Backflush partial confirmation
We currently have 3 operations attached to our material routing. Is it possible to backflush on a partial confirmation in co11n?
To clarify, when confirming a partial quantity of a production order for a particular operation (when the material is moving from one operation to the next), can we backflush the BOM for the material?
run CA03 for your routing:
-for each operation in your routing you have a Control Key (just in case use OP67) - check the completion confirmation in your key
-for each operation you also have a Work center - check 'Backfluch' tick there:
each material component is allocated to an operation in the production order. if a material component is backflushed, the system automatically posts the withdrawal when the operation is confirmed
and..
this indicator is taken into account if the material master specifies that the decision whether a material component is to be backflushed should be made at the work center where the operation is carried out
for your BOM components run MM03 and check Backflush field (MRP2 tab) - if your work center decides to backflush you need to have '2' in this field
Similar Messages
-
Report for mass interruption of partially confirmed orders in PPDS?
Hi gurus,
our client has a lot of partially confirmed orders in the past, and this is giving us problems with the optimizer.
Is there a report for mass interruption of this orders?
We can do it one by one in the DS planning board, but there are too many!
would appreciate any help,
PabloHi Pablo,
I would suggest you can close the partially confirmed orders at R/3 itself
so that it will update in APO via CIF.
There is delivery complete indicator in R/3 production/process order which
upon checking will close the order.
Regards
R. Senthil Mareeswaran. -
Partial confirm on customeru2019s order quantity for EDI sales order
Hi All,
Our company is using ECC 6.0. We seem to having issues with orders coming through EDI u2013 i.e. it will not partially confirm what we have in stocks and just reject the whole line. E.g. If the customer is ordering 300 units for an material and we have 200 units in stocks only, it will zero confirm instead of partially confirm 200 units. If I try to manually key in the same material in the same sales order then it will partially confirm it (I.e. 200 units) instead of zero confirm.
I have checked the ATP check rules and it seems everything alright. Any idea why this would happen only for EDI orders? Are there any EDI setup that will cause this issue? Any ideas where I can looks for the potential issues might be?
Thank you.Evidence,
What happens when you enter the order manually (VA01)?
Best Regards,
DB49 -
Purchase to Order Scenario - Partial Confirmation Issue
Hello Team,
We are using Item Category with Purchase to Order Scenario. When the Sales Order is booked, Purchase Requisition is Created. Sales Order Line is linked to the Purchase Requision/Purchase Order.
In this scenario, we are getting confirmation on Sales Order through PR/PO Initially.
Order Quantity Confirmed Quantity
10 10
Once we receive partial confirmation on PO let us say 7 system only confirms partially Sales Order.
Order Quantity Confirmed Quantity
10 7
Issue happens when our team does partial delivery to customer before receiving full confirmation from the Supplier. System blocks further update of confirmation on the line and it becomes impossible to make delivery to Customer for Partial Quantity.
I can think of two options...
1. Somehow when we receive Partial Cofnirmation, our Availibility Check should confirm 7 on Confirmation recieved from the Supplier and 3 from Delivery Date of Purchase Order. So this issue won't happen.
2. System should somehow allow Partial Confirmation even after Partial Delivery is done to the Customer.
Do let me know if you need any more details from my side.
KaushalHi Kaushal,
i assume that you have special stock indicator in your sales order.
if you do not use confiramtion then all quantities are confirmed at schedule line level.
if you use confirmation e.x. 7 of 10 pieces then you will have confirmer 7 quantities in your schedule line.
if you create another confirmation in PO of 2 pieces and lets say different date you will see another schedule line in your sales order.
do your system works like this?
Is your third party scenario require a googds receipt for PO to move on to delivery?
Regards. -
Operation time calculation based on partial confirmation.
Dear FRndz,
Pls help me out with following scenario.
1.Am defining a task list in which am mentioning the set up time as 30 min & operation time as 10 Min per peice of finished goods.
2.Creating a production order for 10 Pieces.
3.Am doing partial confirmation of 5 Nos.
At this point of time I want the system to calculate the timings appropriately for 5 peices.how do I configure it?....
