Baselin date as a recent GR posting date

My Requirement is to modify baseline date in MIRO to Recent GR posting date for which i have implemented BADI  'MRM_PAYMENT_TERMS  and its functioning properly in MIRO . after doing the payment and generating the invoice document number for same what i found is baseline date in invoice document in FB02 has the the same Date which was coming earlier in Material document in MIRO and not the recent GR posting date which is my requirement.
      i tried to do it by updating the invoice document for modify baseline date to recent GR posting date  in the same BADI but couldnt succeed as the invoice document number is generated after the call of this badi and hence coulnt modify the same .
   so can anyone please sugest me some other BADI and other work aroundfor it?
helpful answers will be awared.
Thanks in advance.
AVI

Edited by: SAP Learner on Jul 23, 2009 11:22 AM

Similar Messages

  • Error posting asset to company ''Specify payment period baseline date''

    Hi All,
    Please some can advise on the below error msg.
    While posting the asset in to company I will get error like ''Specify payment period baseline date'' and i cant go further.
    Please advise ASAP.
    Many Thanks
    Balaji A S

    Dear:
                   This error message normally appears if In the payment terms that you are using (can be seen in OBB8) there is no any default date assigned to the payment term. If it is then assign one like Posting Date or Document Date in OBB8 against the payment term you using. I am a bot confused in your case that why are you getting this error while acquiring the asset. Would you please elaborate the process you are using for asset acquisition.
    Regards

  • Posting date as Baseline Date in Residual item

    Hello,
    While clearing a document with Residual Clearing method through F-28 system is automatically proposing end of the month as Baseline Date for the residual item (newly created item for the balance amount), whereas we want it to be the posting/document date but not the monthend as proposed by the system. Eventhough we have selected the option for default baseline date as posting date/document date in Payment Terms, system is proposing monthend date as baseline date for the residual item. I have set payment terms in customer master record as 0001 (immediate payment).
    Because of the settings made for default baseline date in payment terms (SPRO/AR-AP) system is proposing document date as baseline date for new documents being posted, but we are facing problem only in case of residual items (new item created for the balance amount while doing residual clearing).
    Please let me know the procedure to change the settings, so that posting/document date will become default baseline date for the newly created open item while doing residual clearing.
    Thanks in Advance

    Hi,
    Try to take a look the setting of the following transaction,
    IMG> FA> AR & AP> Business Transactions> Incoming Payments> Manual Incoming Payments> Define Tolerances
    See what has been set for payment term for Residual Items.
    Regards,

  • Invoice verification Invoice date,Posting date and Baseline Date

    Hi Sap Gurus
    Pls Tell Me in detail what Dates should be entered at MIRO transaction,
    Invoice date,Posting date and Baseline Date
    i presumed that the date on the Invoice slip will be Invoice date,
    But in the Invoice the Date is very long back, say a month Older,
    the month of Posting as Posting date, but any posting Date made in MIRO will be Paid after 2 or 3 months so in this case what should be the Posting date.
    at Base line date in the present company Senario the Discount on Vendor payment is literally valid for all the time , say
    In Invoice if the condition is 10% discount if paid in 30 days is given.
    but in actual sense the Vendor is paid 10% less even if he is paid after 4 or 6 months also, so in this case what should be the Entry in Baseline date
    another senario is the vendor has sent only one Invoice for 2 POs how can this be accomadated in SAP
    Pls suggest its Urgent,
    Age may have a Bar, But Points No Bar
    Thanks and Regards
    Sathish

    Hi
    LIV is nothing but You are getting Invoice from the Vendor for your PO   and GR.....and you are checking the Invoice for Price, Qty,Amount etc. by refering the PO  and posting the Invoice...
    Invoice Date : 
               The date of Vendor' Invoice...ie) Date at which the vendor Raised the invoice for his supply against your PO...
    Posting Date :
       The Date at which you actually Verifying Vendor's Invoice and doing the Posting...
    base line date :
        Generally the Posting Date...
    The Imp. of Baseline date is for eg)
    If in the Payment Terms if some conditions are maintained like say
    10% Discount for Payment With in 30 days, if
    PO created on 01.11.2007.
    GR done at 10.11.2007.
    Invoice slip Received at 30.11.2007 but having the Date on it as 20.11.2007...
    So as per your terms you will get 10% Discount if you make the payment on or  20.12.07....
    Here if you keep  inv. Date: 20.11.2007  and Posting Date : 30.11.2007  and Baseline Date as  30.11.2007 ( you cannot maintain baseline date earlier than  Posting date)....even though as per terms the you are  eligible for discount if you make the payment on or before 20.11.2007.....as per the system you are still eligible to get the Discount if you make payment on or 30.12.2007( since you have maintained baseline date as 30.11.2007)...
    this way Baseline date is Importane...
    Generally we use to maintain always Posting Date as Baseline date....
    It is advantageous..
    Reward if useful
    regards
    S.Baskaran

  • Payment terms and Baseline date deact. during posting

    Is it possible to deactivate fields: Payment terms and Baseline date in FB60 and MIRO so that the user can't change them? Terms of payment are defined in Vendor Master Data and shouldn't be changed during posting.

