Batch release of production orders

Dear PP Gurus,
Is there any program / functional module which i can execute in background to release production orders.
I would like to release the production order automatically in background (I do not want to perform custmization setting which relase production orders when created). I would be glad to have a program / logic to perform the same - Thanks!
Regards
Seshu

Thanks for your quick response.
I would like to know if we can run CO05N in background ? I dont want user to execute CO05N.
Do to client business it is not possible to configure SAP system to auto release.
Regards
Seshu

Similar Messages

  • Batch determination in production order

    Hi all,
    Raw materiala are manged in batches and finished products are in serial numbers.
    when I release the production order the batch is not determining automatically.
    can any body expalin the SPRO settings for automatic determination of batch.
    Thanks
    Chindam

    Hi,
    Batch will not determeined at Production order release. only at the time of GR for Produ. order.
    Regards
    sam

  • Automatic Batch Determination   in Production order

    Dear All,
    We are using automatic batch determination is based on FIFO (first Mfg first out) for components..After releasing the order.
    I have maintained Batch Class in all the materials which are used as a all material special Characteristic LOBM_HSDAT as a one of the class characteristic. as we want batch determination  on GR date for few material and for few material LOBM_VFDAT for self life material and its class.
    Then create Sort Rule CU70 mainatained the same LOBM_HSDAT in it. and one with LOBM_VFDAT.
    Then create Batch serch Strategy (USE T.Code COB1- search strategy CO01the respective sort rule and selection critoria.for All ROH HALB and Finish material.
    In Material Master of all component in MRP 2 view select value 3 (Automatic Batch Determination) for BATCH ENTRY. All ROH HALB and Finish material
    After mainting above all prerequisite I should able to do the Automatic Batch Determination as per my selection Rule.
    But Automatic Batch Determination  in Production order after release is not working.
    Please need your help.
    Regards,
    Manish
    Edited by: manish gurnule on Dec 30, 2008 5:26 AM

    Dear,
    Define the batch determination search strategy for process order in COB1 with sort rule in CU70.
    On the initial screen of your application choose Logistics>centrel function>batch management>Batch determination>For process order -->Batch search strategy --> Create.
    On the initial screen of your application choose Batch search strategy -->Create.
    Choose the strategy type, say choose co02
    Choose the key combination-
    Enter the required dat-->say plant ,production order type, product,valid from and component for which you want to have this
    Choose Selection criteria push button. Choose a sort sequence.
    If no values have been entered, enter the selection class and the characteristic values.
    Go back to the screen on which you create a batch search strategy.
    Choose Sort if required(it should be defined earlier(in CU70- here you are giving the charateristic name on which you want to sort)
    For component you need to use MBC1 with search stratgey as ME01 for your plant movement type and material and assign the sort rule and search procedure here.
    Check also in COR4, for the combination of plant and order type...you have selected search procedure-CO0001
    Batch management> Batch serach procedure allocation and check activation
    T.Code to be looked specifically OMCG , CORC
    Hope it will help you.
    Regards,
    Madhu

  • Control availability check during release of production order

    friends,
    Can you guys help me find the user exit/BADI which will allow me to control the release of production order after the availability check is complete.
    In detail, the scenario is that : based on a flag on material master, I should be able to ignore this product's availability during release. I cannot change the availability check to "KP" ( No check) as this product can be sold seperately. So what I thought was that if I get to control the availability check during production order release I would be able to ignore this product before check or may be after check and before the status change.
    I found PPCO0021 exit and function module EXIT_SAPLCOZR_003 which is actually intended for release control for automatic batch determination. I am not sure if I can use this.
    Please let me know if you guys have any idea.
    Thanks
    Prod_Planner

    Let me rephrase the scenario :
    I have a production order for a product P1 which consumes raw materials R1 and R2. R1 is supplied by a nearby vendor every 1 hour to my plant so I do not need to worry about the availability of it when releasing the order but R2 availability should be taken into consideration. So, function 1 or 2 in OPJK will not work (as release need to be stopped if R2 not available) hence I will be using 3. If I use 3, R1 availability is also considered hence the whole order is not released. I will maintain a flag on material master so if R1 has flag, I need to ignore R1's availability but still considering R2.
    As mentioned, I found PPCO---21 which could help me but need your help to understand if there is any other way.
    Thanks
    Prod_Planner

  • Batch no in production order

    Hi Experts,
    when i am releasing a production order (via co02 ) it is generating a batch no as 000000002 how ever i want to generate the batch order as first two digit should be year of the order (ex:11 for 2011) then next two digit will be month (ex: 01 for jan 02 for feb and so  in on.) rest should be as it is. i found a fm CALL FUNCTION 'NUMBER_GET_NEXT' which is generating this batch no as (NEW_CHARG) field can any one help me that what code should i write to generate this format and where should i write it .
    thanks in advance

    let me tell u exact requirement
    After the release of a production order an internally assigned batch number will be assigned to the material being produced. 
    The internally assigned batch number will have u201Clogicu201D incorporated within it.  The logic will be the last two digits of the u201Csystemu201D year (ie:  11), the month in two digits (ie: 01), and a sequential number (ie: 000001).
    The sequential number will change back to 000001 with each month change.
    Examples:     1101000001 (2011, January, sequential number beginning with 1)
              1101000002
              1102000001 (2011, February, sequential number beginning with 1)
    The batch number should be defined as alpha-numeric.

