Basic dates and production dates

dear all,
i have made a PIR using MD61 for 01.04.2010,
after that, i run the MRP using MD02 to make the planned order, so when i open the MD04 tcode, the planned order has been created for 01.04.2010 too...
the problem is when i convert that planned order to production order, when i check the finish date of the production order, it has been change to 02.04.2010, why the start dates and finish dates changes in the production order???
best regard,
MARUFAT

Hi,
i have check in OPU3, the schduling type is backward, and the automatic scheduling is tick
i also check in MRP view, the scheduling margin key is 000 so there is no float time problem, and the GR processing time is 0,
i run the MRP RUn MD02 using planning type 1 using basic dates
but when i convert the planned order into production order, the finish date always change,
so, if the finish date in the planned order is 01.04.2010 , after i convert into production order, the finish date change into 02.04.2010
what makes me confuse is that the scheduling time is backward, but why all the finish date of the planned order after i convert to production order change into +1 days after the finish dates ??
can you help me to solve this problem?
regard
MARUFAT

Similar Messages

  • Basic dates and production dates in planned order

    Dear all,
    I have a planned order (for material A) which has "order finish date" same as "End of production date".
    I have another planned order (for material B) where "End of production date" is eariler than "order finish date".
    Scheduling margin key is same in both the cases.
    Why they are different? Can you please help?
    Regds.,
    Chaitanya

    Dear
    Please Check in the MRP 2 And SchedMargin key it defines the floats
    SCHEDULING MARGIN KEY
    Takes effect only for Lead Time Scheduling
    Configure scheduling horizon OPU5
    which lead time scheduling and capacity planning should be carried out. scheduling horizon is the period in working days. If a planned order has its basic start date within this period in future, lead time scheduling is carried out using the selected routing.
    The production times are calculated from the float times of the scheduling margin key in the material master record and the time from the individual operations.
    If the planned order has its basic start date further in the future than this scheduling horizon, the basic dates are calculated from the in-house production times in the material master and are transferred to the production times
    with Regards
    Pushpalas

  • MRP run - misalignment for planned order between Date and Production Date

    Hi All,
    We've just integrated SAP for a new plant.
    The MRP runs based on Routing Lead Time for Make materials instead on Material Master Lead Time, for Capacity Assessment purpose.
    When requirements dates lay in the past, MRP performs forward scheduling starting from current date and properly defines Production End Date according to Routing.
    By checking MD04, for the proposed Planned Order, the basic date is same as Current Date (= same as Requirement Date) instead of being same as Production Date.
    It works as it if checks stil the MAterial MAster LEad time instead of Routing. In fact if I updated the LT of MM the MD04 provides the right Date.
    For future requirements, the MRP works properly, by having basic dates (both start and end date) aligned with Production Dates of Planned Order.
    How can I do the alignment w/o updating In House Production LT?
    Thanks,
    D

    Hi Caetano,
    we have already done this configuration in OPU5 but it doesn't provide any benefit.
    Below how we configured it:
    Scheduling level: Via detailed scheduling
    Adjust dates: adjust basic dates, adjust dep. reqmts to operation date
    For capacity scheduling: Always basic dates, dep. reqmts to operation dates
    Scheduling type: Backwards.
    Regards,
    D.

  • Batch management - Shelf life and Production date

    Hi All,
    I am working with batch management where i did all the setting of characterestics, Batch class and neccessary settings. i am working with three characterestics shelf life expiration, production date and last goods reciept.
    I have to active shelf life and production date in Migo screen so that at the time of recieving my characterestics can store data. kindly help in customizing setting
    Thank you in advance
    Majid

    Hi,
    You need to activate shelf life expiration check in T.Code OMJ5 for movement type 101 and also plant.
    This will activates the entry of Shelf Life expiration/Production Date at the time of goods receipt.
    If you are using std. SAP Characteristic (LOBM) for Manufacturing Date,Best Before Date and Goods Receipt Date then the value of this characteristic will updates automatically in Batch ,depends on your goods receipt data.
    Regards,
    Dhaval

