Back Flushing Vendor consigment Material in process order

Dear Experts,
I have a question Regarding Vendor consignment back flushing
while i am doing order confirmation system not proposing vendor name and in good movement tab
may i know what configuration or master data setup is missing
My requirment is i need to back flush vendor consginment material automatically
currently i need to manually choose the vendor while confiming the order
Thanks in advance
Rgrds
Raj

Dear Experts,
I manage to use stock determination group for back flushing consignment material
it works fine system automatically picking up vendor as we do not have multiple vendors
now i have new issue
for instance
i  have a   RAW material A  used in a Product A  when i do confirmation system can able to do back flush with movement type 261 K
i am using same RAW material A used in product B and when i do confirmation system give me a error
as below
Pipeline/consignment movement posted without value
Message no. M7234Diagnosis
The system has determined a consignment/pipeline price of 0.00.
Possible reasons:
The system could not find any valid condition for the posting date in the consignment/pipeline info record.
A price of 0.00 was defined in the info record.
System Response
Depending on how the system is configured, the message can be either a warning or an error message.
A withdrawal from this consignment stock or from the pipeline will not create vendor liabilities. For materials with moving average price control, withdrawals are posted without value. For materials with standard price control, a price difference posting is carried out.
The message is also issued when materials are received into consignment stock, as the system must check whether a consignment price of zero is required.
Procedure
If you have authorization, check whether the conditions or the price has been defined correctly in the info record, if necessary. If there is a condition with a price other than zero, check whether the posting date of the movement lies within the condition's validity period.
Proceed
just wonder does any one have this issue
so strange i can issue to product A and not product B
Please help me if you have any problem
Rgrds
Raj

Similar Messages

  • Cost of UNBW Material in Process Order

    Dear Gurus,
    We have created UNBW Material for Raw Water used in our production process.
    (Since we dont want any accounting effect of the raw water we have created it as UNBW Material)
    Now when I do costing of product X which uses raw water the cost of raw water is getting added to arrive at the standard cost of product X.
    But in the process order report "KOB1" though PP has confirmed the material the cost of it is not calculated.
    Please guide how to bring the cost of raw water in the actual process order report of product X.
    Thanks and Regards,
    Amit Dhanurdhari

    Hi,
    As you have mentioned that it is a UNBW material, it carries no value and in real time absorbed as some expenses.
    There is no price for this material and there is no account to capture the consumption as this material goes directly
    to expense account.  Apart from that you require that no fi entry is needed.  Let me put in this way now.
    Create Raw Water Consumption as a secondary cost element.  Create Activity type Raw Water and assign this
    cost element.  Define activity price for this activity type for a cost center through KP26.  Assign this activity in
    a work center (this material need not figure in BOM).In OKTZ cost component structure enter this cost element
    and assign it to Cost Center/Order.  In this you have only CO postings for the cost estimate and no fi postings.
    Regards,
    Sadashivan

  • Batch Determination for material in Process Order

    Hello,
    I need to set up a Batch determination strategy for the Raw material at IM level for a Process Order.
    Basically the materials are Batch Managed and already have a Batch number assigned to it.
    I just want to use a simple strategy of determining material with the oldest GR datel(FIFO) during the Process Order creation/release or during the Process Order confirmation.
    Can you guide me how to set up the strategy and the conditions to do a FIFO for the materials during the Process order.
    Thanks in Advance
    SAP FANS....

    Hi,
    Only Problem with this FIFO strategy in which you want to do Batch Determination with reference to Oldest GR date is GR date itself.
    Batch determination will only possible if Batch Characteristic values are maintain.What I have observe for this GR date is if we use this as a Reference Characteristic in that case also Value is not set automatically in the Batch Data, so value of the GR date is maintain manually.Pls check it your end if no problem then The rest of the things for Batch determination are not difficult.
    Use below link for Batch determination,
    [Batch Management and Determination |Re: Browser Based PI sheet]
    Regards,
    Dhaval

  • Auto GR creation against PO after consumption of material in Process order.

