Availablity Check which includes Block Stock

Hi All,
I do have a problem with Availability Check.
For a material the Goods Reciept is made directly into Blocked Stock. Due to this the MRP is not considering the availability of the stock and creating the new PO for the old reqirement.
I want to know how we can configure the Availability Check so that it can consider the block stock into consideration during MRP run.
Thanks for the help in advance

hi,
To avoid the situation, you need to move the stock to unrestricted use...
Its correct, if we think logically then if there is req. for the material...then you can never use the block stock for the production etc...so, when the MRP runs, it doesnot consider the block stock...
Pls trasfer it to the unrestricted use stock..and then run MRP...
Hope it helps...
Regards
Priyanka.P

Similar Messages

  • Diaply block stock separately in MD04

    Hi,
    We have configured our system to include block stocks for MRP and would want to display the block stock separately.  We have used enhancement EXIT_SAPLM61R_001 & EXIT_SAPMM61R_001
    to create a separate column in MD04 to show this figure but would like to check if it is possible to have this displayed as a separate MRP element (ie. a separate row rather than column).  Appreciate your advise on how this can be done.
    Thanks...

    Dear Ramesh,
    Thanks a lot for your prompt reply.
    Yes, I did sort as per your suggestion.
    Actually I need that generated list where I can see only the Green-light list but not red-light. How can I block that material item. Pls Give me idea.
    Thanks for understanding.
    Bishnu.

  • Every time I open a pdf file which includes a javascript, a dialogue box pops up. I have a question why 'Do not show this message again' is not working even I checked on the checkbox. It should block the dialogue next time when I open the same pdf file bu

    Every time I open a pdf file which includes a javascript, a dialogue box pops up. I have a question why 'Do not show this message again' is not working even I checked on the checkbox. It should block the dialogue next time when I open the same pdf file but not working. What is the matter and how can I deal with it?

    I am trying it on Adobe Acrobat Reader 9.2.1. Tried to fix Hex code, and also tried 'edit-preference-trust manager'. I focusing on Adobe registries but still couldn't fix the problem.

  • Report to check the valued GR block stock

    Hi,
    I used movement type 107 to receive the PO with indicator 'Origin Accept', and would like to check how many stock I have received to the valued GR block stock.
    Anyone tell me which report I can use? I've checked the stock report under IM, but haven't found it.
    Thanks!
    Lin

    run Tcde MB52, and from change layout Ctrl+F8 move column Value BlockedStock.

  • Block Stock consider during MRP Run and Stock availibility check

    Dear All,
    I am facing the stock availibility check , Sytem consider the Defective material which is Block in same storage location ,and system not generate the Planned order .
    -Blocked Material stock 100, and requirement 100 then system not generate the planned. Client need the system generate planned order 100 , Because 100 material is defective.
    I have configured the system scope of availibility , Block stock check remove , but problem is not solve.
    Thanks
    Rajesh Tiwari

    Dear ,
    Can you please re-check your MRP plant parametrs in OPPQ wether   you have selected blocked stock( Available Stock tab )  option by chance ?
    Please de-select the same  and re-run MRP.Generally MRP does not consider block stock  in net requirement calcualtion .One more thing  , MRP does material avilablity check as per OMJJ set up ( define availbality chek ) but does not consider the same while doing net requirement calcualtion to generate PR rather it goes down to MRP plant parametrs ( oppq or oppr )
    Hope this is clear
    Regards
    JH
    Edited by: Jiaul Haque on Sep 16, 2010 9:29 AM

  • Quality check for block stock

    Dear QM experts,
    I want to know which inspection types is suitable for check a material in block stock.
    Here is the case,
    First i used insp type 04 for GR from production. After we got the result that the lot is rejected, then we post the stock into block stock. After that my client want to do quality rechecking with a new inspection lot.
    So, my question is how SAP can support this business process?
    Thanks in advance,
    Helly

    Hi Amol,
    Thanks a lot for ur reply.
    I just wanna make sure.
    If we use 08, is it means that every goods movement will create an inspection lot unless we make a customizing for the movement type with QM not active ?
    Helly

