Avoiding creation of inspection lot for certain vendors.

Hi,
There is one requirement from my client side , that Inspection lot should not be created for certain vendors ( Issuing plant also consider as vendor here).
The correct requirement is if it is transfered from other plants it should not create the lot and on the other vendors it should create.
We have a have a option through maintaining the QM info record but it was not maintained earlier and newly creation is too difficult.
I remember there is some exit is available to overcome this. Any one having the earlier experince on this...Provide the exit and FM name... High priority one.
Regards
Pragash

Dear Pragash
1) You can maintain Quality info Record in enmass using QI06. Only maintain for the vendor you need to skip.
2) This exit can help you in controling the inspection lot
QAAT0002 Control of acceptance lots/goods receipt  
QBCK0003 Extended QM check for goods receipt                                         
Regards
Gajesh

Similar Messages

  • Restrict creation of inspection lot for certain work centers

    Hi
    My client needs to restrict the creation of inspection lot at certain work centers although QM is active for all material processed in these work centers.
    I am using the  function module 'EXIT_SAPLQAAT_002' of QAAT0001 for this purpose. Z04 inspection type ( with Post to insp stock) is maintained for all these material.
    A different Z table is there , where material-work center combination is maintained for which no inspection lot is required.
    Logic provided so that system searches Material-Work center from production order then compares it with the Material-Work center combination with the maintained Z Table.If both found same then no inspection lot will be generated.
    But an error message (Change the inspection stock of material XXXXXX in QM only) appears for all those material while doing confirmation in CO11N . Hence system does not allow to complete confirmation for those material where QM is active.
    Please suggest if i am using the correct Exit or any further improvement is required.
    Thanks and regards
    D Mohanty

    Hi
    Actually the issue is resolved now.The problem was with coding where we were using Table-AFRU for reading prod order details.But AFRU does not consider fresh orders for which it was replaced with AFKO.
    Also the Z table must be maintained as Plant-Material-Work center combination prior to go for any order confirmation.
    Thank you all who have gone through the post , hope this will help those who have to map the same scenario at their end.
    Regards
    D Mohanty

  • Creation of inspection lots for vendors

    Hello friends,
    How can we create inspection lots for all vendors at a time? I want to record results for my vendors(near about 2000 no.) by inspecting their raw matwrials in a lab.

    Hi Kiran,
    Why you are going for manual lot creation if the scenario is like above?
    1.     Assign inspection type 01 to material master
    2.     Prepare an inspection plan through QP01 with usage 5
    3.     Inspection lots will get generated with lot origin 01 whenever you do good receipt through
    migo with 101 movement type
    Conclusion: Inspection lots will get generated automatically whenever you do good receipt with vendor material combination.
    Best Regards,
    Anand Rao

  • Stop Automatic Creation of Inspection Lot for a condition

    Dear Gurus,
    While Creating a Delivery through a Sales Order, Config is maintained such that "Inspection Lot" will be automatically Generated.
    Now Business wants to Stop this Automatic Creation of Inspection Lot only for a Particular Delivery Type and for a particular mode of Transport.
    Do we have any User Exits / BADIs to achieve this requirement.
    Please let us know.
    Thanks in advance.
    Regards,
    Vinay Mutt

    Hi
    To meet you above mentioned requirement you have to modify the program RQAAAS10 as per your logic both to create lot for Expired Material and to consider project stock or vendor stock as In standard SAP these stock are not considered.
    regards
    Manish

  • Automatic creation of inspection lot for Expired Batches

    Hi All,
    I am in one trouble and need some help in above scenario.
    I am able to create inspection lot for batches about to expire, but how to create inspection lots for batches which were already expired or which next inspection date already missed?
    Master data like '09' inspection type, inspection plan is already maintained.
    Second question, is QA07 also affect on special stocks like vendor stock or project stock etc?
    Immediate response will be appreciated.
    Thanks

    Hi
    To meet you above mentioned requirement you have to modify the program RQAAAS10 as per your logic both to create lot for Expired Material and to consider project stock or vendor stock as In standard SAP these stock are not considered.
    regards
    Manish