  • Basic Start and Finish Date coming as default while Order Creation (IW31)

    Hi Members,
    I am in situation where in i am trying to cretae an order from IW31 but after the order creation basic start and basic finish date is being updated as default date which is the current date of creation.
    I have written my code in Include LCOINFNJ where basic start and basic finish date should get populated as per my written code .After debugging i found that the code is populating the dates in structure CAUFVD-GSTRP(basic start date)  and
    CAUFVD-GLTRP(basic end date) but whill posting at user command  SAVE the fields are getting updated back to default dates.
    Even after adding an enhancement point at the end of below given FM where in i am hardcoding the values still the issue remains the same .
    Function Module : CO_ZV_ORDER_POST is the FM responsible for posting.
    Please help regarding this issue .  
    Thanks and Regards.
    Gaurav Chopra

    Hi ,
          If you do not want start and finish date as current date then u can do it via config
    spro ->pm -->maintenance order processing -->Maintenance and service orders -->general data -->Activate default date for current date as basic date  here for a particular plant remove the tick mark in default current date , thus when u create MO on that plant then u will not get any default dates in basic start date and finish date ...
    regrds
    pushpa

  • Basic Start/Finish Date and Requirment Date in Maintenance Order

    Sir,
    We want to know the link between Order Start/finish date and requirement date in Maintenance Order.
    As we are facing problem during change in dates.
    When we change either start date or finish date in the order, the system automatically change the requirment date as of ondate of all the materials which has been earlier issued and also consider the today date.
    Like in Maintenance Order
    Basic Start Date - 01.04.2009
    Basic End Date  - 31.05.2009
    We have issued materials on the order at different date by putting offset value for the requirement date.
    Now if we increase the Basic End Date of order to n30.062.009 or whatelse, the system automatically changes the requirement dates of all the materials issue based on current date. Suppose we changed the Basic End date on 10.11.2009, the system changes all the requirement dates by calulating offset value from 10.11.2009. However these materials has been issued earlier.
    I want to know if there is any remedy to stop to change the requirement dates automatically.
    With Regards
    Mudit Gupta

    HI
    In general the requirement date will get changed only when the IMG settings in OPU7 permits the requirments dates should be adjusted towards the order basic start and end dates
    kinldy check and adjust as per the requirement
    regards
    thyagarajan

  • Basic start and finish dates vs scheduled start and finish dates in work order

    Hi Friends,
    I have observed  that whenever releasing the work order,irresepective of number of operations in the work order, system generating scheduling start and finish dates are same, however after releasing the Work order and by adding another operation in the work order, immediately scheduling end date equaling to Basic finish date (i.e.: Basic start and finish dates are equal to Schedule start and finish dates).
    Can any body please explain why this is heppening
    Please find the screen shots.
    After adding one more operation in the operation list and save the Work order,then Basic start and finish dates are equal to schedule start and finish dates.
    Regards,
    Srinika

    Srinika
    There are many things that affect the order scheduling:
    IMG setting - scheduling parameters
    Work centre settings
    Operation values e.g. work, duration, operation control key settings
    Calendars
    Etc
    So one possible interpretation of the above data is that the initial order operations have no work assigned, or the operation control keys don't require scheduling, or the work centres arn't set up correctly.
    Then you add a new operation which does appear to work.
    Please supply a screen-shot of the operation tab.
    PeteA

  • Upgrade on SAP Plant Maintenance and Product Data Management

    Hi Gurus,
    I assigned to a upgrade project for Plant Maintenance and Product Data Managemet modules.
    Please guide me what are the steps to follow and provide more information on this ...
    Thanks in advance!!!!!!!!!
    Regds,
    RK