  • Availablity check in sales order considering the Raw material stock/procurement

    Hi Gurus,
    Our client Production process requires  the availability check at order level to consider the procurement time required for the Rawmaterial (BOM component of the FERT, whose sales order is taken) in cases when this RM is not available in the plant, and Availability check should not consider this procurement time when this RM is available in the plant.
    ie in first case, it should consider the total time for in-house production as well as the time required to procure the rawmaterials, along with all other times that we use like Gr processing time, packing picking etc.
    In second case it should not consider the RM procurement time, but only the inhouse production time and other times as applicable.
    To my understanding, Availability check at order level will only check the time given in the MRP view of the FERT, and it does not check anything about RM stock or RM procurement time.
    Can you please give me some suggestions to meet this requirement of the client (client is into Food Product Manufacturing).
    Your quick response will be very helpful

    You can try with user exits intended for ATP as recommended in the following note based on material type:-
    Note 1644443 - Documentation on User-Exits in the area of the availability
    That is as and when ATP runs for a sale order, with any of the exits listed out in the above note, you can validate for the material type which would be different for components and accordingly, write a coding in such a way not to consider such of those components.  But ensure that the user-exits are critical and should be tested carefully as cautioned in the note.
    G. Lakshmipathi

  • Which table is GR Blocked Stock saved in ?

    hi:
       when i do gr with movement type 107, can anyone tell me which table is GR Blocked Stock saved in ?
      thanks in advance..
    Monson

    if i do gr with 107, then you can see the GR Blocked Stock  with MMBE, I want to know which table is GR Blocked Stock  saved in , not material document. thanks ..if there is no directly table, can anyone tell me how to calculate it ?

  • Using Windows 7 and LR 5  when I look at the Keyword List a certain keyword has 7 pictures but when I check the Library Filter with that keyword 350 pictures are shown which includes the 7 pictures that have the keyword.  Why does the Library Filter showi

    Using Windows 7 and LR 5,  when I look at the Keyword List a certain keyword has 7 pictures but when I check the Library Filter with that keyword 350 pictures are shown which includes the 7 pictures that have the keyword.  Why does the Library Filter showing pictures that do not match the query

    Dan,
    Here's what's going on in the catalog you sent me, "Joel & Caitlin's Wedding".  There is the keyword "gwenn", which is explicitly assigned to 7 pics. But keyword "schwartz" has a number of synonyms, including "gwenn", and it is assigned to 25 pics.  There is no overlap between the two sets of pics. 
    I discovered these two occurrences by doing Metadata > Export Keywords, opening the exported file in an editor, and then searching for "gwenn".  I found two occurrences of "gwenn":
    gwenn
    schwartz
        {gwenn}
    From this, you can see that the keyword "schwartz" has 9 synonyms, of which "gwenn" is one.
    The filter criterion "Keywords Contain gwenn" will match the 7 pics that are explicitly assigned the keyword "gwenn", and it will also match the 25 pics assigned the keyword "schwartz", because that keyword has a synonym "gwenn".
    This illustrates the behavior I mentioned above: The criterion "Keywords contains x" will match against any of a pic's assigned keywords, any of those keywords' ancestor keywords, and any of the synonyms of the assigned keywords and their ancestors.
    So LR is operating correctly here, if not in a way that's easy to understand. 
    It appears that you are using the synonyms of "schwartz" to represent individual members of the Schwartz family.  A better way of representing family relationships is to have a parent keyword "Schwartz", with subkeywords for each family member, e.g. "Gwenn Schwartz", "Joe Schwartz", "Jane Schwartz", etc.  Repeating the family name in the subkeywords has a couple of advantages. LR usually only displays the "leaf" name of a keyword, so instead of showing you just "Joe", it will show you "Joe Schwartz", helpful when there are a number of different people whose first name is "Joe".  Also, if you ever export your pics to other software, it may not understand the LR hierarchy and won't show the parent keywords, so again it's more informative to see a keyword named "Joe Schwartz" rather than "Joe".

