Dear Experts ,
I have one typical scenario, in whcich we want copy the batch Characteristics semifinsihed  product to finished product.
( these Characteristics recorded by quality dept for semifinshed products and updated in batch)
Please let me know the solutions.
Regards
Sandeep

Hi Sandeep,
This can be achieved by Use of Batch Derivation Functionality.
Go to t.code DVSP and activate Batch Derivation.
Now ,First Create Sander Condition by usng T.code DVS1,
Assign Material type (Halb) and assign required characteristic for which you want to transfer Batch value to Fert Code.
Then create recipient condition by T.code DVR1.
Assign material Type Fert to it and Characteristic which you have assign in T.code DVS1.
This will work during Production Order or Process Order release.
And for this you have do Batch Determination for Halb in Order itself
Regards,
Dhaval

Similar Messages

  • Copy of Batch characteristics value from material master to Batch

    Hi Gurus,
    I have maintained some values in the characteristics under batch classification in material master and want to copy the values in batch characteristics during batch creation at process order release.
    Can any one help me to achieve this in standard way?
    Thanks
    Sandip

    Hi,
    Try to understand the batch classification functionality...In batch classification characteristic values changes from batch to batch...Values should not be maintained in the material master...it does not have any meaning...in the material master we need to assign only the batch class with class type 023 in classification view ...no need to assign the values there....Batch classification means characteristics values differs from batch to batch...
    Thanks
    Kumar 

  • Changing Batch Management Level from Material to Plant

    Hi all,
    We are investigating changing our batch management level from material to plant to meet business requirements.
    SAP has pointed us to a note with a program to reset the batch level, as well as highlighting some things to look out for.
    I've conducted the change in a playpen system and so far it looks relatively straightforward, with complexities arising only when characteristics exist, or when a batch exists in multiple plants.
    Seems that batch master data is moved from MCH1 to MCHA, including the object link number to classification. Unfortunately it seems a limitation of the conversion is that the batch master data is copied to ONE plant only in MCHA, no doubt due to the fact the object number link to classification must be unique.
    My question is this: has anyone performed this change before, and if so can you offer me any advice on what to look out for, or potential problems that arose after the change?
    Any help or comments are appreciated.
    Mark.

    hi..
    first of all try this simple one...
    You will have to delete all the materials, remove stock and then switch the batch management flag.
    Or
    To convert the batch from plant level to material there is Conversion Program defind by the SAP...
    1. For all releases lower than Release 4.5B, implement the corrections and the modification in the report RM07CHDX as described in the correction instructions.
    2. Create the report ZCHTCUCH, which is specified in the attachment.
    3. Run this report in the clients for which you want to reset batch level to plant level.
    4. Call transaction OMCT.
    5. Check whether the batch level for "Batch unique at plant level" is set.
    6. Implement Notes 821891, 944278, 950540 and 1091613 if you have not already done so (or you have not imported the corresponding Support Package).
    7. Execute the function "Batch Level -> Conversion".
    8. Define a plant for a plant view that may be missing.
    9. Always execute the report in the test mode first. Analyze the error log.
    10. If no errors occur, you can execute the report in production mode.
    11. If you are working with batch long texts, first execute the report ZM07CHDX_TEXT in test mode.
    try this out..hope is works,,
    Thanks..

  • Removal of batch management indicator from material master

    I had removed all batch stock from material code but when trying to remove batch management indicator from material master system is giving the message "batches already exist"
    Please suggest the solution.

    Hi,
       The material is NEW and Batch Managed.  No stocks, orders, batches are existing.
       If the Batch Management indicator is removed in Material Master, is there any way *to see/track the batch/lot * of the product.
    Scenarios: Material is NOT Batch Managed
    1.     How to track a batch received for Purchase order.
    2.     How to track a Batch created in a Production order.
    3.     How to track a Batch in Sales Order.
    Thanks,
    VB

  • How to Remove batch mangement indicator from Material Master

    Hi
    I am trying to remove batch mangement indicator from Material master..but system does not allow
    Before this .. I have done all activities also ...clear open SD documnets ,deliveriy documents ,PO documents ,Process order teco and . reservations and activae deletion flag in  batch  ... and made current period  stock an previous period  stock zero... i have cleard all documnets ...still system does not allow remove indicator..could you please guide in this issue ..how to remove batch indicator.
    Regards
    Sasi

    Hi,
    Please refer the below links.
    Re: untick Batch Manegement Indicator on Material Master
    Remove batch management flag and deletion of material documents
    How to remove Batch Management in the Material
    Re: How to remove Batch Management Check in the Material
    Thanks.

