Billing for Project Systems without using Sales Orders

Hello All,
We are using project systems in our project and we are not creating any sales orders for the same, however I am creating delivery using t-code CNSO and hence the outbound delivery is getting created, my question is can I create a billing document for this delivery and if yes how can I create the same.
Kind Regards
Atul

Hi,
Yes you can create billing document for this delivery
Make sure following pre requsites
In VOFA for your billing type assign document pricing procedure under account assignment/pricing tab
In XD02 for customer under sales area data >> Billing assign customer pricing procedure
And last in OVKK in combination of
sales organization + distribution channel + division + document pricing procedure + customer pricing procedure = Price procedure
kapil

Similar Messages

  • Can we combine Query for cancelled requisitions and query for internal requisitions without internal sales order into a single query

    Hi All,
    Greetings.
    I have two queries namely,
    1.Query for cancelled requisitions and
    2.Query for Internal Requisitions without Internal Sales Orders.
    I was on a task to combine those two queries..
    Can we do that? if so, please help me do that..
    Thanks in Advance,
    Bhaskar.

    Hi All,
    Greetings.
    I have two queries namely,
    1.Query for cancelled requisitions and
    2.Query for Internal Requisitions without Internal Sales Orders.
    I was on a task to combine those two queries..
    Can we do that? if so, please help me do that..
    Thanks in Advance,
    Bhaskar.

  • Order related billing for Partial Qty item in sales order

    Hi SD Gurus,
    In case of delivery-related billing we can create a bill for partial qty or item by creating delivery(against order) for partial qty/item. Is it possible to create order-related bill for the partial qty or item ?
    Any suggestion on the subject is appreciated.
    Thanks in advance,
    Velmurugan

    HI Velmurugan,
    This can be solved through by doing an order related billing,
    First check weather copy control setting is there for order to billing.
    In item category check for billing relevance. Make it has order related billing.
    Now do order related billing for partial quantity.
    Regards,
    Nagesh

  • PS Project description when creating sales order using BAPI

    I am trying to create sales orders using BAPI_SALESORDER_CREATE_FROMDAT2.
    Because of the material configuration in table TCN61 the material will trigger a project creation in the project system.
    Now, in order to create a project, we must provide the project description.
    I would like to ask you if anyone knows how to pass the project description in one of the BAPI parameters.
    Thank you for your help.

    Thank you Sreedhar for the answer.
    I tried the CAMPAIGN field but did not work...
    In fact, I am not able to find a field, in any of the of the tables, that could hold the project description (PROJ-POST1).
    An entry is created in PROJ table when we manually create a sales order for materials specified in table TCN61.
    Thanks.

  • BTE's used for project systems master data.

    Hi ,
    Can anyone tell me what are the BTE's used for project systems master data.
    Tcode used are CJ01,  Cj02,  CJ20N,  CJ12,  CNMASS
    When master data is changed or created BTE should trigger.
    Regards
    Subin

    I don't think there are any open_fi BTE available for PS master data.
    you can use classic subs/vals using GGB0 and GGB1 transaction codes.

  • Which Smartform is used for output of a (confirmation) sales order ( in tra

    Where in customizing I can see which Smartform is used for output of a (confirmation) sales order ( in transaction VA02/VA03) and which print program.
    If the mechanism is different please let me know
    Thx in advance(right answers will be rewarded)

    Hi Tina,
    This is very simple.
    You can go to transaction NACE
    Now click on Output Types, here against your output type you can see what is the smart form attached in the field processing requirements.
    If its order confirmation, it would either be standard BA00 or a copy of that, maybe the naming convention would help you.
    Also If you click on the extreme left hand button in NACE, you can see against your output type what are the records maintained, and under communication tab, you could get to see the printer setting.
    Hope this solves your query.
    Reward suitably if helpful.
    Regards
    Ravi

  • Issue regarding condition pricing date as system date for some condition types in sales order

    Hi
    I have already created a sales order on 30.04.2014. Today I am adding new line item to sales order in VA02 transaction. in this order new line items condition pricing date for conditions JEX2,JECX should show as 12.06.2014. But currently it is showing as 30.04.2014. I need condition pricing date as system date for above conditions.
    Regards
    prashant

