Basic start date and finish date changing in the past

Hello Gurus,
I set the scheduling parameters as " Do not adjust basic dates, dep rqmts to order start " and also assigned the priority to populate the basic finish date. System does calculate the finish date based on the priority and start date as current date but it does allow me to change both dates in past or future which should not happen.
Please do note that I activated the defaulted date as current date as well. Even I removed this mark and did not work.
Please let me know if there is any way to restrcit the changing it alteast in the past.
Mahee

This can be prevented using one the following ways depending upon your needs
---> Set the "start in past" field to appropriate value using transaction OPU7 for order type /Plant combination
---> Make the "Basic start date  and Basic end date" fields as "Display only" through the Field selection config for the order type.
---> Use the user exit on "SAVE" of the order to check for the same
Regards
Narasimhan

Similar Messages

  • Start date is in the past: today scheduling

    Dear all,
    How can I fix that error:
    *Start date is in the past: today scheduling*
    *Message no. C7030*
    Diagnosis
    The start date determined in scheduling is in the past.
    In customizing, you have defined the number of days that the start date is allowed to be in the past.  This number is exceeded.
    System Response
    "Today" scheduling is carried out.
    how can i definea new number of days ???????????

    Open ur project in Planning board then go to "Settings->options"
    and enter number of days in the "Start in past" filed more than difference between todays date and Project Start date. Then Scheduling will consider the Project start date as Scheduling start date. Otherwise system will do "Todays scheduling" and it will reset the Project start date to todays date.
    Venkat

  • Planned order start date is in the past

    Hi Experts,
    I am running MRP with lead time scheduling (2) at my production plant. The planned orders are generated against the requirements but the start date of the planned order is in the past. I have not mentioned anywhere in the configuration allowing the scheduling in past. I cross checked plant parameters, MRP group, settings for determining basic dates & scheduling parameters and every where start in the past check is blank.
    Since the planned order basic dates are calculated based on in house production time in material master, I maintained the lot dependant times in work scheduling view (Set up & processing time with base qty). But system is not considering this in MRP run. But its considering the lot independant inhouse prod time maintained in work scheduling view in MRP.
    Is there any other check to be maintained or system limitations? Your expert view on this please.
    Appreciate an early reply.
    Thanks & Regards
    Prathib

    Check OPU5
    S Anil

  • When I enter a calandar event in i Cloud on my laptop the start and finish times change when  the event shows on my i Phone. What can I do to get the times in sync?

    How can I get the calandar times on my i Phone and i Cloud on my laptop in sync?

    How much do they change by, 1 hour? 1 day?

  • Change document for Maintenance Order Basic Start date

    Hi Gurus,
    I want to trace the changes to MO basic start date. But the change document indicator for MO Basic start date is not enabled.
    Is there anyother option to trace the changes to MO Basic start date??
    Thanks,
    Prabhu.

    Prabhu,
    Not all fields are tracked for changes.
    In the past we have developed some functionality to add these missing fields to the change documents.
    In this case you could utilise IWO10009 (at save event) to save the change documents.
    PeteA

  • Order basic start date.

    Hi,
    We are updating the basic start da of order using FM BAPI_ALM_ORDER_MAINTAIN.
    We are deleting the basic finish date and then updating the basic start date.
    I am observing the following:
    1) For some orders, the basic finish date is recalculated, whille for some it is not, and the basic finish date get deleted and the field becomes blank.
    2) For some orders, the basic start date is updated when the start date is in the past and in some cases, it is not?
    Please explain the reason.

    Hi,
    The following settings are there in OPU7:
    Do not adjust basic dates,dep reqmts to operation dates
    Scheduling type - forward scheduling
    Automatic scheduling is checked
    start in past = 0
    Can you please explain what to check when saving in the FM?
    Regards

  • WO basic start date - requirement date

    Good morning folks,
    Would anyone be able to shed some light on any config that would be suitable for the following:
    The materials are assigned to a task list that is then assigned to a plan.  That plan is then scheduled and the work orders are generated.
    When the materials are added to the work order their requirement date is automatically assigned as the work order basic start date - can this requirement date be pulled from the scheduled dates instead?
    The problem is that the material may not be required at the beginning of the WO, so the defaulted basic start date of the WO would not be the way forward.
    Thanks
    Mantas

    hi Mantas
    you can set in scheduling parameters with following possibilities
    <b>Path Plant maintenance and customer service->Maintenance and service order->scheduling->set scheduling parameter</b>
    1)The basic dates are adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.
    2)The basic dates are not adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.
    3)The basic dates are adjusted and the dependent requirements are scheduled for the order basic start date.
    4)The basic dates are not adjusted and the dependent requirements are scheduled for the order basic start date.
    so when you add the components you have to assign the operations,after selecting the operation you can change the operation date, after you change the operation dates,the material scheduled dates will be changed to the operation date
    (using the option <b>1</b>)
    regards
    thyagarajan

