Hi,
I am trying to activate a process chain from BI content . My source system is ERP 6.0. While collecting objects for activating this Process Chain BW gives an errors. It says some of DTP and Transformations are missing. I have put two of the errors are at below.
When i search these missing objects on the BI content these objects are not exist. Also on the BW system they are not exist. I could not find any solution for this problem.
Can you please show me a way for solving this. I am stuck on this.
I am trying to activate following Process Chain.
Technical Name: 0HCM_FULL_P0EMPLOYEE
Name : Load Data for InfoObject 0EMPLOYEE
Error 1:
Shadow object DTP_DYF4USYQ4EYMWILRMUGLXW2KG cannot be expanded; chain is inconsistent
Message No. RSPC142
Diagnosis
You want to determine the objects that are source system-dependent for shadow object DTP_DYF4USYQ4EYMWILRMUGLXW2KG so that they can be inserted in the modified version of the process chain or of a referencing process. This was not possible.
Error 2:
Object DTP_ETKRN0DQM7QVOBZSVBC9J61HB (Data Transfer Process,DTPA) could not be collected for object 0HCM_FULL_P0EMPLOYEE (Process Chain,RSPC)
Message No. RSO296
Diagnosis
You have collected objects in the BW Metadata Repository. Associated objects for the object 0HCM_FULL_P0EMPLOYEE of type Process Chain,RSPC have also been collected. Object DTP_ETKRN0DQM7QVOBZSVBC9J61HB of type Data Transfer Process,DTPA was among these objects. This object
DTP_ETKRN0DQM7QVOBZSVBC9J61HB of type Data Transfer Process,DTPA, is not, however, available in the Metadata Repository.
System Response
Object DTP_ETKRN0DQM7QVOBZSVBC9J61HB of type Data Transfer Process,DTPA is ignored in further collections. The links for object 0HCM_FULL_P0EMPLOYEE of type Process Chain,RSPC are incomplete. This may result in not being able to activate this object.

Hello experts
I am not able to find support package name.
When i click on package level button from SAPM tcode
BI_CONT     703     0000     -     Business Intelligence Content.
Is my BI_CONT add-on installed successfully?
And also i am not able to see BI_CONT in imported packages list.

Similar Messages

  • Short dump while activating process chain

    Please let me know the cause of short dump while activating process chain.. when trying to activate local process chains in metachain it is causing dump

    Can you share more details about error.
    Have you done any changes to local chain? or is this is new chain?
    Try to remove meta chain from schedule, later activate your local chain and meta chain.
    schedule your meta chain.

  • Errror when activating process chain

    Hi All,
    Geeting the error while activing process chains in Quality.
    Error is *'Node Characteristic 0classnum is not entered as hierarchy characteristic for 0material*
    can any one help on this.
    Thanks in Advance.
    Srinivas

    Hi
    This is not advisable to activate a process chain in quality directly. You should do it in development and then transport it across.
    This error is realated to hierarchy. Do you have a hierarchy load attached to this chain?
    Check the hierarcy first. Then activate the chain.
    Cheers
    Chanda

  • Activation Process Chain, Info Objects, Transformations

    Hi Experts;
    Is there any function or abap program, activates inactive Process Chains, Info Objects and Transformations.
    Please Advice
    Regards
    Bilal

    Hello,
    Find below some activation programs used in BI.
    RSDG_CUBE_ACTIVATE      Activation of InfoCubes
    RSDG_DODS_REPAIR      Activation of all ODS Objects with Navigation Attributes
    RSDG_ODSO_ACTIVATE      Activation of all ODS Objects
    RSDG_IOBJ_ACTIVATE      Activation of all InfoObjects
    RSDG_IOBJ_REORG      Repair InfoObjects
    RSDG_MPRO_ACTIVATE      Activating Multiproviders
    RS_COMSTRU_ACTIVATE_ALL      Activate all inactive Communication Structures
    RS_TRANSTRU_ACTIVATE_ALL      Activate Transfer Structure
    RSAU_UPDR_REACTIVATE_ALL      Activate Update Rules
    RRHI_HIERARCHY_ACTIVATE      Activate Hierarchies
    SAP_AGGREGATES_ACTIVATE_FILL      Activating and Filling the Aggregates of an InfoCube
    RS_PERS_ACTIVATE      Activating Personalization in Bex(Inactive are highlighted)
    Programs for activating process chains and Transformations have not been delivered by SAP.
    Regards,
    Pratap Sone
    Edited by: Pratap Sone on Jul 19, 2010 8:39 AM