  • Availablity check

    Dear Friends,
    1.In  availablity check configuration,i cant able to understand ,
    define material block for other users
    2. what is the importance  between checking checking group maintained in sales general plant view and checking group in mrp-3.
    kindly explain on this.
    3. what is back order
    points will be rewarded

    AVAILABILITY CHECK:
    1. Define Checking Groups
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Checking Groups
    You define checking groups with which you specify the type of requirements records the system is to create when processing sales orders or deliveries
    2. Define Material Block for Other Users
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Material Block for Other Users.
    3 .Define Checking Groups Default Value
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Checking Groups Default Value.
    4. Carry out Control for Availability Check
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Carry Out Control for Availability Check.
    5. Define Procedure by Requirements Class
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Procedure by Requirements Class.
    6. Define Procedure for Each Schedule Line Category
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Procedure for Each Schedule Line Category.
    7. Determine Procedure for Each Delivery Item Category
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Determine Procedure for Each Delivery Item Category.
    8. Checking Rule for Updating Backorders
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Checking Rule for Updating Backorders.
    9. Define Default Settings
    Menu Path: SPRO>SD>Basic Functions>Availability Check and Transfer of Requirements> Availability Check with ATP Logic or Against Planning>Define Default Settings.
    Checking group
    The checking group controls whether the system is to create individual or collective
    requirements in sales and shipping processing. In addition, a material block for the
    availability check with transfer of requirements can be set here. The checking group can
    also be used to deactivate the availability check. This option was created especially for
    the assembly order so that when the bill of material is exploded in the assembly order,
    the individual components, if necessary, can be classified as non-critical parts as far as
    procurement is concerned.
    The checking group specifies in combination with the checking rule the scope of the
    availability check. It is proposed in the material master record on the basis of the material
    type and the plant, and copied into the sales and distribution documents.
    _ Checking Rule
    You use the checking rule to control the scope of the availability check for each
    transaction in sales and distribution. You also specify whether the check should be
    carried out including or excluding replenishment lead time. The individual checking rules
    define by transaction, which stock and inward and outward movement of goods should
    be taken into account for the availability check.

  • Availability check for Make to stock and Make to Order

    Dear All,
    Client is selling   Make to stock and make to Order material.
    How and what settings need to do for Avaialbility check.or we can use standard one.
    I hope in case of Make to Order availability check may not happen.
    Please correct me.
    Thanks in advance.
    Regards,
    Shrikant