REgards,
SriniDear,
Go to TCODE :OPK0
This is the single screen entry for confirmation.
Select the profile you are using & in the tab Defaults
go to section default values & select "IMMEDIATE PROPOSAL"
in both "quantities & services"
It will definitely work.
Regards,
R.Brahmankar -
CM01 not updating upon partial confirmation of an activity in order
Hello PP Angels,
I am looking for an explanation for this.
When a production order is partially confirmed, (using CO11N),
for an activity -- say labor time.
(and do not confirm any quantity )
subsequently, on checking the CM01 Standard Overview,
I find the report unchanged, under the requirements column.
(for the week concerned)
But the same ( capacity requirements) gets reduced,
for the relevant week,
on doing a partial confirmation of production order,
for a value in the "Yield" field in C011N.
Is this the standard SAP behavior ?
I am in ECC6.
Thanks in advance !Thanks for the reply !
I have tried it
It does work,
there is a change in the cap reqmnt column in CM01
But the value is not as expected, as explained below.
CM01 shows initial cap req as 33.5H
After confirming the production order
for 10 minutes (0.1667 H) of set up time
I would expect the Cap Req Column to have a value of 33.5 H - 0.1667 H = 33.3 H
but CM01 displays only 0.17 H
( I have created this scenario such that CM01 reflects only one production order.
So there is no mix up of data. )
Can we see how the Cap Req column in CM01 is being calculated, (the details)
I did double click the cap Req value in CM01
and it shows the relevant production order,
but no further details can be viewed pertaining to the calculations.
Thanks in advance !!! -
PO Partial confirmation Quantity not updated for non-catalog items in SRM
Hi Experts,
Partial Confirmation plus Partial Rejection from Ariba(Suppliers network) could not be processed.
Steps to Reproduce:
1) Create a purchase order.
2) Confirm some part of the quauntity and reject the balance part in Ariba.
3) Open the link in SRM and click Copy push button.
4) Click on Process PO and check PO, the PO is not updated with the changes done in Ariba
Expected Result:
PO should update the changes done in Ariba.
Here when part quantity is confirmed and part is rejected at Ariba, its sending a POR but SRM is not updating anything for non-catalog items when POR is copied onto PO.But where as in the Catalog items partially confirmed POR is copied onto PO.
kindly give your valuable inputs to poceed furthur.
Regards,
ChanduHi,
I'm not clear you issue. Is it SC -> PR(backend) -> PO(backend) classic scenario ? or You just created a PO in backend system?
BBP_GET_STATUS_2 will update SC follow-on doc information from backend.
Regards,
Masa -
Partials Confirmations - QTY's not getting picked automatically
We are facing issues, where we are doing confirmations partially. Intial confirmations
are done for a set of quantities followed by confirmations for remaining quantities for that
production order. The problem is system is not picking the remaining quanities automatically
We are plugging in remaining quantities manually before doing confirmations
Is there a configuration setting, where we can popluate the remaining quantities automatically
Transaction Used: CO11n
Client: ECC 6.0
AFS ImplementationThanks for your replies
The given setting was already maintained, but still system was not populating the remaining qty's
more appropriate way is to, change the quantities in the intial front screen of CO11n, rather than
changing the quantities inside CO11n (click through goods movement tab)
By changing the Qty's in the intial screen of CO11n, helps in populating the remaining quantities
during next partial confirmations
Due points have been assigned -
Production Order Partial Confirmation Report
My requirement is to write a report to get all the partial confirmation time, date and Qty of a Production Order. Which table stores the relevant information? Kindly help me.
ThanksHi,
Check with AFRD,AFRU, AFRV RESB, AFKO,& AFPO tables.
Regards,
Maha -
Can we restrict the partially confirmed production order from getting delet
Dear all,
Can we restrict the partially confirmed production order from getting deleted?
I.e. if the production order is having status PCNF then the deletion flag indicator (status DLFL) should not be allowed to set
SmanS
Edited by: SAP PP Consultant on Feb 4, 2009 6:12 AMHi,
Then must be there is change in BS22.Check allowed transaction setting for Status PCNF/CNF .For reference purpose compare it with other client IDES or sand box.