  • Material creating from option COPY FROM MATERIAL thru MM01

    Hi All,
    According to the requirement..I have to create a New Material through "Copy from material"  option given in the MM01, In which it should not accept the already present OLD Material No( BISMT )  i.e. it should generate an error msg to avoid the duplication of BISMT value to the current Mat no created.
    Hope my question makes a clear understandmnt of my problem......
    points will be rewarded.......pls help me ASAP........
    Thanking you,
    Santosh...

    you can put a check in exit - EXIT_SAPLMG02_002.
    the syntax is like this
    SELECT BISMT up to 1 rows
    into  l_bismt
    where bismt = MATNR.
    endselect.
    if sy-subrc eq 0.
    message e000(oo) with 'Material number already exists'.
    endif.
    Hope it solves ur problem.

  • Copying Batch Characteristics Value from Standard SAP Table Field

    Dear Experts,
    1. While creating a user-defined Batch Characteristics 'CREATED_BY' using ct04,  on the Additional Data tab, I filled  the following fields as follows:  Table Name = MCHA,  Field Name =ERNAM.
    'CREATED_BY' was then assigned to a batch Class TRIMMED (of class type 022).
    TRIMMED  was assigned to a batch managed material ADE245DD.     
    After posting co15 (confirmation of production order) for material ADE245DD, the value in table MCHA & field ERNAM is automatically copied into the Batch Characteristics value field of u2018CREATED_BYu2019  for the generated batch.
    2. But I am unable to achieve the same result when I create another Batch Characteristic with similar settings in the Additional Data tab as follows: Table Name = MARC, Field Name = DISPO.
    After doing co15, the value stored in table MARC and field DISPO does not get copied into the Batch Characteristics value.
    Please what do I need to do in Scenario 2 above to achieve the same result as in Scenario1?
    Regards

    Hi,
    Table and field used in additional data table should be related to the object than only it will work, for e.g. MCHA and ERDAT will work if you create a characteristcis and assign it to class type Batch (022/023) because MCHA table has Batch no. as primary key,
    this implies for using material specific table e.g. MARA , you should use characteristics with class type 001 (Material class) , try using with table MARC also
    Cheers
    Dheeraj

  • About the effect for batch level conversion from material to plant level

    Dears,
    Now  we use batch management at material level in our system, now we want to change to batch level from material level to plant level, what effects or risks it will bring during the process of conversion?
    Thanks a lot
    Zhongkai

    Hi
    check the following SAP help link it is very helpful:
    http://help.sap.com/saphelp_40b/helpdata/es/d2/1d4b6e5733d1118b3f0060b03ca329/content.htm
    at the link you can find the following
    Specify batch level and activate status management
    In this IMG activity, you specify the following:
    the level at which batch numbers are unique
    whether batch status management is active in the client
    the plants in which batch status management is active
    the initial status of new batches
    Batch level
    Batch numbers can be unique at the following levels:
    at plant level
    at material level
    at client level for a material
    If you choose plant level, the batch number is unique in conjunction with the respective material and the plant. If you choose material level, the batch number is unique together with the material. At client level, the batch number is unique in the whole client.
    To change the batch level, you have to start a conversion program. This program first checks whether conversion is possible and outputs an error log containing all batch numbers that occur more than once at the new level. Now you need to manually transfer these batch records to numbers within Inventory Management using a transfer posting 'material to material'.
    If you change the level from plant level to a higher level, it is possible that batches with the same batch numbers in different plants are actually identical. In this case, all you have to do is remove stocks (including previous period stocks) so that all batches with the same batch numbers, except one, can be reorganized.
    When you convert from plant level to material level, the material is then to be handled in batches in all plants in which it is defined.
    Standard settings
    In the standard R/3 System, batches are unique at plant level.
    Activities
    To change the batch level, proceed as follows:
          1. Choose the level at which you want your batches to be unique.
          2. Save the new settings and choose Back.
          3. Select function Batch level -> Conversion.
          4. If necessary, carry out the conversion in test mode first.
    Further notes
    Note that you cannot reset conversion from plant level to a higher level in the standard.
    If you create a client by copying an existing client, initially, there are no settings in the target client at batch level. The system makes the settings in the target client only when you have carried out an activity (maintaining master data or posting a goods movement, for example).
    SETTINGS BEFORE/AFTER CLIENT COPY:
    Source client Target client
    Client level Material level
    Material level Material level
    Plant level Plant level
    Batch status management
    Batch status management is an additional function provided by the standard R/3 System.
    Standard settings
    Batch status management is not active in the standard R/3 system.
    Activities
    To activate batch status management, proceed as follows:
          1. Choose Batch status management active.
          2. Save the new setting and choose Back.
          3. Choose Batch status management -> conversion.
          4. If necessary, carry out the conversion in test mode first.
    Further notes
    Batch status management is linked to the batch level. At material and at plant level, the status management settings are valid within the client, that is for all plants. However, if you have defined batches to be unique at plant level, you have to select the plants in which status management is to be active using function Plants with status management.
    If you activate status management, all existing batches are assigned status 'unrestricted'. If you deactivate status management, the systems transfers all restricted batches to unrestricted stock within conversion. Restricted stock only exists if status management is active.
    If you create a client by copying an existing client, status management is automatically activated if batches exist in the target client, independent of the settings in the source client. If no batches exist in the target client, it is not activated. In this case, you have to activate or deactivate status management manually, if required.
    Plants with batch status management
    Activities
    To select the plants in which status management is to be active, proceed as follows:
          1. Set characteristic Batch status management for those plants in which batch status management is to be active.
          2. Save your settings and choose function Back.
          3. Choose function Batch status management -> conversion
          4. If necessary, carry out the conversion in test mode first.
    Initial status of a new batch
    Using this function, you can specify for each material type which initial status new batches are to be assigned. However, if you use a quality management system, this specifies the status of the batches.
    Hope it will help
    Best Regards