  • Work Order Basic Start Date and Basic Finish Date to be changed

    Hi,
    Currently the business creates work orders without specifying the work resulting which the start and fish dates on work order are same. Also we have automatic scheduling turned off. In spite of this If I am trying to manual modify the basic start and basic finish dates on work order it does not allow me to do so. This issue is seen with work orders which are Released whereas orders with status outstanding have no issues. Could anyone please let me know what could be the reason?
    Thanks,
    Vinay

    Please check whether Scheduling type only capacity requirement is configured.
    If yes, choose this scheduling type in order, you can able to change Basic start date & basic finish date.

  • Basic start date and scheduled finished date...can we have Planned date?

    Is there any "Plan Start Date" in SAP, the date where scheduler must put manually in the system to determine the "committed" date for the work to be executed - based on earliest and latest start date which automatically calculated by SAP?
    Our plant must keep the Basic Finish Date unchanged since it is the Required Date of the Work to finish.  We found that the Plan Date does not change and I was wondering if there is any way we can have the Planned date on the order header or have the basic finish date unchanged?
    Appreciate your advices

    Hi
       As per your query screen variant is the better option to be choose so that here you can go with user id based restriction
    Attaching the complete the scenario
    Transaction and Screen variants with an Example
    http://scn.sap.com/docs/DOC-39667
    Try these document & try to configure if you have any further please revert back.
    Thanks & Regards
    Sandeep Kumar Praharaj

  • Changes in basic start dates and its effects

    Dear All ,
    Greetings!!!!
    Can you please guide me in "changes in basic start dates in Prod Ord".
    Actually,We are now starting to plan order creation as following parameters:
                                                     Schedulling type:- Capacity req only.
                                                     Finish date:- 31st(or last date of that month)
                                                     Start date:- 1st( of that month).
    Is it possible to change the dates now for existing Production orders.
    What will be its effects
    It is a kind request to you,to please guide me and correct me if I am wrong .
    Thanks

    Rahul ,
    yes you can change the date of existing production order , only difference it will make is you need to reschedule it and you may face soem capacity availability problem , as the start date for all the order will be same.
    other then this i dont see any issue in it.
    wait for experts suggestion from the forum.
    Hope it help you
    Regards
    Ritesh

  • Basic start date and basic finish date in the maintenance sub-order

    Hi guys,
    when I create a maintenance sub-order by the transaction IW36 are the Basic start date and the Basic finish date taken,inherited from the principal Maintenance order?And if it is in this way,is there the possibility to put these two dates as a current day only on the  maintenance sub-order ?Thanks in advance...
    Maximilian

    Here is my code
      DATA : lv_date_diff TYPE i.
      lv_date_diff =  caufvd_imp-gltrp - caufvd_imp-gstrp.
      caufvd_exp-gstrp = sy-datum.
      caufvd_exp-gltrp = sy-datum + lv_date_diff.
    This is a 4 year old answered message. Please open a thread for your specific query.
    -Paul
    Moderator
    Edited by: Paul Meehan on Nov 24, 2011 8:42 AM

  • Basic finish date earlier than basic start date while backward scheduling

    I am encountering an issue where in when I am selecting backward scheduling for a process order and I am entering the Basic finish date, afte which system is giving me a Basic startdate which is after the basic finish date.
    For eg:- When i give the basic finish date as 08.12.2011, system is giving me basic start date as 09.12.2011
    I have checked the recipe of the material. In the recipe one major flaw that i found out was that all the activity timings were maintained as 0. But when i created a similar scenario in the testing client, i am not getting the issue.
    Please help.

    Hi,
    Check what is maintawined in number of days the start day is allowed to be in the past in scheduling parameters of the order type, in OPU3. If there is an opening float defined in schedule margin key of the order, and concerning this float backward scheduling finds a start date which falls into past, lead time scheduling will automatically switch to forward scheduling starting from today. 9.12.2011 could have been deducted this way. Also check the factory calendar if days upto 9.12.2011 are defined as working days.
    Regards.

