BI Admin Cockpit process chains fail to install

Hi All,
I'm attempting to install and configure the BI Admin Cockpit on our BI Development system.
I've followed the steps outlined in the collective note, 965386.
When running transaction rstcc_inst_biac to install the Content for the BI Admin Cockpit, the background job RSTCC_ACTIVATE_ADMIN_COCKPIT cancelled with error message RS 062.
Regarding this, instructions from note 1039381 were used to clear table entries and I re-ran the job, this time successfully.
Checking slg1, the logs show no errors and only minor warnings and it can be seen via RSA1 that some Technical Content is in the Activated state.
However, when entering transaction RSPC to schedule the process chains, the screen is blank and it appears that the associated chains have not been installed.
Regarding this, note 1065249 has been checked:
<i>'This note needs to be applied only if SP level of software component BI_CONT is less than SP7 and SAP_BW is greater than or equal to SP13.'</i>
Our system is currently at the required SP levels, BW13 and BI_CONT SP7.
Any ideas on how to install the process chains would be very welcome.
Chris

I was able to install BI Admin Cockpit recently after multiple attempts. All process chains installed properly. There are still some minor issues but in general I was able to see the BI Stats reports. Here is the steps that I did:
System Info: SAP_BW     700     13, BI_CONT     703     5
1. Note 934848: Select only myself system in the TX:RSOR Source System
2. Note 834280: Installing technical BI Content after upgrade
3. Apply OSS note: 1039381, 1065249, 1044792
4. Note 965386: Activate tech content in IMG (SPRO) sequentially from Activate SAPI Data Sources ... to Activate Technical Content. Activating it sequentially will help identify which step is failing.
5. Activate Process Chains using txn RSOR Technical Content (0TCT*).
The process chains were installed but failed to be activated. Whe I double click on a process chain nothing was displayed but edit the process chain anyway and activate manually.
Good luck.
Tony

Similar Messages

  • Using Alert Framework to send email notifications when Process Chain fails

    Hi Everyone,
    I've configured ALRTCATDEF in Solution Manager, selected the alerting option for Process Chains in - RSPC > Attributes > Alerting, but it looks like whenever any process chain fails, an email notification will be sent to the same recipients.
    Is there anyway to have an ALRCATDEF - alert category for different process chains, so that different recipients receive notifications for different Process Chains.
    Thanks,
    Ken

    Interesting....I was actually hoping for different recipients for different process chains.
    E.g. for our
    CRM process chain - Support Team 1
    FI process chain - Support Team 2
    and so on and so on.
    I think the only way may be creating a custom process type and implementing a class for this process type that calls function SALRT_CREATE_API. Then adding this process type to the process chain, with a different variant for each.
    However if anyone knows a way to do this in a SAP standard way using the Alert Framework, that would be great.
    Cheers,
    Ken

  • Sending mail to GROUP ID when a process chain fails.

    Hi All,
    Can one suggest me, how to send a failure/success mail to a Group mial id when a process chain fails.
    I am awere about sending mails to individual mail id's when a any process fails or succed. I want to know the group ID creation part & how to tag the same SOCT.
    Thanks in advance.
    BR,
    Kiron.

    hi,
    The Distribution List/Group_id is created in SO23 transaction.
    hope it is helpful to u
    thanks

  • If Process Chain Fail in Production?

    Hi to all,
    Please can anyone tell me, if there is process chain running in production and any process type fail or process chain fail ?.
    Does we need to repair it, or repeat it or, restart it.
    How to identify what should be done and how to do it.
    I shall be thankful to you for this.
    Regards
    Pavneet Rana

    Hi
      Based on the error occur in process chain step, we have to monitor the error.
    If the error or red color occur when you schdule and check the log view,  then right click the error process step and select display messages, check the error clearly by using process monitor.
      based on the error you have to react.
    this links will helpful to you.
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/502b2998-1017-2d10-1c8a-a57a35d52bc8?QuickLink=index&overridelayout=true
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/00a1f389-ec7c-2c10-04bc-9d81b3084171?QuickLink=index&overridelayout=true
    Edited by: Srikanth.T on Jan 23, 2012 11:29 AM

  • What will u do if process chain fails?

    Hi gurus
    What will u do if process chain fails?
    Thank in advance?
    Raju

    Hi rajaiah
    Firstly if a process chain fails, identify the process that has failed and on the context menu of the failed process you will get an option called display message where you can find the exact reason for the failure. A process chain can fail in many cases. So first try to find the error occured . For example if a process chain has failed due to invalid records then we have to edit the psa and reload the data from psa to data target (reconstruction). Based on the error message you need to take the necessary actions...
    Hope this may help you.. please assign points if found helpful.
    Regards,
    Harish.