    Hi GURU's
    My client is asking about automate GR against Purchase Order when he confirm the porcess order of GR consume material means when he confirm the process order, the GR is created for the comsume material( GR must be equal to consume qnty) against Purchase Order.
    1) Is thier any material type issue
    2) what are the setting need to be done
    Please take an Urgent action bocs its a critical point to me solve.
    Hope for the best for ur response.
    My ID:- [email protected]
    Thansks in to all
    Parminder

    Hi Guru's
    My Requirment is...............
    Suppose I have material  X (GAS) type ROH.
    I have already made  a monthy base Purchase Order this.
    We Get GAS through Pipe Line.
    stock my be vary( zero or some stock)
    my question or requirement is when I create a Process Order for Material Y where this Material X is consumed ( 261 Mov Type).
    When I confirm the Created Process order for Material Y(suppose 20) & require quantity of X for this Material Y is 40 & we have no stock or may be less than the require quantity at this time system check the availability & Generate GR for this material X against Related Purchase Order or If have Multiple Purchase Order then ask for Purchase order selection & then post the Confirmation (GOODS Movment).
    Hope u understand my requriment ,Please suggest
    Thanks
    Parminder

  • Requirement calculation of material in process order

    Dear Friends,
    we have one raw material whose base unit of measure is maintained as CAR (cartons) and the unit of issue is in EA in material master.
    now, when we create the process order of Header material, the system calculates the requirement qty of raw material in EA and this is properly shown when i click the material icon for the details of componen.t
    but when i click the icon of material availability check the system gives the message as missing part list even if the current stock fulfills the reqmt. qty.
    hereafter when we click the missing part list overview the reqmt. qty is calculated as per the base unit i.e. in cartons , it rounds of the figure obtained and re-converts to the unit of issue as in EA.
    for eg.
    one carton contains 1472 pcs EA
    required qty of x material as per process order is 16000 EA ,
    when we click on materials icon it shows the figure as 16000 EA correctly,
    but now when we check for material availability and seee the missing parts overview , here the requirement qty is shown as 16192,
    system calculates as follows:- 16000/1472 = 10.869 cartons,
    here it rounds off to 11 cartons and equivalent of 11 cartons is 16192 EA.
    so if, say for e.g. my stock of raw mat. is 16000 EA which can fulfill my reqmnt as per BOM but due to the above calculation shown the release of order is rejected.
    please suggest for the issue to get resolve.
    thnx in advance
    rgds
    Amitabh Rathod

    Dear Amithab,
    Frist thing is always ur base unit of measure should be the minimum one. in ur case u hae done ulta.your BUM sholud be EA and yor altrnative unit of measure should be CAR this u define in material master basic data view. at this piont of time system will not allow u to change unit because stock and other movement document exists.
    Now the only solution to get CAR in exact decimals ask ur MM consultant to enable 3 decimal placess for the unit CAR in SPRO, then ur issue will be resolved
    sree

  • Info Related to Material No, Process Order No

    Hi Gurus,
    Can you tell the Master and auxillary tables related to Process Order No, Material No and Plant.
    I have to run t-code : COPI
    which is used to generate Feedback list ( Process Order )
    I have Process Order no with me but do not have material no and plant...From which table can i obtain the same..
    Thanx,
    Navin..

    Hi,
         You can try the tables AUFK, AFPO, LTAK, LTBK.
    <REMOVED BY MODERATOR>
    Edited by: Alvaro Tejada Galindo on Jun 12, 2008 4:17 PM

  • WM material staging & process order

    HI Team,
    1. Is there any relationship between the control cycle with the TR creation process in process order?
    Suppose there is one process order created (COR1) with production schedule profile saying 'No creation of transfer requirement on release'.
    So this time no matter what, the system will not create any TR while releasing the process order, is this correct?
    2. Suppose there is a process order for finished good 'A' and 'B' is the component.
    Process order is having production schedule profile saying 'Only creation of Transfer requirement on release'.
    Now control cycles are maintained for material 'B" with material staging indicator '3'.
    Would the TR be created while releasing the process order?
    Is there any relation between the control cycles and the process order and also with production schedule profile?
    Please advice on the query in detail.
    Thanks,

    The system determines the material staging type on the basis of the control cycle and determines the production storage bins, in which the components should be staged. 
    Please take a look at this topic: WM-PP interface - material staging
    This information: Material Staging - Warehouse Management System (WMS) - SAP Library
    And this one too: Control Cycle - Warehouse Management System (WMS) - SAP Library
    This will help you understand the staging process in detail and is quite easy to read.