    Hi
    When I am changing pricing date VBKD-PRSDT in sales order header . It is changing the condition pricing date for all. Sales order is created on 04.06.2014. I have added line item 150 on 14.06.2014.
    After adding line item 150 , there I have changed the pricing date as 14.06.2014. in sales A tab of item 150. But still it is taking from Sales order header date as 04.06.2014 for all conditions. But my requirement is for line item it should take as system date for some conditions like JEX2,JECX& JA1Y but for other conditions it will take as Order creation date. Please suggest. I have also attached screen shot below. please go through it.
    Regards
    PK
    Sales order header change mode VA02
    Here pricing date VBKD-PRSDT = 04.06.2016
    Item change mode
    I have added new line item 150 on 14.06.2014
    Changed the condition pricing date to 14.06.2014 & saved
    After saving I have gone to Va02 screen of line item 150
    & there I have gone to condition pricing date field from item condition tab
    for JEX2 condition type but still here condition pricing date is showing as
    04.06.2014 as below.
    Condition pricing date
    My requirement is like this
    For some particular conditions like JEX2  condition pricing date will take as system
    date instead sales order creation date when I will add a new item 150 on
    14.06.2014.but for other conditions it will show as order creation date for the
    same line item 150 .

  • Report Painter Drilldown on Cost Element for Project Systems

    I am currently working on a report for Project Systems. I am trying to copy the functionality of the Internal Order summary (60I2-001) into report group 6P3. I was able to copy the whole layout and also the values of 6oI2-001 into a copy of 6PP4-001 but when I double click on "Balance" it is bringin up the ALV report that 6PP4-001 is using. I would like to call another report which looks like 6LS0-001 but contains Project System info made in report painter when I double click on Balance. Is this possible? Please let me know how.

    Hi Avinash,
    See my replies below.
    1 a & B: You are planning Qty on NWA and capturing costs - labor & Equipment on NWA elements.
    When  you are having elaborated to NWA-Element level, split your total work on each NWA-element and post labor cost. Thus you will have planned Vs actual costs at one place.
    coming to equipment cost - are you capturing using PO through GR?.
    2.a : Option1- create a separate WBS elements for materials and plan cost at WBS level. That value would be your total planned cost of material procurement as estimated. Under this WBS elements create NWAs and assign the materials. With this set up you can assign material and procure so that will have actual costs coming from GR.
    Option 2: Create a one General Cost activity and assign the total planned cost of material on this NWA.
    When you assign the material components, diligently you have to reduce the equivalent amount from the general costs activity. Also note that on component screen, you have to check box "Cost relevant" so that material cost will add to Cost NWA. Let the different materials  have their own valuation class and have default CEs accordingly. that would not be big issue.
    Please discuss with your MM team to get more information. Also my suggestion is to leave blank CE field in configuration.
    The option2 is very cumbersome and high risk but one have to be very cautious to reduce the value from Cost NWA in order to sustain the planned material costs whenever they added.
    3. I have answered the relevance of Cost relevance check box in above.
    Hope above makes sense.
    Thanks,
    Sudhakar

  • Can we create two POs for the same 3rd party Sales Order?

    Hi MM experts,
    Issue: Can we create two POs for the same 3rd party Sales Order
    In Third party purchase process, first sales order created with a spl. item category  and it creates the PR automatically with the Sales order material and Qty and this PR converted PO.
    They got a pur.req. for sale order on same item for same delevery date. They did not get any warning msg. saying that a PO was prviously placed against this sale order.
    How it is possible that we were able to place another PO? concern is that second PO was palced against SO which was already used & completed. they were able to place 2 POs for the same customer same delevery date. How it is possible?
    If anyone face the same issue, please let me know if you have any answer to this questions.
    Thanks in advance.
    Suresh.

    Suresh,
    It is hard for me to give you a definitive answer since you have created a customized solution.
    How it is possible that we were able to place another PO? concern is that second PO was palced against SO which was already used & completed. they were able to place 2 POs for the same customer same delevery date. How it is possible?
    Normally, the system will not do this.  A third party PR or PO will be 'account assigned' to the Sales order.  SAP standard 3rd party will not create additional purchase reqs unless there has been manual intervention.  Try searching for changes in the Sales order and changes in the original purchase order.  They may give you a clue.
    I believe the normal Item category for third party SO is TAS (I am working from memory here, I am not in front of a system).  I don't know what ZTAG does.  I confess I am not an SD expert.  You might also want to post your question in an SD forum.
    You mention two custom applications, ZMMPLAN and ZSTPMP.  These somehow have functionality that is used to help you convert your PRs to POs.  If I were in your position, I believe I would also look at these applications for clues to how they might be contributing to your problem.  And please don't send me details about these apps.  I will not comment on custom code in this forum.
    Sorry I can't be of more help.
    Rgds,
    DB49

  • Controlling Config for Project System

    Hai,
    I have Scenario where in project is triggered when sales order is created using a planning startagy 85(Assembly processing with network/project). for this scenario can anyone guide what are all configuration settings to be done in the controlling module for the project settlement.
    govind.

    hello,
    u r talking about MRP run ie make to order when sales order is created then process starts with production order which is to be converted to plan order by using t.code md02 and md04.
    At each stage u have to maintain actual data and plan data.
    u need to configure controlling related to production run process.
    hope this may helpful to u.