    hi,
    yes for make to order we dont have AvChk.  for make to stock items u need to follow the
    below configuration.
    Availability check
    1. Availability check is an integral part of the business process that determines if the required delivery quantity can be met on a required delivery date. For this purpose the system takes into account pre-delivery activities such as scheduling for picking or packing times and the time taken to produce or obtain the material. It also performs several background functions such as Backorder processing, rescheduling and ATP quantities.
    2. Backorder processing: processing of a sales order that has not been fully confirmed or not confirmed at a certain delivery date.
    3. Rescheduling: is a proposal of how u2013 confirmed quantities already assigned to a sales order can be reassigned to other sales orders that have a higher priority.
    4. Available to promise (ATP): is a process of checking the available quantities of a material. The ATP quantity consists of warehouse stock + planned receipts (incoming stock) u2013 planned issues (outgoing stock). to examine stock on hand (CO09) proceed to logistics u2013 sales & distribution u2013 sales u2013 environment u2013 availability overview.
    5. Replenishment lead time (RLT): is the time taken for the material to become available either internally (in house production) or externally (from a vendor). The most important things to consider during an external procurement are purchasing and MRP 2 (procurement) views of MMR where the processing time for purchasing, planned delivery time and goods receipt processing time are taken into account. On the other hand internal procurement is based on in house production time (MRP 2 view) goods receipt processing time or alternatively RLT time, which is found on MRP 3 view.
    6. RLT (Replenishment Lead Time) is the time taken for the material to become available. RLT is only used when doing an ATP check (Available To Promise). The value of RLT for a material is specified on material master record.
    7. There are three types of availability checks u2013
    Check on basis of ATP quantities.
    Check against product allocation.
    Check against planning.
    Configuring Availability check through Checking Groups u2013
    1. The checking group + checking rule determine how the availability check is to be performed.
    2. The checking group determines whether and how the system checks the stock availability and generates requirements for material planning. The checking group defines what type of requirements will be passed on i.e. summarized requirements (daily/weekly) or individual requirements for each sales order.
    3. The checking rule applies to how the availability check is to be carried out at the transaction level. Note that you must define checking rules for each individual application such as for production orders for example. In Sales and Distribution, the checking rule is specified internally within the system and cannot be changed.
    4. The checking rule, in conjunction with the checking group, determines the scope of the availability check for every business operation; that is, which stocks, receipts and issues are to be included in the availability check and whether the check is to be carried out with or without the replenishment lead time.
    5. Briefly explaining the above u2013 checking group determines which type of requirement to be passed on to MRP whether it be individual or summarized and checking rule which is at the transaction level and can be configured independently for each application module, determines which stocks, receipts and issues to be taken into account. For performing an availability check checking group has to work in conjunction with checking rule.
    6. Advantages of individual processing over summarized processing u2013
    Backorder processing is possible.
    You can access (MD04) order, line and schedule line individually which gives a greater control on available stock and requirements placed on stock.
    The system automatically uses individual requirements in case of special stock items.
    7. Required data for the Availability check to be carried out u2013
    The Availability check must be switched on at the requirement class level.
    The Availability check must be set at the schedule line level.
    A requirements type must exist by which the requirements class can be found.
    A plant must be defined in the sales order for each schedule line item (in other words plant must be defined for every material in MMR).
    A checking group must be defined in the material master record in the MRP3 screen in the availability check field.
    8. Configuring Availability check and defining Checking Groups u2013
    Checking groups are introduced into the sales order based on the setting in the material master record.
    SAP standard checking groups are 01 u2013 summarized requirements and 02 u2013 individual requirements or you can create your own by copying the standard ones.
    Total sales and total deliveries columns are there to configure a checking rule to sum up requirements to post to MRP either individually or by day or week.
    Block quantity required can be set if you want several users to be able to process the material simultaneously in different transactions without blocking each other.
    The no check indicator is CHECKED when you DO NOT want the system to carry out ATP check.
    9. Defining material block for other users u2013 the block check box is an indicator that enables you to block material master records of a particular material during the availability check and restrict other users from accessing same master record and reserve the material. If the block is not set, two users can confirm the same material at the same time for two different orders, not knowing if the stock is available or not. If you select this field, the material is blocked during the availability check and other users cannot: a) Make changes in the material master record. b) Create purchase orders for the material. C) Create orders for the material.
    10. Defining default values for checking groups - Checking groups are introduced into the sales order based on the setting in the material master record.
    However if there is no entry present in the material master record for the checking group, a default value can be set here, depending on material type and plant.
    This default value will be used by the system depending on the material type mentioned in MMR and plant in sales order.
    If an entry exists, this default value is over written by MMR.
    11. Controlling Availability Check u2013 in this section, you tell the system what stock on hand and what inward and outward movements of stock it must take into account when performing the availability check in addition to whether or not to consider the replenishment lead time.
    12. These settings are based on the checking group that is assigned to the material master record and the checking rule that is predefined and assigned to the sales and distribution transaction.
    13. These settings carry out control both for sales order and delivery as well. This is due to the fact that you may want to include specific stock or incoming stock for the sales order, yet at the time of the delivery only include physical stock on hand waiting to be shipped.
    14. It is possible to indicate to the system that you would like the availability check NOT TO CHECK the stock at the storage location level. This indicator is used to set the scope of the availability check.
    15. It is used to switch off the check at storage location level. You create a reservation for a particular storage location. However, the scope of the availability check is set in such a way as to exclude the storage location. In this case, the system carries out the check at plant level only and does not take the storage location into account that is specified in the reservation.
    16. Should you not want the system to automatically check RLT, you may indicate so here. RLT is the time taken for a material to become available. It is only used when doing an ATP check and is taken from MMR.
    17. Defining the elements in the availability check entirely depends on the business needs, but a few tips are given under u2013
    When controlling the Availability check at the time of the sales order, a purchase requisition does not necessarily indicate by it is going to come into the plant.
    A shipping notification on the other hand - a confirmed purchase order u2013 is a good indicator of receiving stock on a specified date.
    It is always recommended not to select the shipping notifications for the delivery requirements type as you may not actually receive the stock into plant or warehouse for which you are creating a delivery.
    regards
    anand

