Hi expert
i have a raw material with base unit of messure in kg which was assigne in BOM as kg
but recently one vendore supllying the same material as base unit of messure in meter
Now i want to change the material base unit of messure as Meter how it is possible
i have stock in kg aroung 50,
Faisal

We can add  alternative base unit of messure in bom?
Dear You should create BOM componenets in Base Unit of measure or Unit Of issue.
In case of BOM component maintain Unit of issue as meter in plant data storage location view In Material Master and add the   Item in BOM-CS02.
Cheers
KK

Similar Messages

  • Unit of Messure issue

    Hi, All,
    I have a question on Unit Messure. What happened if Unit of Messure in General View is different the Unit of Messure in Purchasing View in Material Master Data? Can I change Unit of Messure in Purchase Order? Then do a goods receipt in different Unit of Meesure? In Info Record, Unit of Messure can be covereted? Then during procurement process automatically converted?

    What happened if Unit of Messure in General View is different the Unit of Messure in Purchasing View in Material Master Data?
    Base Unit of measure is same ,only you can give ordering unit in purchasing view
    Can I change Unit of Messure in Purchase Order?
    If you change unit of measure while creation system will automatically converts qty according to your ordering unit
    Then do a goods receipt in different Unit of Meesure?
    I think you can't.System will automatically post as stock keeping unit maintained in Material master.
    In Info Record, Unit of Messure can be covereted?
    You can give ordering unit.If you create Po with respect to info record system will pick UOM from inforecord.
    Then during procurement process automatically converted?
    UOM automatically converts as per data maintained in material master automatically.
    Hope this would help.

  • Follow up material with different base unit of measure

    Hi all,
    I have the BOM with material Mat1 as a component. The base unit of measure of Mat1 is KG.
    Is it possible to replace Mat1 with Mat 2 material in MRP once the Mat1 warehouse stock is depleted.
    The base unit of measure of Mat 2 is KGK.
    The required quantity of MAT1 should be recalculated from KG to KGK accordanly unit ratio.
    Please, expain, where does it maintain?
    Thanks,
    Peter

    Hello Peter,
    You can use follow-up setting (set Mat2 as follow-up of Mat1 in MRP 4 view of material master if this follow-up scenario is valid for all BOM) with discontinuation indicator '1', w/o effective-out date. In this case Mat1's stock will run out (no PldOrd, PR, etc) will be created, and from the date, when Mat1's stock runs out, MRP will calculate with Mat2.
    As I told you, according to my best knowledge, you cannot realize this with different base unit of measures. (you have to change the buom of one of the related material masters or create a new material master if you cannot cope with buom-change).
    Follow-up group scenario can also be used but I guess different buoms will be a problem in that case as well.
    Maybe there are better solution but I'm not aware of it...
    BR
    Csaba

  • Can you hook up multiple pairs of wireless headphones to the MDR-DS6500 base unit

    Can you hook up multiple pairs of wireless headphnes to the MDR-DS6500 base unit or do you need a base unit for every pair you would like to connect to your tv? if you can which models are compatible?
    Thanks

    Do I need an AirPort to attach to each set of speakers that I want to connect, or is there another kind of receiver I can hook up to the speakers that do not have any kind of WiFi or Bluetooth configuration?
    You basically have two choices: 1) Place an AirPort Express base station at each of the speaker locations, or 2) Use an AirPlay-Ready receiver that offers whole-home audio support. The latter would require that all speakers be connected back to the receiver.
    Also, if I am planning to set up the airplay by using the extended network configuration, then the Wifi base station does not need to be an AirPort station? I have Fios and had trouble last time I tried to hook up an AirPort in place of the router that they provided.
    The AirPlay networking protocol requires either a wireless or wired connection between the AirPlay server (typically iTunes) and the AirPlay speaker (AirPort Express, Apple TV, or an AirPlay-Ready receiver or speaker). AirPlay will traverse over an extended Wi-Fi network regardless of which manufacturer hardware is used.