  • Setup of Inspection Lots for some vendors and not for all

    Hello,
    We do have a situation where in the business wants Inspection Lots to be set up for some vendors and not for some vendors - for the same material.
    What it means is, for Material XXXXX001, Vendor 00003 needs inspection during GR for Purchase Order and Vendor 00005 and 00006 should be set up for Non Inspection upon GR and stocks should be posted to Unrestricted.
    Any suggestions / options are welcome.
    Thanks
    Kris

    Hello,
    You can use vendor q-info records to handle this... deactivate the goods receipt inspection on the vendor(s) that do not require incoming inspection.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/c6/b9b3341a933f50e10000009b38f83b/frameset.htm
    Regards,
    John

  • Avoid creation of Inspection Lot by MIGO

    Hi All,
    In some cases I want to avoid the creation of an Inspection Lot, It can be done by configuration.
    How can I do that?.
    I was thinking to change the "Status GR Doc." but In the badi MB_MIGO_BADI that field can by changed.
    Please any help??

    Hi,
    Check tcode OMJJ. Set a movement, and go to 'deactivete QM inspection..' and change the flag 'QM not active'. Read the documentation and the help on F1.
    I hope this helps you
    Regards,
    Eduardo

  • BAPI for Creation of inspection lot

    I have two scenario:-
    1.Can any body help to find BAPI for creation of Inspection lot for the material under PO envisaged for PDI.
    2. Can any body find me a BAPI or FM which can creates inspection lot in QALS table without inspection lot origin under 01 i.e. 0101 or Z01SI01.
    My objective is to creation inspection lot without assigning Inspection type of Z01SI01 or Z01SI02 and so on in the material code under a respective Plant 1004 or 1005 0r 1006 so on.
    In my Z Development for creation of inspection lot BDC is run for QA01 as this code created inspection lot on when material code has inspection type Z01SI01 i.e. location of source inspection and vendr code particular classification under 010 vendor class inspection type Z01SI01. System search both the inspection type for both material and vendor then create inspection lot in QALS table by assiging inspection matching inspection on the lot.
    I want to get rid of assignment of inspection on the materilal. If any BAPI or FM is avalable for creation of inspection without assigning inspection type on material code. I want to create inspection lot in which Inpsection type assignment can be done based on vendor class only.
    YPB

    2. Can any body find me a BAPI or FM which can creates inspection lot in QALS table without inspection lot origin under 01 i.e. 0101 or Z01SI01.
    I am very sure that this is not possible.You can not create inspection lot without inspection lot origin or inspection type.
    Regards
    Sujit

  • Creating inspection lot for vendor returns

    Hi All,
    In Subcontracting, components are sent to vendor using Mov Type 541, if vendor returns the components without any value addition we recieve the goods with Mov type 542.
    Now, when we recieve the goods using 542 customer requires that the material has to be posted to quality inspection and a lot has to be created.
    I have already tried with inspection type 08 but its not working.
    Any ideas how it can be done?
    Regards
    Naveen Goveas

    Hi Naveen,
    You have come across a common problem in later releases of SAP. Ram is nearly right in the settings for control of inspection lots for goods movements. In the standard system movement type 542 has no inspection lot origin assigned, so even if you have maintained an inspection type for your material there is no "trigger" for the inspection lot creation from that movement type. Unfortunately, you cannot change the inspection lot origin settings for movement types. The only choice you have is to create (as a copy) a customer defined movement type (one which already has the appropriate inspection lot origin assigned) and use that instead. You have to also be careful about the 'Quantity' and 'Value' updating strings for your new movement type.
    Hope that helps.
    Colin

  • Inspection Lot for inspection type 09_ Vendor field is blank

    Hi,
    Inspection lot for inspection type 09. I am not getting the vendor name in inspection lot details. Vendor field is blank.
    I need this field updated. Please guide me what to do for this.
    Thnaks & Regards
    Kundan kumar

    HI Ashok,
    I checked in material batch data( msc3n) vendor details is there.
    Please update me more in this regard
    Thanks & Regards
    Kundan kumar

  • Scenarios for "manual creation of inspection lot"

    Hi QM gurus!!
       I would just like to ask the main function of QA01 or "<b>Manual creation of inspection lot</b>"
    What are the cases/scenarios where this tcode is used? I would really appreciate if you could help me.. Thank you.
    Regards,
    Heinrick Palad