  • Reservation & Availablity check

    Hi ,
    To produce a material A , component B is needed . Material A is required for export customer and Domestic customer as well
    but the export order is very high importance due to that if the material A stock is available in stores then it should reserve for export order only and the same way the dependent requirement component B also should get reserved
    Ex: Export order qty - 10 Nos , Domestic order Qty - 10 Nos , material A is available at stores is 5 Nos , so the 5 numbers should get reserved for export order ( this can be done by ATP check assigned with item category in sale order ) , for the remaining 5 requirement system create a planned order for A and dependent requirement for B
    Component B stock is 5 Numbers & this 5 numbers will get reserved for material A based on availablity check rule 
    but my query is suppose the reserved qty -5 is issued to domestic order requirement then the shoratge for export may occurs.
    what are the setting need to be done  to avoid the reserved material issuing to other order ( it should get blocked )

    R,
    The answer is yes, as I stated in my earlier post.  The quantities are irrelevant.  If 'B' stock is built as 'make to order', it cannot be issued to any other requirement, except for the specific sales order/item for which it was built.  In effect, all B stock is reserved to individual orders.  There can be no 'stealing' without manual intervention.
    You can construct your Bills of materials and Material masters to be MTO all the way down to the Raw Materials, if you wish.  In each case, the stock at any MTO level of the BOM only exists to serve one and only one sales order requirement.
    I suggest you try this in your sandbox to see how it behaves.  Managing B as MTO meets all the requirements you have stated so far.
    Rgds,
    DB49

  • Stock in MD04 is also considering Blocked stock with Unrestricted Use

    Hi PP Gurus,
    In MD04, the stock which the system is showing also considers Blocked Stock for Planning means stock= Unrestricted Use Stock + Blocked Stock.
    We Dont want blocked stcok to be considered.
    We are using 01 availabilty check with PP checking rule.
    In OPPJ, the check box for Stock-Include Safety Stock is only Checked.
    Can anyone Please explain why the system is considering blocked stock for Planning???
    Thanks in advance,
    Regards,
    Rakesh Wade

    Hi,
    Pls check in OPPQ - Available stock tab - Blocked stock would have been activated and hence the system is considering the Blocked stock also.
    This indicator when activated causes blocked stock to be included in the MRP calculation.
    The indicator you enable in OPPJ will come into effect only when you carry out an avilability check.
    Regards,
    Sheik

  • Availablity  check with ATP logic

    Hi everybody
    Can any one tell me where where we assign Checking rule (A - sales order) in availablity check.