    Hello Kurni,
    In PDM/PLM latest version is PLM 7.0.
    There are many new functionalities available in this version.
    Earlier version can be accessed from SAP GUI, but the latest one can be accessed from Portal/NWBC.
    DMS side many notes have to be applied as you will be instaling EHP4.0 as part of the upgrade.
    ECM side some standard reports are missing in PLM 7.0, which were available in ECC6.0.
    Regards
    Prasad K

  • Point of sales (POS) and Product data management (PDM)

    Hi guys,
    please any one can tell me what is Point of sales (POS) and Product data management (PDM) in SD module and give me structures on this

    As i know it is not supported.
    Oracle supports counter sales order. But if performance is considered invoicing and receipt is slow in Oracle. So this can have workaround...

  • Authorization for Basic dates and Forecast dates

    Hello colleagues,
    My customer requires is to have separate authorizations for using Basic dates and Forecast dates within WBS Element, Network and Milestone.
    Iv'e noticed that the rellevant autorization object to have this separation is C_PROJ_TCD ; field: PSARG ; activity: 111 & 112. However I wonder if this is relevant to all related objects  in the project or only to the Project definition object.
    If the answer is only to PD I will be glad to have an idea how to controll it within the other objects .
    Thanks in advance
    Best Regards,
    Nir
    Edited by: Nir Horvitz on Nov 23, 2010 10:32 AM
    Edited by: Nir Horvitz on Nov 23, 2010 10:41 AM

    It is for all the objects... but you can not control it on basis of only that auth object.
    For network,
    use object :
    C_AFKO_ACT
    and activity 22 Display dates
    for Project def and WBS, use
    C_PROJ_KOK, C_PROJ_PRC, C_PROJ_VNR
    C_PRPS_KOK, C_PRPR_PRC, C_PRPS_VNR
    Regards,
    Amol Sarode

  • What is master data and bussiness data

    Dear all
    I am new guy of crm.
    I have some question.
    What is master data and transaction data.
    What is sold to party,ship to party.
    What is heirar key.
    What is header data and item data.
    Regards
    Amit sahay

    Hi,
    Master Data
    Purpose
    Data about basic objects used in business transactions and stored in the system on a long-term basis.
    This area enables you to store, augment, and consolidate master data, while ensuring consistent distribution to all applications and systems within your IT landscape. By ensuring cross-system data consistency, master data management reduces data maintenance costs, accelerates your business processes, and greatly improves your decision-making processes.
    Business Transaction
    Definition
    Business object in SAP CRM that offers the following possibilities:
    •        Business interaction with a business partner at a given point in time
    •        The result of an interaction (for example, a contract)
    •        The initiation of or request for an interaction (for example, an opportunity)
    •        The preparation (that is, the collection or supplementation of information) for a possible business interaction (for example, an activity)
    •        The product or object or a (potential) interaction (for example, a sales transaction or service process)
    The same interface and processing concept is used for all business transactions. The various components of business transactions are reusable.
    Use
    The business transaction provides business structures and functions that can be used in various processes of a company, for example, in sales, marketing, or service.
    In CRM, business transactions are used in the following areas:
    •        Sales:
    ¡        Sales transactions (sales orders, inquiries and quotations)
    ¡        Opportunities
    ¡        Contracts
    •        Marketing:
    ¡        Lead Management
    •        Service
    ¡        Service Process
    ¡        Complaints
    ¡        Service Confirmation
    •         Activity Management
    ¡        Interactions
    ¡        Task Lists
    Business transactions can be created, displayed, and processed in various channels.
    A sales order can be created in Internet Sales, post processed in CRM Enterprise and then transferred to SAP ECC.
    Structure
    Business transactions are structured as follows:
    The structure of a business activity is based on the answers to three questions:
    Who?
    The participating business partners can be entered at transaction level.
    What?
    The products and services to which the business transaction refers can be entered at item level.
    When / How Much?
    The quantity and the times to be considered can be scheduled at schedule line level.
    This is a basic structure, and can differ for certain business transaction categories. Activities, for example, do not contain items or schedule lines. Sales transactions contain all three levels.
    Similarly to the business transaction, the item category defines the characteristics and attributes of a transaction item, and controls the processing of an item.
    Integration
    Various basic functions are linked with the business transactions and can be triggered from the interface for the business transaction if the relevant Customizing settings have been made. These include, for example, the availability check, pricing and partner determination. You can find more information in the SAP Library under mySAP CRM.
    See also:
    You can find more information on the business transaction in the Implementation Guide (IMG) under Customer Relationship Management ® Transactions ® Basic Settings  ® Define Transaction Types and Define Item Categories.
    Sold to party:'A' sells product to 'B'.Then "B' is the sold to party for 'A'
    Ship To party:A ships(send to ) 'B'.Then  'B' is the ship to party to 'A'(In some scenarious the product can be deliverd eg:'C' then  the the ship to party varies
    Regards,
    Satish Mathala

