will solve...PLZ Reward
    Regards
    Durga Prasad

  • New calculation for availability check in sales order

    Hi there,
    When a sales order date and hour are changed the system doesn't calculate the new availability date, it maintains the initial one. Does anybody knows if it's possible to calculate it automatically?
    Thank you!!

    Hi,
    I have a doubt..why system should perform ATP check for labour?
    I am assuming because you have mentioned hours.Secondly which date you are changing the requested delivery date?
    Kindly clarify the doubt.
    Regards,
    Amrish Purohit

  • Note messages at the time of availability check in sales order entry form

    Hello Friends,
    Im getting the following note messages at the time of availability check in the sales order entry form.
    ATP Process resulted in no data
    User defined exception in package OE_SCHEDULE_UTIL Procedure Load_Results_from_rec
    User defined exception in package OE_SCHEDULE_UTIL Procedure Load_Results_from_tbl
    After this when we book the order, the order line status becomes 'Booked' and does not change to 'Awaiting Shipping'
    As a result of which im not able to proceed ahead with the rest of the order to cash cycle.
    Can somebody please guide me in resolving this error.
    We don't intend to use ATP as the client's business process is such that they maintain adequate inventory balances.
    Regards
    Anil Wadhwa

    Hi Anil
    Are you using a RAC DB configuration? Please check if this is true, there are special setup steps that are required to be performed in case of RAC DB configuration and this issue usually occurs if such configuration is missing specifically if its happening randomly for some ATP requests.
    You can find actual steps to be performed on metalink.
    Thanks
    Navneet Goel

Maybe you are looking for

  • Authorization Issue with AR01 while executing through a Variant

    HI Experts, I have a user who is trying to execute AR01 with a variant created by user.  when user tried to execute it gave a message No Data maintained. I tried the same with a test user giving SAP_ALL, i got the required data.  so I ran a trace on

  • Developer-Online: Create a Digg login style using jQuery and CSS

    Create a Digg login style using jQuery and CSS Hello Friend, today We'll see how to create a Digg Login panel using only CSS3 and a bit of jQuery script. You'll see how is simple present a login feature using a modal window creates by js. You'll find

  • Entering a Block of Numbers

    Finally taking the time (and time and time......) to switch from Appleworks to Numbers. I have a list of things that don't work as I expect but here is just one but its big! In Appleworks I can select a block of cells and just start typing numbers, p

  • How can i activate photoshop cs ??????...... pls help me on this........

    How can i activate photoshop cs ??????...... pls help me on this........ pls let me know how to activate ps cs .........

  • HT5622 Change Apple ID

    I changed my email address that used to be my Apple ID as well. I followed the procedure in order to modify the Apple ID getting back confirmation by email to my new address. In the mean time I selected a new psw. Everything seems ok but if I try to