  • Error while release of production order u201CNext period is not openu201D

    Hi Experts,
    Need your opinions on this issue where my client is facing a problem while create and release a production Order on the last day of the month (Last day of period change).
    While create and release of production order for Plant xxxx, system uses to give the error; period Next (e.g. 12) is not open. Same thing if I have created the order using T. code CO01; but when I tried to release and save the order through T. code CO02 then it gave me the same error (Next period is not Open), it checks for the next period to open.
    The above scenario happens only on last day of the month. Earlier this kind of error was not there so the question is why the period check is happening while saving the production order.
    After speaking to the user, it is determined that they are facing this problem since upgrade (Since last 8 month). Hence need to check what additional check has been implemented with upgrade from R/3 4.7 to ECC 6.
    Error Message No F5201
    Appreciate your help how to dig up this issue.
    With Regards
    Anant

    Hi Guys,
    Please throw some light why on the last day of the month (Last day of period change) at the time of release the order user is getting error: Period Next (FI Next period) is not open ( message No. F5201).
    My question is why system carried out period checks at the time of release of Production Order.
    With Regards
    Anant

  • Batch Determination in Production Order Component Overview Screen on the basis of FIFO, Thickness, Grade, width etc.

    I am facing a difficult scenario. Pl. help me out. In my Business Process I am assigning Batches in Production Order Component Overview Screen. Here I am assigning relevant batches to BOM Components manually, My Management want SAP to suggest batches automatically on FIFO basis, thickness, grade, width & first batches should automatically assign to Production order.  Can you pl. tell me how to configure this scenario.
    Or can I pull stock overview screen at Production Order Component screen to assign relevant batch to BOM Components
    Once batches assigned in Production Order component screen cannot be changed. It can be changes by specific persons only.

    Hi,
    Automatic Batch Determination for production order components is possible by configuration.
    You can also refer below discussions to map your scenario.
    Batch determination in production order | SCN
    Automatic Batch Determination in Production order
    Regards,
    Naresh

  • Re:No release of production order without standard cost estimate

    Hello Experts
    I do not want to release any production order without standard cost estimate
    I have come acroos the same problem raised by some other users and can you please suggest how to achieve this?
    Is there any way to achieve this without user exit?
    Thanks and Regards
    Subbu

    Hello Subbu,
    In this case, you need to put the status as "B4" Blocked in costing 1 view of material master, when you create the costing view and change it to "03" status when you released the cost estimate.
    Please note that this field can be overwritten in MRP view also. Hence please get the good control of material master and good coordination with PP team to achive this.
    Please let me know if you require any clarifications.
    Thank you,
    Regards,
    Santosh
    Please reward points if helpful.

  • IDOC on create or release of production order

    Hi All,
    I want to create IDOC on creation or release of production order (CO01), can anyone provide me steps and setting that i need to do to achieve this functionality. Business object used for his is BUS2005, and on release of Production order RELEASED event of object type AFVC_PM  is getting triggered.
    Thanks

    Check below badis.
    AFABD_CHANGE
    CAUFVD_CHANGE
    SIDAT_UPDATE
    Regards,
    Mkhan

  • Multiple batches for a production order and mapping with components

    Hello Gurus,
    Our business requires to create multiple batches for one production order + they want to trace which component in the production order has been issued to the main equipment.
    For example, I am creating production order for 'A' equipment for 4 qty. Business wants to create 4 different batches for these equipment
    Lets say now 4 batches are created A001, A002, A003 and A004.
    Now lets assume 2 nos of 'B' component are required for 1no of 'A' component. So the requirement of B component is 8.
    Lets say 8 batches are generated B001, B002 ......B008
    Now lets say batch B001 and B002 are issued for A001 and packed together. How do we map this?
    I understand we can do some enhancement for creating the multiple batches but I still dont know how to map them with each other.
    Please help

    Hi Ethan
    There is a functionality called WIP batches, that allows you keep the batch traceability within an order.
    With WIO batches you can track which batch of component was used to produce each batch of finished product.
    See this link for more details:
    Work-in-Process (WIP) Batch - SAP Library
    BR
    Caetano

  • Automatic release of production order for perticular work center

    hello,
    any body please help me how to set automatic release of production order when creation for a particular work center. please suggest me.
    Thanks & Regards
    Bhakta