    Hi,
    You can use Screen Variants using T.Code  SHD0 . You can make certain field as display only. You can use the help of your abapers......
    Assign points if found useful
    Regards,
    R.Ramakrishnaraj

  • Baseline date not default in MIRO for Invoices posted against STO Pu.Order

    Hi All,
    Baseline date doesn´t default in MIRO for Invoices posted against an STO Purchase Order.
    We are trying to post an Invoice in MIRO with reference to a STO Purchase Order for planning delivery cost.
    Delivery cost in PO has not got the Vendor number because conditions are customized not possible to process manually so in MIRO the system asks to enter the Invoicing Party and then the baseline date.
    The client requires that when the invoicing party is enter manually in MIRO, the term of payment should be pick up from Vendor Master Record.
    Could someone confirm if this possible ?
    Thanks and regards,
    Laura

    Hi Laura ,
    The payment terms in Invoice are taken from PO only .
    Refer SAP Note : 177224 for more details.
    Regards
    Ramesh Ch

  • How to changes baseline date in miro with Posting date

    Please tell me the procedure to change the baseline date in miro with posting date (EKBE-BUdat) on basis of  Purchase order No (EBELN) .
    I tried it by using user exit :-EXIT_SAPLKONT_011  Enhancement : LMR1M002 but got stuck somewhere .Please tell me how to work on this .

    hey guys my problem is solved by using a badi  " MRM_PAYMENT_TERMS" .In method "PAYMENT_TERMS_SET" writing the code .

  • Inventory posting-default baseline date

    Hi Expert!
    i have opened a forum regarding invoice posting-how to set document date to be as the dafault baseline date in MIRO,FB60,FB65,FV60 and FV65.. I got the path given by prashant "SPRO=>FA=>Accounts Receivable and Accounts Payable=>Business Transactions=>Incoming Invoices/Credit Memos=>Maintain Terms of Payment" but will it affected to all company codes?? I only want to set it up for 2 company codes only.. is it possible to do so?
    Then one more thing is, in the path i can see payment terms 0001, 0002 and 0003 but however they're different than payment terms which are being using currently..K160,K165... where can i check payment terms againts company code?
    Please advise..

    Hi,
    You use the standard terms of payment or customize terms as per your requirement with default baseline date controls.
    These are stored in table V_T052.  You can choose any of these terms as per your requirement.  If you use page up or down
    key, you go to the next page and see other terms or click positiion tab to view K160 or K165.  These terms of payments
    are either assigned during transaction or directly assigned to Vendor Master or Customer Master in Company Code data.
    If you want to see the terms of payment assigned to the vendors/customer in two of these company codes use SE16N
    and view through tables LFB1(vendors) KNB1(Customers).  You cannot make a specific assignment to the company code.
    Regards,
    Sadashivan

  • Difference between Posting Date & Baseline date in MIRO

    HI,
    What is the difference between Posting Date & Baseline date in MIRO?
    Regards
    Chandan
    Edited by: Chandan H N on Dec 14, 2009 11:11 AM

    Dear,
    Posting Date:
    Posting Date in the Document
    Date which is used when entering the document in Financial Accounting or Controlling.
    Use
    The fiscal year and the period for which an update of the accounts specified in the document or cost elements is made, are derived from the posting date.
    When entering documents, the system checks whether the posting date entered is allowed by means of the posting period permitted.
    Note
    The posting date can differ from both the entry date (day of entry into the system) and the document date (day of creation of the original document).
    Baseline Date
    Baseline Date for Due Date Calculation
    Date to which the periods for the cash discount deadline and the due date for net payment refer. This is the case for line items in open item accounts.
    For line items in G/L accounts, the item is due immediately on this date because there are no cash discount specifications.
    Procedure
    During document entry for open item accounts, the date may be defaulted. For this, a terms of payment key must have been specified in the customer's/vendor's master record for which a default value is requested in the document.
    The proposed date can be overwritten.
    If the cash discount rates (and days) have not been entered, the baseline date for payment is the same as the due date.
    Regards
    Utsav