    HI,
    The table below provides a brief overview of the functions you can use to process inspection lots. Appropriate cross references are included for the more extensive tasks or for those for which additional information is available.
    Prerequisites
    The inspection lot processing functions can be linked to various authorizations that are checked by the system whenever you try to process an inspection lot. The following types authorizations are relevant to inspection lot processing:
    Material authorizations
    The material authorization for QM is stored in the material master. For more information, see  Creating and Changing QM-Specific Data for a Material.
    Inspection type authorizations
    This authorization controls which inspection type the user can access in order to create an inspection lot. The inspection type authorization is plant-specific.
    No authorization checks are executed in QM when an inspection lot is created automatically.
    Features
    Function
    Pushbutton / Menu path
    What you should know
    Accessing the initial screen for the inspection lot processing functions
    Logistics ® Quality management ® Quality inspection ® Inspection lot processing ® Inspection lot
    Creating an inspection lot manually
    See Creating an Inspection Lot Manually
    Changing an inspection lot
    Choose Change
    Enter the number of the inspection lot you want to change and then choose Enter.
    Displaying an inspection lot
    Choose Display
    Enter the number of the inspection lot you want to display and then choose Enter.
    Creating a new batch in an inspection lot
    See Batch Creation in Inspection Lots
    Cancelling an inspection lot
    Call up an inspection lot in the change mode and choose Inspection lot ® Functions ® Cancel lot.
    See Cancellation of an Inspection Lot
    Blocking/unblocking an inspection lot
    Call up an inspection lot in the change mode and choose Inspection lot ® Functions ® Block lot.
    To unblock an inspection lot, choose Inspection lot ® Functions ® Unblock lot.
    When you block an inspection lot, you cannot process the lot further. You must unblock the lot if you want to perform any additional operations.
    Transferring stock in an inspection lot
    See Stock Transfers
    Making corrections to inspection lot quantities
    See Corrections to Inspection Lot Quantities
    Creating a QM order
    Call up an inspection lot in the create or change mode and choose Goto ® Insp. lot acc. assgnmt.
    See QM Order Creation
    Resetting the sample calculation
    See Resetting the Sample Calculation
    Printing inspection instruction/sample-drawing instruction
    See Printout of Instructions
    Approving a task list
    Call up an inspection lot in the create or change mode and choose Inspection lot ® Functions ® Give approval
    If the task lists in your company must be approved before they can be used, you should make sure that only approved task lists are assigned to an inspection lot. If the system selects a task list that has not yet been approved, you can use this function to approve the task list (provided you have the necessary material authorization).
    this link help u.
    http://help.sap.com/saphelp_erp2004/helpdata/EN/be/00bbe7ca5311d2961800a0c930e04c/frameset.htm
    reward is usefull.
    tahnks.

  • Creation of one inspection lot for more than 1physical sample

    hello SAP,
    we have one common question.I have created 3 physical sample 20000006,2000007,2000008 and now i want to create one inspection lot for these 3 physical sample through QPR5 Transaction but system is generating each inspection lot for each physical sample which is wrong process. this is common scenario for most of the industry.SO please clarify and provide the solution

    Hi,
    I hope this solution gives some way out for you to solve your problem . I assume the sample is for  the same material , phy. sample type and category
    Create a new physical-sample drawing with refernce to :
    Using this function, you can create a new physical-sample drawing (with one or more physical samples) that references:
    An inspection lot
    A production order or process order
    A production version
    You use this function to create physical samples that have not been planned in a sample-drawing procedure and which you can draw from a production process according to your specific needs. In an inspection during production, for example, you can draw physical samples from the process on the basis of time or quantity (for example, a physical sample every three hours or for every 1000 liters of material produced). You can freely specify the inspection-relevant operations in which you want to inspect the physical samples for the new physical-sample drawing.
    please do let us know wether you were able to create one inspection lot .Or else please ellaborate the question step wise t-code and functions Will try to find a solution .
    cheers
    kp
    source of information : SAP