For your reference I have pasted Error log on the same.
Balance of ORD 1000000702 is not zero
Message no. KO115
Diagnosis
The balance on object ORD 1000000702 is not zero. That is, there are still costs on the object.
System Response
The object cannot be closed and the deletion flag must not be set.
regards,
Dhaval -
BAPI for Partial Confirmation CO11N
Dear Gurus,
REG : BAPI
How to get the actual activites for partial confirmation of qty
we have tried some bapis like for getting activites we have used
bapi_prodordconf_get_tt_prop
but in this bapi it is calculating total qty i.e, order qty not for the yeild qty.
I need to get the yeild qty planned activites
Tks
MuraliHi,
Check the Bapis
BAPI_PRODORDCONF_CREATE_TT
BAPI_PRODORDCONF_CREATE_HDR
Regards,
Raj. -
Process Order Partial confirmation (PNCF) and Final Confirmation
Hi expert,
I'm already running t-code COHVPI to mass processing process order so it status change from TECO to CLOSED. But there is an error message "process order partially confirmed". Is that true if process order must be final confirmed before it changed to CLOSED. Should we change the status of partial confirmed (PNCF) to Final confirmed (CNF) before process order CLOSED.
Please give me a suggestion.
Thank you.Correct. Final Confirmation is THE signal to the rest of the world that that this order is DONE (at least from the GR standpoint). This will also retire the order from the APO/SNP radar.
-
Partial confirmation of production order
Hi,
My requirement is that when i partially confirm production order system should calculate the activity time(machine time) propotionately based on actual confirmed qty.
What is actually happening is that system is proposing the machine time based on full operation qty.
I will explain the case with following example:
Total Order qty - 20
Now when i do CO11N the system proposes full operation qty of 20 & also the machine time 20 hrs(based on data given in routing)
Now i when do partial confirmation of 5 units the machine time proposed is still 20hrs.
This is impacting my costing report( as it should consider 5 hrs instead of 20 hrs)
One more thing i want to clarify is that during confirmation we can change the machine time but requirement is that machine time should be in proportion to the confirmed qty(This is to reduce the confirmation effort)
I hope things are clear to you.
regards,
Mohit GoyalHi Goyal
I suppose you are in SAP version 4.6c & above.
you try in TCODE :OPK0
This is the single screen entry for confirmation.
Select the profile you are using & in the tab Defaults
go to section default values & select "IMMEDIATE PROPOSAL"
in both "quantities & services"
It will definitely work.
YMREDDY -
Workforce Planning for Partially Confirmed Activities
Hi All,
I have recently configured Workforce planning for one of the clients, and it has been working as per the requirement. Here, I have configured Workforce Planning profile and Scheduling parameters of Network. So, once a Project and a Network is created, User plans Personnel for this Network's activity using CMP2. Also, CATS profile is maintained in such a way that Worklist shows the Planned hours and accordingly a person can book Time against it.
Now, the problem arises after a Personnel assigned to an activity books the Timesheet. Once a Person books time against this particular Activity, it gets disappeared from CMP2 screen. Now, practical implications are that, suppose that person goes for a leave or leaves the organization and PM wants to assign another person for the same Activity (which is partially confirmed).
How can we address this issue - to perform workforce planning for Partially Confirmed activities?
Any pointers to User Exits, BADIs, BAPIs or SAP Notes are highly appreciated.Hi Sanjeev,
Thanks for your feedback.
In CMP2, we are already checking the activity work hours. According to that only we are adding resource, then checking that resource's availability and then assigning work.
As an example, activity work duration is from 20.08.2014 to 30.09.2014. I assigned a resource A from 20.08.2014 to 30.09.2014 for 8 hours because he is available in that duration.
Now, the real problem comes when this resource is suddenly unavailable (due to any reason) and PM comes to know about this on 07.09.2014. Resource A has already booked Timesheet for the duration he has worked (20.08 to 06.09). So activity is PCNF.