    Dear,
    Use T Code COHVOMRELEASE here select work center as ZPACK then in header menu Program--Schedule in background here define as perodic job and set ferquency as Hr.
    Or Use Transaction SE38 to create  the variants for program PPIO_ENTRY and schedule it through SM36 or use standard variant as SAP&RELEASE.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Query on Batch Determination in Production Order

    Dear Gurus
    I have one query on batch determination in production order against the scenario given below, which need your help .
    We know that it is possible to allocate the same component batch to two concurrent production orders at the same time in SAP.  But as per the business requirement its not possible physically. So business want to update the batch selection logic to exclude the already allocated batch to any open production order.
    In my understanding it cant be done without any enhancement, but require your expert opinion before coming to any conclusion.
    If you have any idea to achieve the solution kindly let me know.
    Thanks

    Dear
    I am not sure whether you can change the Batch SELECTION logic  for concurrent production order .As far as I know batch selection is done on Batch search strategy /sort Rule
    Explore SAP Help : http://help.sap.com/printdocu/corePrint46c/en/data/pdf/LOBM/LOBM.pdf
    Refer this useful thead from expert :Userexit in Batch determination and external number ranges for batches
    Regards
    JH

  • Problem while releasing the production order.

    Hai gurus,
    When i release the production order , SAP doesn't block when i have a deficit of stock for some materails.I checked all the customizing and found every thing is fine.
    As the materials that has defict stock has back flush indicator, is that the reason why the system is assuming the stock when releasing.

    Hi,
    You need to consider the following customization settings
    (1) OPJK - For the Plant/Order type/Availability check-2 for the material availability - Release material - set the indicator '3' No release if parts are missing
    (2) OPJJ - For availability check & checking rule - check what all elements are considered as part of ATP check.
    With these settings - in the production order if the order header has status MSPT - Missing parts (i.e. components are missing) only then system will stop the release of the order.
    I hope this addresses your query
    Warm regards,
    Umesh

  • Exit or Badi: On release of Production Order

    Hi,
    Module PP.
    Q) Say, equipment is under maintanance so it should give warning message while releasing the Production order through CO01.
    Note: it should give message while releasing the Production Order and not when saving it.
    Regards,
    Sujit

    Check below badis.
    AFABD_CHANGE
    CAUFVD_CHANGE
    SIDAT_UPDATE
    Regards,
    Mkhan

  • Error when release the production order

    Hi all,
    while release the production order i am getting the error :-   Plant 1000 is not the only plant assigned to valuation area 1000 , how to resolve this error .
    & can we release the prod order without calculating the cost ?
    Thanks & regards
    satish

    Hello,
    I'm facing the same issue when trying to create a production order using tran. CO01 with inputs (Material:  P-100, Production plant: 1000, Order type: PP01. Next the total quatity of material is chosen freely, Dates/start is set to todays date, Scheduling is set to Forwards scheduling).
    Error message :
    "Plant 1000 is not the only plant assigned to valuation area 1000"
    Message no. CK238
    As explanation SAP says:
    "Diagnosis
    You are attempting to use material costing or order costing. However, the system has determined that plant 1000 is not the only plant assigned to valuation area 1000.
    Costing is only possible when each plant has its own valuation area to which no other plants are assigned.
    System Response
    It is not possible to cost in your system.
    Procedure for System Administration
    Go into Customizing for the Corporate Structure and check the valuation level. The valuation level must be the plant level"
    The error message implies that the user is not given the opportunity to create and save a production order.
    I have secured the followings:
    1. Valuation level is set to Plant level so that the valuation is now done at plant level. (The other option was at Company code level, which is not checked.)
    Question:
    Is there a solution to this problem?
    Thanks and Regards!
    Edited by: WilliamG on Feb 16, 2010 4:04 PM

Maybe you are looking for

  • A list of inputs using netui tags

    Hi all, we have a family of netui problems which occur quite frequently. The main problem is: what to do when we have a list of items (we don't now how many), and we want to display them, and get some input from the user. 1. The simplest form, when t

  • The screen is messed up, how do I get it repaired?

    I have the 60BG Video IPod, and I believe it needs repairs... A small while back, I was raking leaves while listening to music on it. I just turned it off in my pocket, so I didn't notice anything. Sometime during the next day, when I was going to wa

  • Cannot sign into evernote account after 10.1 update

    I just updated to 10.1.0.4189 and can no longer sync remember with Evernote.  The settings app says my password authentication is "expired" but won't allow me to enter a new password.  In the same breath it says my settings do not need to be changed.

  • Using WEBGUI printing Problem encountered

    Dear all, having implemeted the WebGui application server a printing problem in the browser occurs. Suppose that an ABAP-report issues a list consisting of various pages. Once you apply threprint button in the internet browser (Microsoft 6.0) only th

  • The Internet of things and your television

    Almost all the information currently on the Internet is created by humans. Content mainly produced by people. But the Internet of Things (IoT) is about devices connected to the Internet and interacting with other connected things and to a small exten