  • Error while activating process chains from Business Content

    Hi All,
    I am trying to activate the SAP Business Content Process Chains, which load data to 0PM_DSO2 in Plant Maintenance Area -
    1.Delta Upload : MTTR / MTBR   (0PM_DELTA_P02)
    2.Initialisation  :   MTTR / MTBR  (0PM_INIT_P01 )
    And they are failing with the error
    "Object  0PAK_BZJNGI4SYTTJM5DXY8IPMHB0C could not be found in version
    Message no. RS_EXCEPTION280"
    "Message Text
    Object  0PAK_EYQGZ09K9SFFUMOFRQ0730LJ0 could not be found in version
    Technical Data
    Message type__________ E (Error)
    Message class_________ RS_EXCEPTION (Exception Messages)
    Message number________ 280
    Message variable 1____ 
    Message variable 2____ 0PAK_EYQGZ09K9SFFUMOFRQ0730LJ0
    Message variable 3____ 
    Message variable 4____  "
    In the collected objects, these two infopacks are not present also.
    Can you please let me know how to proceed?
    Many Thanks in Advance,
    Vineeth

    Hi
    Make sure these 2LIS_17_I0NOTIF and 2LIS_18_I0NOTIF datasources are being installed.
    Check these links.
    http://help.sap.com/saphelp_nw70/helpdata/EN/e7/082888ca2f994794986448568aec2d/frameset.htm
    http://help.sap.com/saphelp_nw70/helpdata/EN/e7/082888ca2f994794986448568aec2d/frameset.htm
    Chandu.
    Edited by: Chandu on Jan 22, 2009 2:24 PM

  • BI Admin Cockpit - Problem in activating Process Chains

    Hello,
    We're trying to activate the content for BI Admin Cockpit.
    While activating the process chains, we get a "red" message as
    mentioned below.
    "Object '0PAK_5JTN7F5HTP45CGZ04PQTMCNTI' (ISIP) of type 'InfoPackage'
    is not available in version 'D'
    Message no. RSO252"
    OSS message 966131 suggests that "The InfoPackages mentioned are shadow
    InfoPackages and the message is unnecessary because there should not
    have been a search for the package at all." and we should apply the
    correction (as part of SPS10) for this purpose.
    We are currently on SP11 but still having the same issue and hence not
    able to activate the process chains for BI Admin Cockpit.
    Thanks for your help with this.
    Ashish

    Hi Ashish,
                   We had the same issue. You must have one of following:-
    BI_CONT 702, Support pack 7
    or
    BI_CONT 703, Support Pack 4
    Once you get either of above, you will not have that problem. But you might have some problem in process chains because of roll up of aggregate in delta PC. Just ignore that and you will be OK...( This problem is because there is no agg. defined and PC is trying to do roll up..which make no sense and hence there is error)
    Also refer to OSS note 965386
    This is my first answer to SDN...so assign my first points..:)
    Thanks,
    Anil

  • Error while activating Process Chains

    Hi all,
    while activating the Process Chains, i am getting the following error "Job BI_PROCESS_PSAPROCESS could not be scheduled. Termination with returncode 8"
    when i double click on the error msg, i got the following help msg: "
    <i>Message no. RSPC065
    Diagnosis
    Program RSPROCESS is to be scheduled as job BI_PROCESS_PSAPROCESS under user ALEREMOTE.</i>
    Can any one please show some way to solve this problem? please do this favor, i have been suffering with error for a long time.
    Points will be given
    Thanks
    Ganesh

    Hi,
    Just analyze the error message that you get while activating the PC, don't give any server name.If you are trying to run process chain using Flat file, it won't work,
    and you should have source system R/3 or you have own datasources in BW system itself at that toime you can use PC to extract data. If your source system is Flat ile, it won't work. other wise you should place your flat file in application server, using AL11 tcode.
    <b>OSS : 511475</b>
    <b>Symptom</b>
    You cannot schedule or perform any batch jobs with the BW or source system background user.
    The error RSPC 065 occurs in the process chains:"Job could not be scheduled, termination with return code 8"
    <b>Other terms</b>
    RSPC065
    <b>Reason and Prerequisites</b>
    The user type is
    "CPIC" up to 4.6B
    "Communication" as of 4.6C
    This user type may not execute or start any batch jobs, irrespective of the user authorizations.
    <b>Solution</b>
    Set the type of background user to
    "Background" up to 4.6B
    "System" as of 4.6C
    This user type corresponds to the "Communication" type and may also perform background functions.
    Through the Customizing, the BW user is automatically created by mistake as a communication user.Depending on your BW system release, you can solve this problem as follows:
    BW 2.0B
               Import Support Package 24 for 2.0B (BW2.0B patch24 or SAPKW20B24) into your BW system. The Support Package is available once note 456551 with the short text "SAPBWNews BW 2.0B Support Package 24", which describes this Support Package in more detail, has been released for customers.
    BW 2.1C
               Import Support Package 16 for 2.1C (BW2.1C patch16 or SAPKW21C16) into your BW system. The Support Package is available once note 456566 with the short text "SAPBWNews BW 2.1C Support Package 16" has been released for customers.
    BW 3.0A
               Import Support Package 8 for 3.0A (BW3.0A patch08 or SAPKW30A08) into your BW system. The Support Package is available once note 452632 with the short text "SAPBWNews BW 3.0A Support Package 08" has been released for customers.
    <b></b>