  • Planning Profile for Project System

    Dear All,
    In planning Profile (T Code OPSB) for Project System we can find  RElem.f.billing plan ..field, in this field which cost element we have to assign wheather it is sales revenue or secondary cost element cat.31 or else..plz adives me..
    Thanks and regards

    Mr. Sridhar,
    Thanks for ur reply, here my querry is, i have types of sales revenues like domestic, export, industrial etc.. there is only option is there to maintain revenue cost element, so which revenue cost element i have to maintain in planning profile.
    Regards
    Ramesh

  • How to run MRP for Bulk Material without using LTP

    Hi, how can I run MRP for BULK material without using LTP.
    Thanks in advance
    BK

    Hi,
    Use trasnsaction code OPPQ and goto BOM Explosion and selection depends on
    Field selected
    No dependent requirements are created for informational purposes for bulk material items in the plant selected. This can improve system performance.
    Field not selected
    Dependent requirements are created for bulk material items in the plant selected. These dependent requirements are displayed in the planned order for informational purposes only. They are not considered in the net requirements calculation; that is, they are not included in material requirements planning (MRP) and are not displayed in the stock/requirements list
    Reg,
    Deepak.
    Edited by: deepak k b on Nov 11, 2008 6:56 AM

  • To generate planned orders throught MRP even without forecast/sales orders

    Goor morning, we should send long term plan forecast to the suppliers, but in the system we're able to see just few weeks demand (lng term horizon is not still implemented). Do you think is possible to generate some planned order as MTS policy (based on the past consumption), even without any sales order or forecast inside the system? Tks in advance

    1) create a Plan IN MD61 with inactive version select the period as you want & enter  W- week in initial screen
    2) create a plan In MS31 and assign the created in active version plan in MS32 assign the plant and activate  independent requirement
    3) Run MRP in MS01, system will create a plan order for LTP
    4) and do the evaluation for created plan order in MS38.

  • Order related billing for third party. Third party order..

    Hi
    While we are running batch job for billing system is throwing below error.
    Order related billing for third party. Third party order..

    Dear Nortel,
    Can you Please check whether, during the item category configuration for TAS (T. Code: VOV7);  you have marked relevant for billing indicator as F?
    Also, maintained the copy control (T. Code: VTFA) between OR => IVA (for TAS) as follows:
    Copying requirement = '013',
    Invoiced quantity = 'F', (*)
    Quantity/value = '+',
    Pricing type = 'G'.
    Best Regards,
    Amit
    Note: I would recommend you to Please go-through following document in full, atleast fo once. This will definitely help you to review your settings for Third Party Order Process Customization.
    [Third Party Process|http://yasosap.wordpress.com/2008/10/22/third-party-scenario/]

  • Pricing Schema for Project System

    Dear Sappers,
    I'm configuring Pricing Schema for Project System(PS) module.
    The requirement is, the schema will be in such a way that it supports both excise, CST, VAT and service tax.
    In PS module the user raises a Purchase Order having procurement of material as well as taking service from Vendor.For this in PO he will maintain both material as well as service.
    I'm configuring the Pricing schema in MM - Purchasing - Condition.
    My question is for materials procurement, everything is working fine.But for service respect to activity number I want to maintain service tax and other cess in condition record.
    But to maintain service tax & other cess for activity number, I want the access sequence of sevice to be in Purchasing.I've taken the standard table for Plant, Vendor, Purchase Organinzation and activity number combination from External Service management and making a new access sequence in MM - Purchasing.All fields are coming but for Activity number, it not taking the document structure and showing error.
    How to overcome this??
    Any suggestions will be highly appreciated.
    Warm Regards
    PKB

    Hi Pankaj,
    Thanks for your suggestions.
    As per you reply, the access sequence is already maintain in External Service Management.But I want to bring the same combination Plant, Vendor, Purchase Organizartion and Activity number that is Table 97 to MM - Purchasing - Conditions- Access Sequence.
    I've tried to do it, but when I'm creating in MM - Purchasing, all document structure is copying except activity number.What I analyse the error is due to application area.Activity number is MS (External Service Management) area but i'm trying to do in M(Purchasing)
    Even though when I enter manually MS for the access sequence system is not taking.
    Suggest me.
    Warm Regards
    PKB
    Edited by: Pranaya Barik on Dec 11, 2009 12:09 PM

Maybe you are looking for