  • PR Creation at Inspection lot creation

    Dear QM Experts
    can we generate Purchase requisition with the creation of Inspection lot, Automatically.
    in my case there are some inspection operation performed by external agency for which he charge some amount for services.
    for this i created a control key of external services and assign this in the inspection plan in a separate operation and enter all the required data like cost element, vendor, Purchasing oganization and material group but when i created the inspection lot , PR is not generated,
    should this requirement be cater by SAP?
    Regards

    Hi,
    Why do not you try here Source inspection.
    During crsation of purchase order lot will get generated .you can inspect material before its coming to your place..
    You have to activate 0101 inspection type active.
    Qinfo record you have activate source inspection.
    Even in procurrement key in custamizing you can have option if material get rejected.
    Once purchase order created to create lot you have run transaction QI07.where you can click on create lot.after saving this transaction you can get lot..Then you record result as per toyr requirement like from external services.
    Regards
    SANIL

  • Automatic creation of inspection Lot upon GR

    Hello all,
    i have a problem with QM module. I want that when QI is active in material master the system automaticcaly create an inspection lot. At the moment when i post the GR the system doesn't create it.
    The GR is posted in a storage location manage by WM, so i have customize also the interface WM-WM.
    Can you help me, please?
    Thanks
    Matteo

    Hi Matteo,
    The settings required for automatic creation of inspection lot are as follows:
    1. Tick the procurement active tick on the material master and assign a QM control key.
    2. Assign inspection type 01 and set this to active.
    3. Create the q-info record for the material, plant and vendor combination.
    4. Set the inspection control to inspection active in the q-info record (no need for the status profile unless you controlling which inspection type to create depending on the specific status).
    5. Also ensure for the PO you receiving that the stock type is set to quality inspection and the QM control key is specified.
    This should create the inspection lot automatically without the need of a status profile.
    Regards,
    Roderick

  • Manual creation of inspection lot

    on october 1st  i received the  material (QM is activated for this Material)  2000 qty from the vendor 100011
    system automatically created Inspection lot 2000 qty......in that i i have posted only 1000
    now in MMBE i am seeing 1000 in QI stock now today i have to move the stock from QI to unrestricted.....
    Manually i created inpection lot using QA01 for the Remaining 1000 qty......after that i am clueless how to proceed with pls guide me.............with the following steps.......

    Hi
    Creating Manual inspection lot for the remaining 1000 qty will not prompt for the stock posting. Here u can only record the results for the same.
    For the balance stock posting, u need to go to the same inspection lot( old one which was created for the 2000 qty against GR). To search for this lot, in QA32,
    select the radio button " select all inspection lots"
    Provide the date range. if u are not sure about the dates, keep blank
    provide material, batch etc.
    Now after execution, check the inspection lots for the status SPRQ or SPST
    Select the insp lot & click on Usage Decision. Post the balance stock to unrestricted.
    Thanks
    Sachin

Maybe you are looking for

  • Hard Drive not recognized when booting from XP CD on docking station

    The hard drive on my X60 failed to the point where I couldn't recover and reinstall the image. I have backups of all my data and a docking station so I didn't sweat it. Bought a new drive and installed it and this is when the trouble began. I created

  • HP OFFICEJET PRO 8500 - Will not install on wintows 8.1- says SYSTEM CANNOT FIND SPECIFIC FILE

    My HP Officejet 8500 will not install on windows 8.1.  The error message says: The system will not find the specific file

  • Hooking Macbook to Toshiba LCD HDTV

    Am trying to hook my 2008 Macbook to my Toshiba 40RV52R 40" LCD TV, using Mini-DVI connector, HDMI cables and PC audio cables from the Macbook's headphone jack. Am getting great picture, but can't seem to get the audio to work. Toshiba customer servi

  • Documents in Pages appear blank

    I can't see any text in documents opened in Pages. Text is visible in the list preview. I have tried dragging the iWork 09 plist to the desktop and reopening, but that didn't work. Also made sure text display is set to black on white. Others seem to

  • Use of wizard in config

    Hi all,      When do we use wizard in configuration. What is advantage of going with wizard and manually?  Is it possible to use wizard configuration for all scenarios. Till now I have used wizard configuration.  Is there is any scenario where we do