  • Activating Process Chains in QA System

    Hi All,
      i have transported objects from DEV to QA. all the objects in the QA are in active state but the process chains are not activated and they are in grey state. how to activate the process chains manually. are there any pre defined programs to activate the process chains.
    Regards

    Hi,
    try to do the following..
    Got to RSPC and there select ur chain by double clicking it, next go to the menu PROCESS and there u have option called check and activate . So this option will first try to check the consistency of ur chain and then if no problem exists it will activate it.. and in case if prob does exists it will highlight the process where it encountered teh errors..
    Hope this helps..
    Regards,
    Pankaj

  • Problem in activating Process chain in Quality after transport

    Hi All,
    We have moved a set of process chain to Quality system.
    When tried to activate the Process chain it is showing error in DTP.
    The DTP name is same as in the Dev system.
    So, we tried moving the DTP alone in another transport request.
    Still the error exists. We also tried moving the process chain again.
    We had tried importing only the structure and also the entire flow again.
    Nothing worked.
    Please suggest some solution.
    Thanks in Advance,
    Geetha

    Thanks for yor reply.
    Suman,
    I have checked the Object Changeablity now in Dev system, I found it like Not changable for DTPA.
    The DTP from DSO to Cube is fine, but we have problem with the DTP from DataSource to DSO.
    Also, in the dev system when i clicked on Object Changeablity I get a popup like "System can be changed; settings not necessary".
    Please suggest me like what must be done.
    Prashantk & Arvind,
    We imported the Process Chain along with the DTP first and we faced the problem.
    So we imported the DTP alone again, but still we had the problem.
    Again we imported the Process Chain after importing the DTPs.
    So what i feel is DTPs must be there in the Quality, but why we have the problem persisting.
    That too only for DTP from Data Source to DSO but not for the DTP from DSO to Cube.
    Regards,
    Geetha
    Edited by: Geetha Devi Ramalingam on Jul 12, 2011 9:43 AM

  • Activating Process chain with Yellow message about index recreation

    Hi SDN Community
    As part of a Process Chain which loads data into an infocube,
    If an index recreation is not included in the process chain, we get the following warning message:
    A type "Generate Index" process has to follow process "Execute InfoPackage" var.ZPAK_4CFH2W389QSOOUU1UVP8PBLFU in the chain     
    As we do not want to have the index recreation in this particular chain, and rather, another chain,
    will there be any issue of having this process chain in this warning message mode without an index recreation.
    Thank you.
    Simon

    Index recreation is not mandated because you have the option to either create it or not. Recreating/rebuilding your index improves read time and so it is recommended. If you are creating the index at a subsequent step you can confidently ignore the warning message.
    Regards,

  • Activating Process Chains

    How do we activate a meta chian,
    we have main chain A and a local to it B and C
    if i made a change in B, activating and scheduling A does not effect the changes made in B.
    If i activate and schedule B then it might run; am i right.
    So how would i go about activating and scheduling the whole chain including the local chains.
    THANKYOU THANKYOU THANKYOU

    Hi.......
    A local chain is always schedule as immediate run............So after making the Changes in Local chain..........Activate it.........and also keep the scheduling option as immediate only..............no need to scheduke it seperately..........when it is a part of a meta chain..............why u will take an immedite run for that.............then Just deschedule the Meta chain............and then again Schedule it back........
    Regards,
    Debjani..........

  • New Process Chain Activation

    When a new process is transported to qa or prod it has to be MANUALLY activated one time before the NEW: prefix is removed and the chain can be used by a meta chain.
    Is there a configuration setting or some way to have the chain AUTOMATICALLY activated when it is transported to qa or prod?
    Thanks,
    Mike S.