    dear srikanth
    please gothough this
    TOR AND AVAILANBILITY CHECK
    To confirm the quantities for a particular line item in the sales order on particular day system carried out transfer of requirements (TOR) & AVAILABILITY check, so has to confirm the quantity on particular day as system should know what are there requirement of the sale order and delivery with MRP then system carries out availability check function, to confirm the quantity on particular day. Depending upon the IMG setting system carries out availability check function based on 3 methods:
    A) Availability Check with ATP logic or against planning:
    In ATP logic systems ATP Qty while carrying out availability check function for
    Particular line item (ATP qty=warehouse stock +planned receipts planned issues)
    Planned Receipts: EX: - purchase requisitions, purchase orders, stock in transfer stock at inspection etc.
    Planned Issues: - EX: - open sales order & open delivers
    B) Availability check against product allocation:
    Availability check can be carried out against product allocations in which system automatically restrict the user to confirm the quantity beyond reserved quantities per particular customer. EX:- Availability qty =100, existing orders=10,then system automatically distributes to items evenly to the sales order.
    C) Rule based Availability check:
    Rule based availability check can be carried out based on the business transaction.
    EX: - For normal sales order system has to carry out availability check for special sales order ex: - cash sales and rush order systems need not to be carry out availability check,
    In rule based availability check system in which system carried out Global availability to promise in all plants. In this check system transfers the requirements to APO system where GATP takes place and the result of the availability check transferred to R/3 system. This process takes place with the transaction code CIF(central inter face) inR/3.After carrying out availability check function system proposes(by using ATP logic) default values of ATP check  result to the user in a dialog box, in which system gives the  choice to the user to take the decision in contest of insufficient stock.
    a) One time delivery:
    If the user chooses one time delivery and the order Quantity is 100 units system confirms 50 units then systems automatically confirms as a zero. If the user saves the document with the zero confirm qty then system   trace the sales order as aback order (V_RA), which can be confirmed later by RESCHEDULLING (V_V2).
    b) Complete Delivery:
    If order Qty=100, Availability stock = 50, system says that remaining can be given after one week. Then if the user selects this option then system push up existing confirmed qty to after one week and the total qty can be confirmed after one week only.
    c) Delivery Proposal:
    If order qty=100, system confirms 50, and remaining 50 can be confirmed after one week. If the user chooses this option then system confirms 50 Qty today allows the user to delivery 50 quantities today remaining 50 can be delivered after one week.
    CONFIGURATION SETTINGS FOR TOR:
    Define Requirement Class:
    Path: Img  S&D   Basic functions   Availability Check & Transfer of requirements   Transfer of requirements    Define Requirement classes
    Requirement classes control MRP, Requirement consumption, strategy, relevance for planned. It specifics whether the availability check & TOR to be Called out for transactions.  Ex: Sales Order
    It determines whether requirements relevant for MRP or not, the allocation indicator from the sales view which controls the settlement of customers requirements with planned independent requirements. It determines the item b to be settled as an availability heck. Assignment, the settlement profiles the results analysis key. The TOR and Availability check functions are globally controlled using the requirement class for all the Sales documents. The values from the Requirements class are transferred to scheduled the of the sales documents class are transferred to scheduled the of the sales document default values and can be over written there.
    Define Requirements Classes:
    Requirement class defines whether the system has to carry out availability check based on the STP Qty. Ex:
    Define Requirement Types:
    Here we define requirement type, Ex:  and Assign to Requirement class that we defined in the promote step.
    Determination of Requirement types using Transaction:
    Requirement type is going to be determined for sales document by following a search strategy. .
    First System checks strategy group in MRP3 view if it trend requirement type then system takes from it, otherwise.
    It will go to MRP group in MRP1 view, otherwise
    It will check to Material type, otherwise
    It will go to item Category + MRP type, otherwise
    It will go to Item category only, otherwise
    Finally system determines the transaction b not relevant for TOR & Availability check.
    Choose Item category TAN+MRP type PD=Requirement type =0
    Define Procedure for each schedule the category:
    Here we define respective schedule the category of the sales documents, whether an availability check and TOR should be carried out. This setting is relevant for sales documents only. It is fine tuning of availability check for sales documents TOR & Availability check function    can be activated at sales order level those are proposed in to schedule line category level. If u wants to deactivate TOR availability check function at schedule the category level and want to deactivate at requirement class level it b impossible.
    Ex: If u wants to check availability w/o transferring the requirement we can use it.