  • Send sms when bi process chain failed

    Hi SAP Gurus,
    Is some one inform me how is it possible to send an SMS when a process chain failed ?
    Is there a possibility to paramter something on the SAP BI system to execute this action ?
    Thanks

    Hi,
    I dont think there is an SMS option . But an email can be send when a Process chain gets failed.  The detail step for this is
    1. go to ALRTCATDEF
    2. select classification "Process Chains"
    3. click on display/change
    4. double-click on "error in a process of a process chain"
    5. click on "fixed recipients"
    6. write in your username (you have to maintain your e-mail address in SU01 for that to work)
    7. save
    8. In RSPC, take the required process chain
    9. go into edit mode
    10. from the menu, select Process chain -> attributes -> alerting
    11. check "send alerts if errors occur"
    Regards
    Lekshmi

  • Process chain failed at COLLAPSE PROCESS TYPE ?

    HI all ,
    we have one process chain , in that  we have used oe process type collapse  for the cube .
    it got failed , but in the manage screen , under request status , it is showing tick mark i.e collapse successfully .
    give me some solution..
    regards ,
    Srinivas .

    Hi Venkatesh,
    thank you,  i have resolved this issue.
    i have checked in SM12 and there is no lock on the particular info cube then i repeated the process.
    the process chain failed at the stage of rolling up infocubes and the next triggred process was successfull even though i repeated the process chain.
    my concern is how the next process triggrred and it was successful when rollup process failed.
    can you please explain me
    thanks

  • Process chain failed at  AND process type ?

    hi all .
    Process chain failed at  AND process type ?
    and it is giving  message      Job cancelled after system exception ERROR_MESSAGE     .
    what is the reason & solution .
    regards ,
    srinivas ,

    Hi,
    That depends on the system behaviour... There is no issue in that... You can repeate the process.. If there is no repeat option available then you can on the detail view.. there is a chance that you will get a repeat option there.. If not then copy the chain.. remove the loaded process and add one starter chain an continue the chain in immediate mode...
    Regards
    Sajid khan

  • Process chain failed on creating Indexes

    Hello All,
    Since a few days our process chains have failed because of an impossibility to create Indexes.
    Job BI_PROCESS_INDEX can run for 3 days without any result. Usually it runs during 4 seconds.
    When we stop this job, the next day the process chain fails to delete indexes.
    If we run RSRV for our infocube we get the following error :
    ORACLE: The status of index /BI0/E0PA_C01~040 is INVALID
    Our DBA says it's a BW issue.
    Any idea to solve this issue ?
    Thanks &
    Regards
    Catherine

    If we run RSRV for our infocube we get the following error :
    ORACLE: The status of index /BI0/E0PA_C01~040 is INVALID
    I hope u followed the below to check cube.
    RSRV -> Tests in Transaction RSRV -> All Elementary Tests -> Database -> Database Statistics for an InfoCube and its Aggregates
    In that case, did u execute "Correct Error" (button in toolbar) to fix that error ?
    If that does not fix the issue,
    cannot u delete (button in toolbar) and reschedule Process chain (delete index -> DTP load to Cube -> create index) to create index ??

  • Process chain Failed!!! please help

    Hi All
    Process chain failed at activation of ODS process and the error message is
    Cannot activate request 0000006602(REQU_3YG2WB3F2C48PDD4X4BOW5FYS) of DataStore object
    Activation of M records from DataStore object RC2CTD01 terminated
    Please Help!!!
    Thanks

    I've checked in the monitor screen it's giving me the below error under status tab
    Request still running
    Diagnosis
    No errors found. The current process has probably not finished yet.
    System Response
    The ALE inbox of BI is identical to the ALE outbox of the source system
    or
    the maximum wait time for this request has not yet been exceeded
    or
    the background job has not yet finished in the source system.
    Current status
    All of the packets from the source system arrived
    I've repeated the process and it is asking for seconds...so how much should i give in the second field....
    Please help!!!