So PM wants to reduce the Work assignment for Resource A from 30.09.2014 to 06.09.2014 and assign Resource B from 07.09.2014 to 30.09.2014, but he is unable to get this activity in CMP2 view because it is PCNF. Here PM can only see activities of same project which are in REL status.
So how can I enable this PCNF activity in CMP2 view.
If there is any IMG activity settings, then let me know.
If this is standard behavior and can be done through User Exit/BADI/BAPI then also let me know.
Message was edited by: Aditya Kotak -
Restriction of posting date in transaction CO11N for partial confirmations
Hi all,
I am trying to restrict(by checking thru an exit) the posting date in co11n , for this i m using enhancement CONFPP04.
Import parameter AFRUD_IMP IS USED.
Now when i m putting production order no , operation activity no.(for e.g 10 , 20 etc ) and posting date IN SEL SCREEN OF CO11N
AFRUD_IMP-BUDAT( POSTING DATE ) CONTAINS VALUE in debugging mode , hence i m getting the value of posting date
and in that case check is written in code. This is the case of full confirmation.
But in case of partial confirmation i have to give production order no , operation activity no , *Partial confirmed qty * and posting date , in this case the posting date value changes to 0 in the debug mode ie.
AFRUD_IMP-BUDAT is showing 0 and hence no calculation can be done base on the date.
Our requirement is such that if there is a prd order no say X,
then in CO11N if user enters prd no X , operation activity no 10 , post date say D1
then again for prd no X , operation activity no 20 , post date of activity 20 should not be less than D1
SIMAILARY for X, ACTIVITY 30 , post date should not less than that of activity 20. and so on.
But if partial quantity is mentioned value of AFRUD_IMP-BUDAT is becoming null.
If anyone knows about this scenario please share.
Thanks and regards
Pankaj GuptaHi, In the T-code Mb31
The Posting Date which is used is when entering the document in Financial Accounting or Controlling. The fiscal year and the period for which an update of the accounts specified in the document or cost elements is made, are derived from this posting date.
When entering documents, the system checks whether the posting date entered is allowed by means of the posting period permitted.But this posting date can differ from both the entry date (day of entry into the system) and the document date (day of creation of the original document).This is for the practical purpose .
So its for the Monthly permitted and not for a day or range .
Secondly when you are saying :
"We want this <b>default date to get freeze</b> the moment you enter
the transaction (MB31). If you are opting for second option we want
<u><i><b>some flexibility to change the date as required</b></i></u>."
Both freezing and opting for changes is not possible , either one can occur .
You can freeze/display mode only the field for the T-code and the document type, but that will not solve your problem .
What i understand from the description is you want to Do GR on A particular date or GR should be allowed after a particular date . <u><b>Please let me know</b></u> if this is the case then there's a way around to do this that is you can do GR and Post on the dates near to your desirable dates .
cheers KP
Maybe you are looking for
-
[SOLVED] drm:radeon delays xorg start for 30 secs
Does anyone knows about a reason why starting the X.org server could take over 30 seconds? Jun 19 15:15:59 Arch kernel: [drm] Initialized drm 1.1.0 20060810 Jun 19 15:15:59 Arch kernel: [drm] radeon kernel modesetting enabled. Jun 19 15:15:59 Arch ke
-
Is there a TLOG? What's wrong?
Hi, How can I find out if my application has a TLOG device configured. In the dmconfig I see that the parameter DMTLOGDEV is set. Often I see this following error in the ULOG - LIBGWT_CAT:1042: ERROR: Can't open domain log What could be going on? Wil
-
How do i get my apache and php server ?
Hello, I want to be able to test my php page through my computer. How can i do that? I am very new to php and apached stuff. I have on my mac 10.4.3. How would you do it? Thanks
-
How can I get into my Photo Vault from my computer? Lost my Iphone
How can I get into my Photo Vault from my computer? Lost my Iphone
-
Can't Enable On Board Graphics
HP Pro 3500, Windows 7 Proffesional I bought an EVGA 8800 GTX Video Card on E-Bay (due to low budget) for $55, the seller said that it was used yet in perfect working order. I installed it, and when I attempted to boot up the system, a long whine was