  • Invoice posting - set document date as baseline date

    Hi Expert!
    I have issue regardig invoice posting.
    When invoice posting transactions are done, the baseline date in the transaction is changing due to unknown reasons. The baseline date should not change and should be the document date. This in turn is having effects on the culculation of the due date for the payment terms.
    In this case, i would like to make the document date as the default baseline date and remove the option of changing the baseline date. Please guide me on how to do it step by step.. Please also advise step by step how can i do that in transaction MIRO, FB60, FV60, FB65 and FV65..
    Thanks..

    prashant,
    let say i have 3 company codes but i want to set the document date as the default for baseline date only for 2 company codes, how? If i tick on document date in the path u've given, will it be affected to all of company codes?
    Where can i check for the payment terms against company code? Because payment terms in the path u've given seems like different than what is being using in the PO currently..
    In the path there are 0001, 0002 and 0003 but payment terms which are being using in the PO are K160, K162....
    Please advise..

  • Add the baseline date , posting date and the item text in the Standard Prog

    Have to add some parameters in MRRL transaction Program is RMMR1MRS and apply some calculation part in it.
         The additional fields External PO (EKKO-ZZEXT_PO_NO) and Interface ID (ZZINTERFACE_ID) are added in the ZMRRL and  will be used as the extra selection criterion along with the standard available in the MRRL.
         In the processing option, baseline date (ZFBDT) and posting date (BUDAT) will be added, the default selection for the same is blank.
    Moderator message: "spec dumping", please work yourself first on your requirement.
    Edited by: Thomas Zloch on Oct 3, 2011 11:00 AM

    Hi,
    You need to use substitution with exit (GGB1/ OBBH) to populate the GR date in the baseline date field.
    Also go through the below thread:-
    [Re: Substitution - Baseline Date to be replaced by the Goods Receipt date;
    Regards,
    SDNer

  • MIRO Baseline Date should be same as GRN posting date.

    Dear sir.
    While doing MIRO, the Baseline date should come default date as GRN posting Date. who i can achieve this.
    Because in payment terms, the default baseline date is 1)no default 2)document date3)posting date4)entry date is there.with is it will not come.
    if any user exit or BADI is there Pl send sir.
    regards
    jayareddy

    Hi
    Base Line Date
    Not possible bt std sap.
    Vijay
    Edited by: Vijay on Apr 27, 2009 1:41 PM

  • Baseline date not getting populated from SRM invoices posted to ECC 6.0

    Hi,
    We are currently in ECC 6.0. The SRM system is in 4.0. We have this particular problem that the baseline date is not getting populated from the Invoices posted from the SRM. The baseline date is blank and the document is saved.
    Did anyone face the same problem??? Can you please refer SAP note 541934 and expand........
    Thanks
    Aravind
    Edited by: Aitipamula Aravind on Aug 10, 2009 5:13 AM

    Hello,
    Yes, you could check the attached note 541934 and regard the implementation of the field ZFBDT in the invoicing document.
    Note 541934 provides a solution how to achieve the MM-customizing for payment baseline dates getting effective for invoices with SRM-origin. This note needs to be applied at your ERP-MM-side in the former plug-in-layer. As described in the note, this is a modification. It's recommended to apply in non-productive system first.
    Hope the above infor.are helps for you!
    Best Regards,
    Gladys xing

  • Bapi_acc_document post is not calculating baseline date based pymnt terms

    Hello friends,
    Im using bapi_acc_document_post to post db and cr note and i m passing payment terms in the input file but the bapi is not calculating baseline date .
    pleasee let me knw the solution.
    Regards,
    Sunny

    that's the disadvantage of bapis and direct input in opposite to BDC. So use "old" rfbibl00 with batch input!
    A.

  • Invoice posting-baseline date-uneditable field

    Hi Expert!
    Is there any way to make default baseline date field in MIRO,FB60,FB65,FV60 and FV65 as unchangeable field? I set the document date as the default baseline date but is there any way to make it unchageable for a specific company code only?
    Thanks

    Hi,
    For making the baseline payment date uneditable, use this path :
    Financial Accounting(New) > Financial Accounting Global Settings > Document > Rules for changing documents >
    Document Change Rules line item > choose Account type K + Field Name BSEG-ZFBDT > click copy as and
    in the change view enter your Company Code and remove the tick from the box of possiblity of changing field
    "Field can be changed" and save the entries.
    Regards,
    Sadashivan