  • Reverse Material Ledger Process Order Revaluation

    Hello,
    I have settled process orders for Material Ledger and revalued them.  More postings have been made after this has occurred.  How do I reverse this process?
    Thanks for any help you can give me.
    Joe

    Hi
    Go to the following path in SPRO:
    Controlling -> Product Cost Controlling -> Actual Costing/Material Ledger -> Actual Costing -> Activate Actual  Costing. Double-click on "Actiavte Actual Costing" and change the indicator from "2" to "1".

  • Hide Back Flush Indicator and Bulk Material Indicator in PM order

    Hi Experts
    Can any one help me, how to hide or display Back Flush and Bulk Material Indicator in PM order Components tab. Can we customize this or we need to do the modification in standard program.
    Thanks is advance
    Regards
    N.Saidasan

    Try to hide it my using transaction variant tcode SHD0
    If it dosent work then use
    User exit 
    IWO10009 Maintenance order: Customer check for "Saving"
    PPCO0023 (check changes to order components)
    BADI
    IWO1_ORDER_BADI
    This will solve your problem

  • REM Back flush using firmed planned orders

    Dear Gurus,
        We are using REM manufacturing process in SAP , we are doing backflush for stage wise confirmation and final confirmation.while doing this we are not referring any planned orders as reference.
    if we update new part numbers in BOM the system asking for the availbilty of that particular new part numbers but physically we are having old materials .
    we want to consume that old materials how it possible in the MFBF t.code.
    if any one please help me ,  if I firmed a planned order with quatity or date then sytem will ask the old materials instead of new one.
    pls explain what is planned orders and their impact on MRP ?
    how we can firmed that planned, if i firmed what is the impact duirng backflushing?.
    Thanks & Regards
    Suresh babu.s
    WIN - IS.
    Suresh

    Hi
    please compare the process when you create the production order manually in Co01 instead of creating the production order by converting the planned order.
    Here you are carrying out back flush with out refering the planned order.
    It is like creating the production order manually.
    In such case system will always look the BOM as of now.
    It will not refer any of the planned order & the components there in.
    If you want to consume the old parts instead of new parts , you can delete the new part numbers & add the old ones in MFBF. this will be allowed by system.
    In this case you are back flushing with out reference to planned orders.System will not ask for old components at all whether planned order is firmed or not.
    Once if planned order is firmed a star (*) mark will appear in MD04 near the planned order number.
    Once if the planned order is firmed, it will not be changed in subsequent MRP Run.
    Hope it is clear.
    Pl. award if it is clear else pl. update.
    Regards
    YMREDDY

  • Goods Receipt for Material which has no Standard Price in Process Order

    Hello everyone, is there a way by which we can prevent GR for process order which contains material that does not have standard price? And if ever we received material using process order how can we correct the process order right after we correct the standard price.

    Hi,
    i just don't know why you raised new thread as already ur previous thread is not closed
    Now just let us know whether system is throwing any error
    or what exactly happing in cofirmation screen
    Go to OPK4, here
    under goods movement there is option all components  just tick it
    then in second tab Gen individual entry tick Goods movement & termination for incorrect goods movement
    Coming to GR
    what is storage location ur giving
    just check in MMSC, whether this storage location is activated for the header material ( GR )
    Added
    Plz Go through all possible options
    [Auto GR is not happening.;
    Regards
    kumar
    Edited by: kumar kumar on Nov 10, 2009 2:25 PM