  • INHOUSDE PRODUCTION TIME AND BASIC START DATE

    WHAT IS THE RELATION BETWEEN INHOUSE PRODUCTION TIME AND BASIC START DATES

    Hi,
    Inhouse production Time : This is the field avl in material master, where we provide No. of days required to producce a Product / Assembly. While running MRP if you use the Scheduling as " Basic Scheduling" in MRP parameters system will take the value from Material master and do the backward scheduling and find the Basic Start and Finish dates for a Order. i.e. From the Finsh Date system subtract the Inhouse Prod time and arrive at the Baic Start Date.
    If you select the Lead time scheduling in MRP parameters then system will ignore the Inhouse prod time mentioned in Mat master and consider the Routing Timings for scheduling the Order.
    Hope this will help you.
    Regards
    radhak mk

  • Basic Start Date and Schedule Start date

    Dear All,
    In a Preventive Maintenance order generated through IP30, I am getting Basic Start Date and Schedule Start date as different dates. For all other orders those date as coming same.   I am using forward Scheduling. Can any one of you please tell me what would be the problem?
    Regards,
    Babu R

    [SAP Note on Scheduling - Note 45433|https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=45433]
    Regards,
    Maheswaran.

  • Production order Basic start date calculation

    Hello PP Sapperu2019s,
    I have an production order for total qty - 865,00.This production order created on 11.08.2011 and I could able to see the Basic start date as 26.06.2011.Please let me know how this basic start date gets calculated. I mean what are all the parameters included for calculating this basic start date.
    My Observation:
    I have checked in OPU3 for the respective plant and order type the scheduling type mentioned as Backward.
    SMK u2013 903 (ie, opening period for planned order u2013 3 days)
    In Routing we have two operations.
    Requesting from forum people to give me the detailed calculation part on how this basic start date gets calculated / arrived.
    Please let me know if you need any more inputs.
    Cheers,
    Kumar.S

    Hi Kumar,
                     As per my understanding this is all decided/maintained through scheduling parameters which are defined in Customizing per order type, plant and production scheduler (from the material master) (Customizing for Shop Floor Control, by choosing Operations > Scheduling > Define Scheduling Parameters). In what follows the parameters are described that affect the scheduling of a production order. Further control parameters are described in the course of this section.
    According to your query I suggests ,In Customizing you can specify that an order is rescheduled as soon as it is a certain number of days late (Start in the past indicator). The system then automatically carries out today scheduling when the basic start date of the order is more than the given number of days in the past. This scheduling is a type of forward scheduling starting from todayu2019s date and where the necessary reduction measures are applied .
    Else you can also specify  that a production order is to be rescheduled automatically whenever it is saved (indicator Automatic scheduling). If changes relevant to scheduling are made in the order and this indicator is not set then the order is given the status NTER (dates not current).
    Hope this would be useful for you at some extent.
    Please revert if required .
    Regards
    Chandra

Maybe you are looking for

  • Can't fix a crashed hard drive-impeding circumstances

    I have an early 2008 Macbook pro 15" 2.4ghz (T8300). Now when it attempts to startup I get the white screen with the spinning circle but it stays stalled at this screen indefinitely. While the icon continues spinning theres also a constant clicking s

  • Trimbox: Preflight says it's missing, Acrobat says it's there?

    The Pagesize on my pdf, as Acrobat shows it, is 6.69 x 9.61, and this is the Crop size as well.  The help documents for Acrobat say Trim Size is the same as Crop Size.  However, preflight says the Trimbox or Art box is missing from all pages.  How ca

  • COLLABORATE Call for Speakers Deadline EXTENDED!

    If you are on the fence about speaking at COLLABORATE 10 or missed the deadline, you still can submit your presentation as the deadline has been extended through Oct. 23rd. There has been a good response so far but more speakers are still encouraged

  • Photoshop Touch iOS Crash on Launch

    [ iOS - iPad 4 ] Initially I had no problems. I loved it. Everything functioned as expected. The problem started when I attempted to sync my file with CC! As soon as I choose sync, it crashed. Ever since then, it crashes instantly upon launch now. I

  • Trip schema PL does not exist in the system (T706S)

    Hi Guru's, I have configured Travel Management. When saving Travel request tcode - 'TRIP', it gives an error 'Trip schema PL does not exist in the system (T706S) Message no. PTRA_WEB_INTERFACE036'. I have maintained schema for Variant '40' Indian Acc