    Hi Mike,
    Welcome to SDN!!
    You would need to do that to enable the schedule the process chain. I did notice an OSS Note or some document which stated the settings usinh which we can avoid this. I dont have access to my documents now. Would search and post.
    Meanwhile all the posts discussed here talk about manual activation:
    Process chain scheduling in QA
    Process Chain Status is new after transport to QA
    Also chek this blog:/people/sap.user72/blog/2005/09/05/sap-bw-and-business-content-datasources-in-pursuit-of-the-origins
    Bye
    Dinesh

  • Error in process chain activation

    HI
    I am learning on 3.0b,(on my pc) while using process chains, at the time of activating the process chain it is giving the following error "JOB BI_PROCESS_PSAPROCESS COULD NOT BE SCHEDULED, TERMINATION WITH RETURN CODE 8". Why am getting this error, is there anything wrong with my system or software or there any mistake in activating process chain" (what ever may be the process type i use, i am getting this error), plz help me.
    thanks

    Hi Ganesh,
    The possible reason for that error is the User type of the background user. Please check out OSS note 511475 which talks about this problem and possible solution. I have used this earlier.
    You can see this for info on how to make the change:
    /message/685940#685940 [original link is broken]
    Hope this helps...

  • Why process chain activation is taking more time?

    Hi BW Gurus,
    I am going to activate the process chain, but it takes more time to activate the process chain . What may be the reasons ?
    Regards,
    Raju

    Hi,
    Process chain activation becomes slow due to the following reasons.
    1)Large no of entities in RSPCCHAIN Table i.e, there is  lot of process chains and very large process chains.
    2)There is a missing index for the RSPCCHAIN Table.
    Solution for this problem is  we have to create an index for the following fields of the RSPCCHAIN table.
    EVENT_GREEN
    EVENT_PGREEN
    EVENT_RED
    EVENT_PRED
    Still  if you want further clarification on this , Refer the following sap notes.
    906512---Activating process chain is very slow.
    Related Notes: 872275, 872273& 872271 .
    Regards,
    Chendrasekhar

  • BI Admin Cockpit: Program variant missing in Process chain

    Hi,
    I'm installing BI Admin Cockpit and have troubles with Process chains. I followed the installatin guide and had problems activating process chains: 0TCT_C2_INIT_P01 and 0TCT_MD_C_FULL_P01 because of missing InfoPackages. I solved this by installing an correction as it is described by Note: 1432353. After this I activate these Process chains manually in RSA1 Administration--> BI Content -->Process Chains (all necessary objects). No Problems occured. The Problem is when I'm start these Process chains, I get an error on the last step. There is an Abap Programm with an variant. This variant is missing in the System.
    The Variants are:
    - RSTCC_Dataload (0TCT_C2_INIT_P01)
    - RSTCC_QRuntime (0TCT_MD_C_FULL_P01)
    I tried also to get these Process chains with Dataflow before and after to view if I forgot anything to activate, but there is no programm variant. Can anybody explain, how to get these programm variants?
    Thanks and greetings,
    Sebastian

    Sebastian,
    I faced the same problem. Basically what I found was that variants were not defined. So I manually created the value for variants:
    1. For RSTCC_DATALOAD assign value  TCT_C2_DELTA_P01
    2. For RSTCC_QRUNTIME  assign value   0TCT_C0_DELTA_P01
    Our system info is similar to what you have and I in fact had Basis team patch BI Cont to level 6 but this did not help. If I were to take a guess i would have to say that these variants are missing in the 7.01 BI version, you can either choose to create a OSS message with SAP and wait for them to fix it or you could fix it manually.

Maybe you are looking for

  • Video in pdf does not work in Windows

    Hi, I created a interactive pdf in InDesign CS6. I tried embedded a flv., a mp4 and .mov into the file. Looks great on my mac. When I send it to a colleague who has all the latest software in windows, she can not view the video. She gets an error mes

  • Viewing Pictures inserted into Eudora from iPhoto '08

    I tried inserting (NOT attaching), by dragging-and-dropping, a photo I'd exported from iPhoto '08 into the text of an e-mail I was composing on Eudora v. 6.2.4. Cc's of the message to Hotmail and Yahoo addresses displayed the picture correctly, but a

  • Ipod is disabled connect to itunes

    hello!! my ipod is disabled and it says connect to itunes..i have followed many steps recommended by the community and now it shows coonct to itunes..but itunes doesn't show my ipod not even computer recognizes it..plz tell me how can i solve this pr

  • Macbook using Moshi HDMI Adaptor

    i have a macbook, wanting to connect to tv by way of the HDMI adaptor from Moshi, the pack says audio/video adaptor for macbook .... video works fine but no audio? any suggestions?

  • Error Message: F5413

    HI all, User query: for GL212004, if matching of open line items uses assignment, he'll hit the error message: F5413 again.  Can this be turned off?  Any effect on other company codes? regards JK