  • MTO material - Combine three planned orders into one process order

    Hi Gurus,
    Does anyone know if and how I can convert three planned orders of the same material into one process order?
    So:
    1.
    Sales order 1 (material X) --> generates Planned order 1
    Sales order 2 (material X) --> generates Planned order 2
    Sales order 3 (material X) --> generates Planned order 3
    2.
    Process orders 1,2,3 (material X) --> Process order 1
    3.
    Process order 1 --> reserved sales order stock for sales orders 1,2 and 3

    M,
    One process order cannot create Sales Order Stock for three different sales order items.  A single process order can produce Sales order stock for AT MOST 1 sales order/item.
    This scenario can be achieved under a Make to Stock environment, where the production order creates 'generic' stock (not sales order specific).
    Best Regards,
    DB49

  • Can we assign process order in MB21 RESEVATION for extra material

    Sir,
    in Production sometimes we required extra raw material but already we issues raw material against  process order then that time where we assign extra raw material in process order or where we check costing of extra material qnty aginst process order.
         can we asssign extra material against process order in MB21 with movement type 261

    Dear,
    It is not possible to create the manual reservation against the order for 261 movement type. Because system generate the automatic reservation for an order whcih can not be modified. Better you go for component or operation scarp to plan the extra requirement. MB21 you create the reservation with 311 movement here you give reference of an order also maintain the long text for same. By this you can transfer the extra consumption from main storage location to production storage location. And issue material against the order with MB1A 261 against the oder as unplanned consumption.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Basic and scheduling  dates & time calculation in process order creation

    Hi guru's,
    i have one requirement, i need to calculate and display the basic and scheduled dates & times based on the given input i.e material , plant , process order type , quantity , UOM and scheduling type ( for corresponding scheduling type user will provide either start date or finish date ) using RFC. can  u plz provide any function module for this purpose or logic for calculating the same  , as i am working on version 4.7ee .
    Awaiting for a quick response.
    Regards,
    Madan

    Dear Rohan,
    1.Check the length of break timings defined in the resource that is assigned in the phase.
    2.Check in OPUZ whether for the process order type and plant combination whether scheduling is to include the break time also
    (whether the check box for scheduling with breaks) is included.
    Check and revert back.
    Regards
    Mangalraj.S

  • Goods Receipt against Process order mvt 262

    Hi,
    Is it possible to not to receive material against process order (262 mvt) if it is not issued using process order using 261.
    Do the needful.
    Regards
    Mohan

    261 and 262 are two different movement types INDEPENDENT of each other. I definitely know for the fact that SAP allows you to create a 262 without a 261. if you were to restrict it... you can disable access through a tcode for that mov. type 262 and ask users to use MBST to cancel any material documents created via 261 movt type.. that would ensure a smooth process

Maybe you are looking for

  • I cannot see text when in a chat session

    I started an online class that has chat sessions. I could enter the chat room, but could not see my text or anyone else's. I could see that I had successfully entered the chat room. I was using java applet.

  • Switching themes with customized templates

    Most typical Apex applications start with a quick prototype containing most of the required functionality, get required approvals, and continue building it up. During all of this, the concept of "themes" is mentioned and demonstrated as a reassurance

  • Help needed applying OSS note 981295 in SAP ECC 5.0 with SAP Kernel 640_REL

    Hi Experts, Our functional team is trying to implement a kind of workflow through a notification via SAP Inbox (transaction code SBWP) after the release of a Purchase Order (Transaction code ME29), this is every time when a purchase order is released

  • Help.. Pricing error: Mandatory condition 0PR0 is missing

    I've been having this warning message everytime i try to use a " zero priced" item in CRM 4.0.. Part of its effect was, the "message number" for this particular warning message contains invalid characters (such as '###' or 'CH' etc..) which gives us

  • Synchronization between B1 and third party software

    Hi Experts,            Is it possible to synchronize between SAP B1 8.8 and Third party software.Here the third party software comes as 'LIBSYS' which is used for Library purpose.so we need to synchronise some data between B1 and Libsys.So if i have