  • Diff B/W master data and transaction data

    Hi all,
    What is the main Diff B/W master data and transaction data.  give me some example ?
    Thanks in Advance
    Krish...

    hi krish,
    MASTER Data is the data that exists in the organization like employee details, material master, customer master, vendor master etc. These are generally created once.
    Master data are distributed throughout the company, they are often not standardised and often redundant. As a result it is very costly to offer efficient customer service, keep track of supply chains and make strategic decisions. With SAP Master Data Management (SAP MDM) these important business data from across the company can be brought together, harmonised and made accessible to all staff and business partners. As a key component of SAP NetWeaver, SAP MDM ensures data integrity via all IT systems.
    Regardless of the industry, companies often work with different ERP and Legacy systems. The result: the business processes are based on information about customers, partners and products which is displayed in different ways in the systems. If the data are recorded manually, there are more inconsistencies: some data sets are entered several times, others cannot be retrieved by all divisions of the company.
    As corporate applications are becoming increasingly complex and produce ever greater amounts of data, the problem is intensified further. Nevertheless, your employees must work with the inconsistent data and make decisions on this basis. The lack of standardised master data easily leads to wrong decisions, which restrict efficiency and threaten customer satisfaction and profitability.
    In a word: in order to save costs and ensure your company’s success it is necessary to consolidate master data about customers, partners and products, make them available to all employees beyond system boundaries and use attributes valid company-wide for the purpose of description.
    TRASNACTION Data - These are the business documents that you create using the master data - Purchase orders, sales orders etc
    http://help.sap.com/saphelp_nw2004s/helpdata/en/9d/193e4045796913e10000000a1550b0/content.htm
    Regards,
    GNK.

  • Scheduling start date and end dates

    Hello Gurus,
    I am trying to understand the schedule start date and schedule end date functionality in Plant Maintenance. I do understand the basic start and end dates. Currently I set up u201C3.Do not adjust basic dates, dep rqmts to order startu201D and set the scheduling type as u201CForwardsu201D . Please note we donu2019t do any capacity planning or leveling.
    So my question is, why the scheduling start date is defaults to the basic  start date  for forwards and scheduling finish date defaults to basic finish date for backwards ? I tried adding couple of operations and save the work order. It did not change anything in schedule dates.
    Do we really need to care about scheduling dates if we donu2019t use capacity planning ?
    Please advise
    Mahee

    Hi,
    As per priority, final dates would be calculated as we will define the duration based on the priprity. Either current date or basic date only applied to Scheduling start date.
    You can change the scheduling start date so that based on priority, final date would be calculated.
    Regards,
    Maheswaran.