  • Base unit of measurement while saving production order

    Hi
    While saving production order I am getting following problems:
    "Material has no base unit of measure"
    Whereas UOM is there, I also can see that as soon as I  enter qty while creating the order. System automatically prompts the UOM.
    I also donot find any problem in MRP run, planned order creation etc
    So what can be the problem?
    Edited by: BNR on Nov 24, 2008 5:22 AM

    Dear,
    It may be data base problem as you are getting this problem fequently so please check with Basis person.
    Have you defined the any production unit in both material master WS view & in routing or any other alternative unit of measurement please check?
    Regards,
    R.Brahmankar

  • Base Unit Of Measurement error

    Dear Sir \ Mam,
    Our some materials base unit of measurement is in KG, and we want to make bills, excise RG1 entry in KG for milligram sales or material transfer. How to go for such transaction, system is not allowing for such transactions.
    Pls Note : We can't create two separate materials code for these UOM issue materials.
    Requesting a help.
    Regards,
    Randhir Padwal

    Hi,
    As per my understanding you have base unit in KG and you want to material issue and sales in miligram unit. If this is requirement then you may try to assign "sales unit" for material master in "sales:sales org1" view. you have to also give the conversion rate from KG to miligram in additional data.
    for issuing you have to maintain issue unit "miligram" in material master view "Plant data/stor1"
    Regards,
    mukesh

  • Material Master MATMAS IDOC and base unit of measurement

    Hi
    We are using SAP standard material master IDOC type MATMAS05 to trigger IDOC. Our material master is having base unit of measure as "G". We are not using ISO unit of measurement. But Material master IDOC, segment E1MARM is populating base unit of meaurement (MEINS) as "GRM".
    Any idea why IDOC is picking ISO unit of measurement instead of material master base unit of measurement.
    Any idea how to send base unit of measurememt as "G" instead of "GRM" in DOC segment.
    Thanks
    Nilesh

    There are ISO codes for country keys, currency keys, units of measure and shipping instructions. According to SAP design guidelines, you should use ISO codes for an IDoc if they are available. When you set up the IDoc, the SAP codes have to be replaced by ISO codes.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/BCMIDALEPRO/BCMIDALEPRO.pdf

  • Base unit to change in material master

    we  assigned base unit of measurement to one of our material code say KM and after that we created routing .When we come to know that base unit is wrong and instead of KM base unit required was KG then we delete routing for the material.After that when i tried to change base unit of meas. in mat master system is giving me error
    Routings already exist that are assigned to the material.  
       RType RtgGrp   GpC Plant                                
       N     50013509 1   UHVC                                                                               
    I want to know how it is possible?
    Is there anything remain?

    If SAP tells you that you have routing, and even shows which one, then oyu have not really deleted it.
    BOM Deletion - Transaction CS02, open the BOM header view and select menu "Material BOM > Delete.
    Routing Deletion - Transaction CA02, select the routing overview button and select the routing line to be deleted, press the deletion button.

  • Error while changing base unit of measurere

    Dear
            i hav prob. while changing base unit of measure system gives error massage is material used in BOM, ECM is activated in our system and that material is showing only when valid from date is not  entered othervise that material is not shown in BOM.how to remove that material from so i can change base unit of measure.

    HI
    You can only change the BUM if there is no stock  production order planned orders reservations, PO s etc are not in the system  there should be no transaction of the material ,after ensuring all this, u can change unit of measure
    For more info
    check these threads
    Base unit of measure cannot be changed
    Re: BOM unit of measure
    change base unit of measure
    Regards
    Anupam Sharma

  • Changing Base Unit Of Measure in Material Master

    Dear All,
                  We need to change the base unit of measure of certain materials who have been assigned inspection plan. We have deleted the material from Inspection Plan and later even the plan. But still the system not allowing to change the BASE UNIT OF MEASURE. The error thrown by the system is : Material is assigned to inspection Plan.
    Please guide in this regard as changing the material for us will be a very cumbersome act.
    Regards

    Hi Rohan,
    Please check 'display errors' in MM02 when you are trying to change the BUoM. It will say what prevents you from doing that.
    Please check:
    http://www.sap-img.com/materials/change-base-unit-of-measure.htm
    BR
    Csaba

  • How to correct CIF error Base unit of measure does not exist?