    Choose schedule line category CP & Activate Availability check, requirement & Product Allocation
    Block Quantity confirmation in delivery Blocks:-
    When we transfer requirements to MRP then confirmed quantities is also reserved for confirmed sales documents, if transaction is blocked for delivery the reserved quantities are also blocked so that the conformed quantities cannot be used by any other purpose. So has to avoid this situation we can block the transfer  of requirements(TOR) for delivery blocks, in this case requirements transferred to MRP but will not be reserved, that will be cleared once we save the documents then system shows confirmed qty as zero.
    When we remove the delivery block then system automatically carries out availability check & confirms the qty.
    A) Deliveries: Blocking region for sales Area:
         Here we define blocking regions for TOR ex:-credit limits
    B) Reasons for scope of delivery blocks: TOR. Block:
    Ex: - 01 credit limits-check confirmation block.
    Maintain Requirements for TOR:-
    Here we can define our own requirement with the help of ABAPer for TOR
    Ex: - a) 102- prevent reservation in the event of credit block
           b) 102-purchase requisitions.
    System doesn’t create purchase requisitions for sales order line items if it has a credit limit.
    Availability check:
    Configuration setting:-
    Availability check with ATP logic or against planning:-
    A) Define checking group:
    Checking group defines what kind of requirement record system use to create when sales order & deliveries are processed for this material. We can create 2 kinds of requirements records
    Individual requirement records: that means system creates requirement record for each S&D document.
    Summarized requirement Records: That means system creates requirement records under certain condition in the material master record. There are 2 type of summarized requirement record:
    Summarized requirement records for each day.
    Summarized requirement records for each week
    Define checking Action;
    Here we define     01- daily requirement      -B                                        02- Individual requirements -A
    Where      B-total record per day
         A-single record per day
    B) Define material Block for other users:
    When 2 users tries to confirm the quantities for the sales order for same material at a time system will be confused to confirm the quantities both sales orders. So has to avoid this kind of situation we can block the materials from confirming the quantities for 2 users at a check, check block
    C) Define checking group default values:
    Checking group is going to be determined depending upon the material type & plant.
    -Go to new entries, specify material type, ex;-FERT
    & plant = checking group of availability check: 02
    D) Carry out for Availability check:
    Here we define checking rule for the Availability check & allocate them to the checking group. The checking rules specify the scope of the availability check. For a respective transaction, means which planned receipts & planned issues systems has to taken into consideration and also it determines whether system has to take RLT into consideration.
    *Select checking group of availability check-02, checking rule=01
    *Go to details icon, & check which planned receipts & planned issues system has taken into consideration for availability check
    *save it, exit.
    E) Define procedure by Requirement class:
    Here we define requirement class whether on availability check & TOR should be carried out the setting that we carries out at requirement class level they are at global level. There settings automatically copied into define from of requirement class and vice versa.
    *Choose requirement class: 041 & check availability check & TOR (requirement)
    F) Define procedure for each schedule line category:
    Here we carry out fine tuning setting for availability check at schedule line category level. Here we define whether system has to carry out Availability check for particular transaction.
    Ex: - if we want to implement availability check w/o TOR for a particular transaction. According to settings at requirement class level TOR & availability check function activate & those setting will be copied into the schedule time category by default, so that at schedule line category level we deactivated TOR
    G) Determine procedure for each Delivery Item category:
    Here we switch on or switch off availability check functions of a delivery item category
    *choose item category ‘TAN’. & specify the appropriate value.
    H) Checking group for updating back orders:
    Here we assign checking group to a plant that rule specifies for individual application, according to which the availability check is carried out;
    I) Define Default settings:
    Here we define the result of the availability check.
    *Choose your sales Area, & check fixed dates& Qty options & specify ‘D’ or ‘E’
    Where: D- Dialog box in the case of shortages (one time delivery)
    E- Dialog box in the shortages (delivery proposal).
    rewards if it helps
    siva

  • Consideration of GR Blocked Stock (mvt 103) for MRP.

    Dear Expert,
    My requirement is to consider GR blocked stock (mvt 103 non valuated stock) in MRP run.  My Business process is goods received in plant through movement 103 and then regular GR ( mvt 105)
    I do carry MRP run twice in the month.
    Requesting you to provide me solution which will help me to consider GR blocked stock in MRP.

    Hi,
    In OVZ9, for the combination of avaibility check please select Check blocked stock Indicator determines whether blocked stock is included in the availability check.
    Please try and come back.
    Regards,
    R.Brahmankar