  • Query with Start Date and End Date

    Dear Members,
    I have done a basic query on to get a report on Sales Invoices processed in a given period with the General Ledger account they were posted to. Minor hassle is that to change the dates, I have to go into the script (see extract below) and change dates manually, save query etc.
    Is there a way to have the query, when selected to run, pop up with window, allowing user to input say "start date" and "finish date". I imagine it will require some complex addition to the script below, any assistance will be appreciated.
    Regards
    Raj
    SELECT T1.[DocNum] AS 'Document Number', T1.[DocDate] AS 'Posting Date', T0.[AcctCode] AS 'Account Code', T0.[Dscription] AS 'Item/Service Description', T0.[LineTotal] AS 'Row Total' FROM  [dbo].[INV1] T0  INNER  JOIN [dbo].[OINV] T1  ON  T1.[DocEntry] = T0.[DocEntry]   WHERE T1.[DocDate] > (CONVERT(DATETIME, '20110801', 112) )  AND  T1.[DocDate] < (CONVERT(DATETIME, '20110831', 112) )

    Hi Raj,
    try this:
    /*SELECT FROM [dbo].[OINV] T0*/
    declare  @StartDate as datetime
    /* WHERE */
    set @StartDate = /* T0.DocDate */ '[%0]'
    /*SELECT FROM [dbo].[OINV] T1*/
    declare  @EndDate as datetime
    /* WHERE */
    set @EndDate = /* T0.DocDate */ '[%1]'
    SELECT T1.DocNum AS 'Document Number', T1.DocDate AS 'Posting Date', T0.AcctCode AS 'Account Code', T0.Dscription AS 'Item/Service Description', T0.LineTotal AS 'Row Total'
    FROM dbo.INV1 T0 INNER JOIN dbo.OINV T1 ON T1.DocEntry = T0.DocEntry WHERE T1.DocDate > @StartDate AND T1.DocDate < @EndDate
    Thanks,
    Neetu

  • Split Spry.Data and Spry.Data.Region from SpryData.js?

    I don't like Spry.Data.Region or anything like Spry.*.Region because it make hard to customize using javascript.
    But Spry.Data with Observer / Notify feature is great one. In fact, using SpryData.js, I can write my own "render html object" easier.
    SrpyData.js is big (127KB) even when compressed, it is still 65KB. That why, needed split Spry.Data and Spry.Data.Region from SpryData.js so who want to use Spry.Data only like me will get smaller trafic.
    I've tried remove all Spry.Data.Region content in SpryData.js. Surprise, some in Spry.Data call to Spry.Data.Region >>> Design have problem.
    Anyone can help splitting them?

    Found this in the archives:
    <div spry:if="{ds_RowCount} == 0" class="trigger" style="display:none"></div>
    Basically a hack to point the tooltip to a hidden div so no errors are thrown.

Maybe you are looking for

  • HP deskjet 3050A scan utility won't open with Mac OS 10.8.2

    I downloaded the new software for the HP deskjet printer. Set it up to print wirelessly, which works fine. But the HPScan utility (I seem to have one that says HP Scan and one that says HPScan 3) neither utility can be opened. Message says "check wit

  • Native C++ Custom Exception Not Recognized

    Hi, I'm having a problem with the native part of my code when throwing a custom exception. It is never caught when the exception is thrown in a separate class, it always falls in the generic catch(...) section. I know this problem has something to do

  • Errors in JSP's

    I have used JDeveloper 9.0.4 and 10.1.2 for developing a Web applications and get the following error, when I compile my JSP: Error(1): java.io.UTFDataFormatException: Invalid UTF8 encoding. This is the begining of my JSP, and the errors is marked on

  • Error from log, after rebootDatabase Manager not working

    Ok, lets try this again :- ) I got Ubuntu 8.04, 32bit installed on a DL360 G3, I figured that I can learn how Oracle works, I don't want the Express Version, I need to learn what we will be using at work and not a limited edition. After I re-boot the

  • Opportunity Management

    Hi, Can anyone help me to create SAP CRM OPPORTUNITY using External List Management, I know we can do for LEAD/ACTIVITY. Awaiting your reply. Thanks.