    Dear experts,
    I'm trying to cif a location product with base unit of measure KG in R/3 and alternative unit of measure well maintained.
    it gives me a CIF queue saying that
    "Base unit of measure ZXX does not exist (Product 0000000000000XXXXXX has not been created)"
    I do not understand why, the unit ZXX does not exist in the alternative unit of measure for any of the materials managed
    I also checked CUNI table and ZXX is not there neither in R/3 or APO,
    Thanks for your help
    E

    Looks like the Alternate UOM --Zxx is not maintained in APO.
    2 ways to do this:
    (1) program- RSIMPCUST
    Re transfer all your UOM settings from R3 to APO
    (2) Manual Maintenance in APO:
    SPRO>SAP NETWEAVER>GENERAL SETTIGNS>Check UNits of Measurement
    Thanks
    Kumar

  • Views and Base unit of Measure is not coming in Chines Lang

    HI All
    Plz Help me.
    I log-In Chines Server, during MM01 the views are coming in English language instead of chines.
    and  during PO creation The Base unit of Measure is not Coming in Chines Language it is displaying Some number??
    I have maintained Source and taget lag in CUnI..but still Im getting this problem..
    How to solve this plz help..
    Thanks and regards
    Ramesh reddy

    Hi
    Please maintain the translation in the Following Configuration
    Logistics - General->Material Master->Configuring the Material Master->Define Structure of Data Screens for Each Screen Sequence
    Select the Specific Screen Sequence & Maintain the languages
    Similarly please maintain the Translations in the Transaction CUNI for the Base UOM in respective languages
    I hope currently in your system only Language EN is maintained
    Thanks
    Madhav

  • Base unit of measure can not be changed since EAN is already assigned.

    Hi,
    We would like to change the UOM from EA to SET .In order to tag MM # as BOM Header and ZCEN (Serial number profile)but the error massage appears as below print screensystem is not allowing to do so ,throwing following error message:
    "Base unit of measure can not be changed since EAN is already assigned."
    Could you help to resolve the same.
    Thanks,
    Amit

    Hi,
    Thats correct you must be getting Error message M3 341 ,
    EAN international article number is tied with material number in basic data view with EAN Category and seperate number range
    EAN is a standardized unit that uniquely identifies a material relating to a unit of measure or type of packaging.
    The International Article Number (EAN) is assigned by the manufacturer of the material. In this case, the EAN identifies the
    manufacturer uniquely. A company can assign EANs using "in-store" numbering techniques known only to the company.
    If you still want to change UOM you need to first remove the EAN assigned..please explore further if you have internal number range
    for EAN or external ..etc
    Thanks
    Diwakar

  • Item category N: Only base unit of measure EA allowed,Message no. CO344

    Dear all
    I am facing  the following  issue,
    Item category N: Only base unit of measure EA allowed
    Message no. CO344
    Diagnosis
    You have entered a unit of measure for a component of the item category N which does not correspond to the base unit of measure maintained in the material master record.
    Procedure
    Use the base unit of measure maintained in the material master record.
    Please give  the solution  for how do handle that issue.
    Thanks&Regards
    K.Muthukamatchi

    Hi
        My requirement is: The item category N should allow me to use alternate UOM.
      When i checked with Item category L, the system allows me to use alternate UOM. I need the same to work for Itm category N also.
    Through  forums, i found that, in standard SAP, system will not allow to use alternate UOM for Item catedory N.
    Is there any config settings to be done for my requirement?
    Kindly do the needful.
    Thanks & Regards,
    K.Muthukamachi

  • Cannot switch base units on Goods Receipt PO copied from Purchase Order

    Hi,
    I am wondering if there is a simple trick or setting for this or if we have to use a UDF/FMS...
    When using Uom for sales and purchasing, you cannot switch between Yes and No for base units on the target document(GRPO) when copying a PO to GRPO.
    For example, enter a purchase order selecting 'No' for base units and enter quantity 1 for item with Uom case(25 pcs in a case). 25 are ordered. If the warehouse receives 23 instead of a full case from the supplier,  they want to be able to enter 23 on the GRPO(copied from PO). They don't want the warehouse staff calculating what percentage to put in for quantity (23/25 = 0.92),  they would just like them to use the drop down box and change the base units to Yes and receive the quantity 23 units.
    Any suggestions?

    Hi,
    How often this would happen?  If it is very frequent, my suggestion would be considering it when you create PO.  You know, if you could change that option, the link between PO and GRPO will be broken.  It is not recommended.
    Thanks,
    Gordon