  • Process chain failed during DTP

    operation generate could not be carried out for the request no ...
    My process chain failed while DTP . Then i right clicked on it and clicked on display messages then the error is
    operation generate could not be carried out for the request while DTP in process chain
    Please give me the solution

    hi,
    chk if the DTP performs load with info spoke.
    if so chk the source and destination defintion of the infospoke definition.
    Ramesh

  • Process Chain failed at Delete PSA event level

    HI Every one,
    I am monitoring process chains, which are running on daily basis.
    I have one <b>Delete PSA</b> process chain, this chain contains only two events
    1. Start Event 2. Delete from PSA.
    Process chain failed at<i> Deleted from PSA</i> event level.
    Below is the error message I got from the process chain screen.
    "Data inconsistency in /bic/b0000231000 table,partition was not deleted"
    "Delete request REQU_4353ACARKJNY70Z5F11 from PSA 8ZMMOM...."
    Please help me by giving possible reasons for this error message and solution for this problem.
    Thanks  in advance.
    Regards,
    Narayana K.

    hi,
    Are you deleting the PSA requests using abap program?
    Regards,
    Vijay

  • Process Chain Failed at "AND" stage!!!!

    Hi Experts,
    Could any one guide me the steps to rectify the Process chain failure at AND stage???
    Steps:
    1.Start
    2.Data loads(9)
    3.AND(failed here)
    Error message:This AND process is not waiting for event RSPROCESS, parameter 3VW29DJ1PBX67PFJHD5IAEYI1     E

    We encountered a similar error.  Actually it wasn't an error, the process chain just stopped at the AND process and did not continue.  We are on BW 3.5.  I believe there is are OSS Notes for this.  See 1005481 or 1003941.
    If this is not the case, try to reschedule the process chain.  To remove from scheduling:
    1.  select Process Chain -- Remove from Scheduling.
    2.  Activate and Schedule process chain
    We did not install the notes (above) and rescheduling did not work for us.  We ended up changing and tranporting the process chain again and we were fine.
    Hope this helps.

  • One of the APD Process Chains fails.

    Hi All,
    I have created two different process chain (PC1 and PC2 for example)which use program RSAN_PROCESS_EXECUTE  to execute the two diiferent APD (APD1 and APD2 for example) . PC1/PC2 executes APD1/APD2 respectively.Both the process chain have the same trigger event.
    The issues is that only one of the process runs successfully and the other fails at the program RSAN_PROCESS_EXECUTE
    For example if the PC1 runs PC2 fails at the program RSAN_PROCESS_EXECUTE and vice versa.
    The Error message it displays  is
    1) Job started     S     00     516
    2) Step 001 started (program RSPROCESS, variant &0000000155350, user ID ALEREMOTE)      S     00     550
    3) Spool request (number 0000030567) created without immediate output       S     SY     355
    4) Processing completed with errors. See spool list     E     RSAN_PR     22
    5) Job cancelled after system exception ERROR_MESSAGE     A     00     564
    Thanks
    Rajiv

    hi,
    To check the detailed error message for failure of APD, check in RSANWB, goto that APD and click on monitor.
    You will find the spool over there.
    Check the error message and let us know, so that we can try to help you out.
    It can be due to authorization issue or due to low memory.
    Regards
    Lavanya

  • Process chain fails every time at "roll up of aggregates"

    hi all,
    A process is deffined in such a way that...                                        start
                                                                                    i
                                                                                    i
                                                            Delta loads to infocube1(load)  deltaload to infocube2(load)       deltaload to infocube3(load)
                                                                            i                                                 i                                          i
                                                                            i                                                 i                                          i
                                                            delta load of aggregate(cube1)   delta load  of aggregates(cube2)     delta load  of aggregates
    Every time when this process chain get executed,this fails at delta laod of aggregates step.If i repeat again it works fine.But repeating is not a solution for this.So,i want a permanent soltuion for this..
    Please guide me what to do?and explain me why this happens.
    Error message:-process rollup of filled aggregates/bia indexes,variant delta load of aggregates
    Thanks( in advance)
    Moushmi

    Hi Moushmi,
    Have you checked if the system has processes available while the chain is running?  It could be that your system is overloaded and the aggregates wouldn't roll up because you have no processes or available memory.
    Check with your Basis resource.  Also, try changing your chain to do only 1 at a time.  Do you have many aggregates to load, are they big, and most important are they being used.
    Kathleen

Maybe you are looking for

  • HT1937 How to change my questions if I forgot the answers?

    ???

  • Waiting on server problem

    I have an intermittent problem with FTP on CS6 that is widely reported on the Internet. When I try to upload files CS6 hangs with a "waiting on server ..." message.  How do I fix this bug?

  • Hiring someone to update my Mac OS X 10.4.11

    Hello.  I had posted a question earlier regarding updating my computer but I am not computer savvy at all.  Can anyone recommend in the Los Angeles area someone I could hire to come and do it for me?

  • Query - to calculate data for previous year

    Hi forum, I have a requirement to calculate ' Total number of complaints received current month last year / total number of complaints last year)*current year total complaints target.' I have no of complaints as key figure. Any ideas how to do it in