  • Net Price - direct copy from material master into purchase order

    When purchase requistions are converted to purchase orders, currently we are maintaining Net Price manually
    before saving the purchase order. Is there a way where the standard price is copied from the material master {Accouting view} into the purchase order directly without manual entry
    If yes, Please advice

    Hi,
    1. Go to SPRO > MM > Purchasing > Authorization Management > Define Function Authorizations for Buyers > Function Authorizations: Purchase Order > Here "New Entries" and define Function Authorization Key as "01" and give description.
    OR use T. Code - OMET
    Here under "General parameters" subscreen, cctivate "Adopt PO Price" indicator and select "Enter conditions"
    In "Possible ref. objects", select "W/o reference" otherwise reference documents (for e.g. PR, RFQ, etc...) for PO creation will become mandatory.
    2. Now go to SU01 > Enter User ID > Parameters Tab > Here for Parameter ID EFB i.e. Function Authorization: Purchase Order, maintain value "01" and check in PO, PR will become mandatory for that user.
    3. Now during creation of PR in ME51N, under "Valuation" Tab, you will get option for PO Price Adoption as Net or Gross. Select as per your requirement and it will copy Price to PO.

  • Picking or copying Characteristics  Value from material master

    Dear Experts,
      Please i create   five Characteristics  which i assign to a Class ( of type 022 ). The Class is then assigned to  materials in the classification View of the Material Master.
    I want  one of the five Characteristics to copy its values from specific parameter value  maintaned in the  Material Master.
    Please assist on how to accomplish this?
    I did the following but did not get the desired results;  While creating this  Characteristic, in the Values Tab, I filled  ''MARC'' in the Tablename field   & in the Fieldname field, i enter the technical fieldname of the particular field from table MARC which i want.
    I want this particular value to be automatically copied into the Characteristics Value field in the Foreground  for eacb batch anytime Goods Receipt is done.
    after doing this, anytime Goods Receipt is done & a batch number generated, it takes me to the Classification screen, but this particular field which i desire  to be auto updated remains blank. 
    Please assist ?

    Hi,
    1. This will not automatically updated just as we wil fill the addtional date table and field.
    2. you need to write the object dependency to get it updated when you call somewhere
    3. Generally in the batch level you will be able to do this .( even you can use function / object dependency )
    Reg
    Dsk

  • Transfer of characteristics values from material variant to its subordinate

    Gurus
    Need your Expert opinion on Variant configuration
    We are using Multi level Material Variants and our bussiness process demands for configuration of These Material variants in Transaction MD81 and during creation of Sales order .These configuration will not affetc the BOM explosion but will only be passed to the The lower level components (Which are again theMulti level Configuriable  Material variants ) as manufacturing instructions .To Enable these Flow of Characterisitcs we have Applied a Note which allows the Multi level Configuration of Material Variants and Pass this Values to lower Level and the characteristics value flow is visible as well for lower level from CU50 ,but when i create the requirement through  CIR or sales order and Configure the Material Variants  and Generate the Procurement Proposals to fullfill these requirements (MD02) in the form of Planned order  we are unable to pass one the Characterisitcs values to planned orders of  lower level Components of Material Variants .These characterisitc values are Used as Manufacturing Instructions and should be passed on to the Lower level of Material Variants through the use of dependencies in Configuration profile .but the problem is it works in CU50 and does not flow in planned orders , does any body have a solution for this ?
    Thanks In Advance
    awaiting reply
    Milind

    Hi Milind,
    I check that you implement a Note which allows the Multi level Configuration of Material Variants? is it sap note? mind to share the number.
    I ever faced this problems to before but fortunately the case in simpler so i just create another variant and maintain the component for the variant. For example : characteristic color. I create variant with color red black etc. For variant red, maintain component red. For variant black maintain component black, so on. Is it possible for your case?
    Regards,
    Arman

  • Automation of batch number copy from RESB to AFPO using COR2/COR5

    Dear exports,
    As subject, I need to copy batch number from RESB-CHARG to AFPO-CHARG AUTOMATICALLY.
    I made enhancement in user exit ZXVBZU02. It works manually when click "create button" under tab "Goods recpt" in transaction COR2 after batch number determination (assign value to RESB-CHARG first).
    For automation, I'd like to do copy by either RELEASE (in COR2 or COR5) or SAVE (in COR2) this process order instead of clicking "create button".
    I found an BAdI WORKORDER_UPDATE, and put break-points in method AT_SAVE, AT_RELEASE, IN_UPDATE. But somehow it's NOT stopped.
    I think I may pick the wrong BADI, or no such solution.
    Your help is most welcome.
    Thanks alot.
    Steven
    Edited by: Steven Zhang on Oct 29, 2008 10:48 AM

    YES, badi is active. Also the break-point was placed in before_update (actually, I prefer at_release). It's bypass all those methods.
    Now I am suspecting whether this is the right BADI. From naming, it looks it is. But as we knew there is a tool (useful report), it can report all enhancements (including user exit and BADI) according to transaction. The badi WORKORDER_UPDATE is not listed in both COR2 and COR5.
    How? pls throw a light on this.:(
    By the way, I'm using ECC6.
    rgds,
    Steven

  • Conversion of Batch from Material to plant level

    Hi
    Each time i try to change the Batch management level from Material to Plant I get the following message:
    This type of conversion is not yet implemented Message no. CZ308

    Please see also the  [thread|Batch Management; and SAP note 891902, especially bullet 4.
    Regards,
    Stefan

  • Batch Classification - copy values

    Hi,
    One of the requirements on the SD side is to print, the Batch class Characteristic values from the Raw MAterial on the Finished good's Invoice. Having performance concerns about reading MB56 for each Invoice line item, I was wondering if there is anyway to copy Batch characteristics values from the RM to the Finished good during Production ORder completion or any such process. All products are Batch managed.
    Would appreciate any inputs from you with similar requirements and your solutioning to it.
    Thks in Advance!

    It is not required that both the materials should have the same characterisitics.
    It completely depends on your requirement and development, of what characterisitics to be copied.
    If you need the total characteristics of the RM to be copied to FG then you should have the Characterisitcs in common.
    What ever the characteristics you want to copy should exist in both the materials.
    Hope this helps you.

  • SAP MM Batch characteristics during Plant to plant stock transfer

    Hello,
    I have a requirement where if i have 100 kg of a batch A in X plant and i transfer 70 kg of this batch A to Y plant. So now i have 70 kg of Batch A in X plant and 30 kg in Y plant.
    I want the batch characteristics of the batch A to be copied in Plant B as well, but when plant B does some quality testing and overwrites a few batch characteritics this should not affect the batch characteritics of the Batch A in plant X. ( We donot want to create a new batch in Plant Y due to traceability reasons)
    We have maintained Batch level at "Plant level" in config
    Any pointers to userexit to force copy the batch characteristics initially from Plant X to Plant Y for Batch A is also welcome.
    Thanks
    Anurag

    Please dont post the same question in multiple forums.  Continue in one thread
    thanks
    G. Lakshmipathi

Maybe you are looking for

  • Can I use the install disk on two computers?

    I haven't actually installed it on my computer yet, I just allowed whatever was going to install itself to come up. If I have another computer, can I use the install disk to put OSX on there or not? If so, can I still use it in case I need a backup l

  • Additional Field in VAT report : s_alr_87012357

    Hi Experts, I wish to add 1 more fields in VAT report s_alr_87012357. Please dont suggest to copy the standard program in Z Program. I am looking for alternate option. Thanks Ganesh

  • MOVED: 「Display driver has stopped working and recovered successfully」

    This topic has been moved to GAMING Notebooks. https://forum-en.msi.com/index.php?topic=250960.0

  • Site Studio Placeholder question...

    Hello all, I was wondering if it's possible to check if a placeholder has a subtemplate, regiontemplate or data file associated to it through idoc... for example, consider the code below: <body> <div id="content"> <!--$wcmPlaceholder("Content_Placeho

  • Partioning of Cube

    hi firends i wand information on the Partition of cube, i have partition on the cube per month wise, but where it is going to show me where i can see the data in the sap according that partition thanks and regards shafeeq ahmed